Lane Wilson Company, Inc. v. Gregory

322 So. 2d 369, 1975 La. App. LEXIS 3388
CourtLouisiana Court of Appeal
DecidedNovember 6, 1975
Docket12730
StatusPublished
Cited by5 cases

This text of 322 So. 2d 369 (Lane Wilson Company, Inc. v. Gregory) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lane Wilson Company, Inc. v. Gregory, 322 So. 2d 369, 1975 La. App. LEXIS 3388 (La. Ct. App. 1975).

Opinion

322 So.2d 369 (1975)

LANE WILSON COMPANY, INC., Plaintiff-Appellee,
v.
R. W. GREGORY, Jr., Defendant-Appellant.

No. 12730.

Court of Appeal of Louisiana, Second Circuit.

November 6, 1975.

*371 James H. Trousdale, Jr., Monroe, for defendant-appellant.

Kostelka & Blackwell, by Marshall Blackwell, Monroe, for plaintiff-appellee.

Before HALL, MARVIN and BURGESS, JJ.

BURGESS, Judge.

Plaintiff, Lane Wilson Company, Inc., sued defendant, R. W. Gregory, Jr., to recover the balance of the contract price allegedly due under a building contract in which plaintiff agreed to construct a swimming pool for defendant. In answer to plaintiff's suit, defendant alleged that plaintiff had not constructed the pool according to the terms of the contract and reconvened for damages in an amount sufficient to correct the alleged defects in the pool. The trial court found that plaintiff had substantially performed under the contract. Therefore, the lower court held that plaintiff was entitled to recover the contract price subject to a credit of $300 to remedy a defect in plaintiff's performance. We amend the trial court's judgment and affirm the judgment as amended.

Defendant is the owner of a KOA Campground facility near Monroe, which provides trailer space and utility connections for overnight campers and mobile home travelers. To make his campground more attractive to the traveling public, defendant decided to have a large swimming pool built. Accordingly, defendant entered into a written contract with plaintiff by which plaintiff agreed to construct a 30-foot by 60-foot swimming pool with a depth varying from three feet to six feet for a price of $12,000. At a later date the parties orally modified their contract by agreeing that plaintiff would add a diving board and increase the depth of the pool to safely accommodate persons using the diving board. Other oral modifications included enlarging the walkway around the pool and erecting a longer fence.

The original contract was also allegedly amended to reduce the number of water inlets from twelve to six. The cost of these modifications raised the contract price to $13,643.36.

The contract was entered into on February 2, 1973. Construction began on May 29, 1973, and the pool was completed by the first part of July. Defendant has paid $8,400 on the contract but refuses to pay more because of the alleged failure of plaintiff to construct the pool according to the terms of the contract and because of alleged defects in the construction. Plaintiff brought this suit to recover the balance allegedly due it.

*372 Article 2769 of the Civil Code governs the disposition of this appeal. The article provides:

"If an undertaker fails to do the work he has contracted to do, or if he does not execute it in the manner and at the time he has agreed to do it, he shall be liable in damages for the losses that may ensue from his non-compliance with his contract."

In Florida Ice Machine Corp. v. Branton Insulation, Inc., 290 So.2d 415 (La.App. 4th Cir. 1974), the court in interpreting the code article stated:

"The jurisprudence interpreting this code article has made it clear that construction contracts are treated in a different manner than other commutative contracts. In the latter there can be no recovery in the absence of full performance. In the case of construction contracts, a substantial compliance with the contract is sufficient to justify recovery of the contract price by the contractor. The remedy against the contractor (or the subcontractor, as in this case) in the presence of substantial compliance or performance is to allege and prove the nature and extent of the unfinished or defective work in order to reduce the sum owed to the contractor by the amount of the cost involved in properly completing the contract work. Therefore, the person proceeding against the contractor who has substantially performed must prove both the existence of the defects or omissions on the part of the contractor and the cost of repairing or finishing the defective work."

As reflected by the jurisprudential interpretation of Article 2769, this appeal presents two issues. First, has plaintiff substantially performed the contract thereby enabling him to recover the balance due on the contract price? Second, if plaintiff has substantially performed, are there any defects in the construction which entitle defendant to damages in an amount sufficient to remedy the faulty performance?

In Airco Refrigeration Service, Inc. v. Fink, 242 La. 73, 134 So.2d 880 (1961), the supreme court considered Article 2769 and the meaning of "substantial performance." The court stated:

"Substantial performance of the contract is essential to warrant the application of this rule of law. For if the breached contract has not been substantially performed, the contractor may not recover on the contract, but is limited to recovery on quantum meruit.
"The principal question presented in this case is whether or not there has been substantial performance so as to permit recovery on the contract. This is a question of fact. Among the factors to be considered are the extent of the defect or non-performance, the degree to which the purpose of the contract is defeated, the ease of correction, and the use or benefit to the defendant of the work performed."

In light of the factors enumerated above, we cannot say the trial court was manifestly erroneous in finding that plaintiff substantially performed the contract. Defendant contracted for a 30 by 60 foot swimming pool deep enough to accommodate persons using a diving board. The defects alleged by defendant are not such that defeat the purpose of the contract or prevent defendant from using the pool. In addition, the defects for which plaintiff may be held accountable are easily remedied.

In reconvention, defendant has alleged numerous defects in performance which entitle him to damages.

(a) Rather than measuring 30 by 60 feet as called for by the contract, the pool's measurements fluctuate from 59 feet six inches to 59 feet three and one-half inches in length, and from 29 feet one-half inch *373 to 29 feet three and one-half inches in width.

(b) The walls of the pool are not vertical but slope severely to form a bowlshaped pool.

(c) Plaintiff installed only six water inlets as opposed to twelve water inlets called for by the contract; this deficiency coupled with the poor placement of the inlets results in insufficient water circulation in the pool.

(d) The pool is not ten feet deep as the parties allegedly agreed.

(e) Plaintiff improperly installed a "skimmer box" which cased an unsightly dangerous bump in the concrete.

(f) Plaintiff did not lay the amount of concrete walkway called for by the contract.

(g) Plaintiff installed the water pump on a piece of wood planking rather than on a concrete base.

(h) Plaintiff damaged defendant's sewer line while building the pool.

(i) Plaintiff installed incorrect depth markers.

(j) Defendant supplied 200 feet of pipe to plaintiff for which he was not compensated.

(k) Defendant performed some clean-up work which plaintiff was obligated to do but did not.

(l) Plaintiff only installed six water inlets but charged defendant for twelve water inlets.

This court will consider each of these alleged defects in order.

(a) Defendant alleges it will cost some $2,000 to remedy the defect in the length and breadth of the pool. In Blakesley v. Ransonet, 159 La.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Red River Parish Port Commission v. Headwaters Resources Inc.
698 F. Supp. 2d 684 (W.D. Louisiana, 2010)
Allstate Enterprises, Inc. v. Brown
907 So. 2d 904 (Louisiana Court of Appeal, 2005)
Wike v. Joseph
516 So. 2d 1236 (Louisiana Court of Appeal, 1987)
Brown v. Delegal Construction Corp.
445 So. 2d 1251 (Louisiana Court of Appeal, 1984)
DESIGN & CORROSION ENG., INC. v. Piggly Wiggly of Mansfield, Inc.
408 So. 2d 292 (Louisiana Court of Appeal, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
322 So. 2d 369, 1975 La. App. LEXIS 3388, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lane-wilson-company-inc-v-gregory-lactapp-1975.