Allstate Enterprises, Inc. v. Brown

907 So. 2d 904, 2005 WL 1523588
CourtLouisiana Court of Appeal
DecidedJune 29, 2005
Docket39,467-CA
StatusPublished
Cited by20 cases

This text of 907 So. 2d 904 (Allstate Enterprises, Inc. v. Brown) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allstate Enterprises, Inc. v. Brown, 907 So. 2d 904, 2005 WL 1523588 (La. Ct. App. 2005).

Opinion

907 So.2d 904 (2005)

ALLSTATE ENTERPRISES, INC., Plaintiff-Appellant
v.
Greg BROWN and Denise Brown, Defendants-Appellants.

No. 39,467-CA.

Court of Appeal of Louisiana, Second Circuit.

June 29, 2005.

*908 Kenneth L. Harper, for Allstate Enterprises, Inc.

C. Bryan Racer, Monroe, for Greg Brown and Denise Brown.

Before CARAWAY, BROWN and STEWART, JJ.

CARAWAY, J.

This is a dispute between homeowners, who directed the construction of their home based on plans obtained from the internet, and the framing contractor which they hired. The contractor filed a lien for the balance owed on the parties' contract and the homeowners reconvened for damages related to the contractor's alleged substandard work. The trial court ruled in favor of the homeowners regarding the defective work, awarded damages in excess of the total contract price, and denied the contractor's claim of offset for the unpaid balance. Finding that the trial court erred in its failure to apply the doctrine of substantial performance of the contract, we reverse the ruling to allow the offset and to adjust the excessive award for damages to the homeowners.

Facts

Greg and Denise Brown obtained the services of Allstate Enterprises, Inc. ("Allstate") to furnish labor for a portion of the construction of a new home. Allstate first sued the Browns for $10,552.00, the unpaid balance on the contract, and the Browns reconvened for alleged damages resulting from Allstate's substandard workmanship.

After obtaining architectural plans for the home off the internet, Mr. Brown contacted Bill Thompson at Allstate to frame the foundation, pour the slab and frame up the house. The framing work included the roof, outside doors, windows, all walls and stairs. Brown testified that he "subcontracted" with other contractors, including electricians, plumbers, and a sheet rock subcontractor. Brown did some of the finishing work like interior painting.

The Browns' house design, Chatham Plan No. 4254-A-1, called for construction of an elaborate two-story, five-bedroom and three-bath stucco house with 4249 square feet of living area, 802 square feet of porches and an 816 square foot detached garage. The plans called for ten-foot ceilings on the first floor and nine foot ceilings on the second floor, along with an upstairs balcony traversing the family and dining room areas. The first floor architectural details included numerous archways and columns.

With regard to care and accuracy of these architectural designs, the plans expressed the following limitations:

Great care and effort have gone into the creation of the design of these plans. However, because of the impossibility of providing any personal and/or "on-the-site" consultation and supervision over the actual construction, and because of the great variance in local building code requirements, and other local building and weather conditions, designer assumes no responsibility for any damages, including structural failures, due to any deficiencies, omissions or errors in the design, blueprints, or specifications.

Thompson studied the plans and prepared the following proposal which was accepted by the Browns:

We hereby submit specifications and estimates for: House approximately 4691 sq. ft. on slab. Second story contains 1236 sq. ft. Total of 5927 sq. ft. Form, set, & dig footings install rods, wire, Visqueen Framing to include Studwalls, ceiling joists, rafters, decking, felt, cornice (soffit), set outside doors and windows. Cornice not to include crown mold per owners instructions and front *909 doors square fit. Outside of Home to be vinyl siding instead of stucco. Slab normal one foot above ground.
Bid Exclusions: No materials, electrical, plumbing, A/C & Htg
Raised Slab of 30 inches above ground will be cost plus 8% Approximately $2,605.83 for the slab. Total approx. $39,742.24
We propose hereby to furnish labor only — complete in accordance with the above specifications for the sum of $37,136.41 with payments to be made as follows: 4 payments: 1st¼ 2nd¼ 3rd¼ 4th¼

Greg Brown arranged to furnish all construction lumber and materials using a list based on the plans prepared by Tom Sanders, a lumber supplier. Although Sanders compiled the list, Brown shopped it with others and ultimately contracted for building materials with Russell Moore. Moore delivered the construction materials to the site as needed, based on Sanders' list.

The Browns alleged that Allstate's work on the house deviated from the plans and constituted substandard workmanship in numerous areas. The house foundation was apparently overshot by 3". This led to the dormers, windows, doors and dining room chandelier being off center. Allstate's carpenter, Randy Dodson, admitted that he missed 1½" on each end of the form when he set it, which caused the front porch to be 3" short. To remedy this situation, Thompson suggested a 3" double-studded wall on the left hand side of the interior of the house. Denise Brown authorized construction of the double wall. Dodson testified that alternatively, a concrete saw could have been used to remove the excess 3" from the foundation.

The height of the upstairs exterior walls deviated from the plans. The highest exterior second floor wall measures 41" high, which makes use of the upstairs walk-in closets difficult. The plans called for the walls to be no less than 66" high. The deviation was apparently attributable to either a design defect in the plans, a discrepancy in the pitch of the roof, or simply the location of the walls in the upstairs rooms. Brown's construction expert, John Maroney, testified that the problem with the short upstairs walls occurred because Thompson did not draw framing plans prior to starting construction.

The house plans called for 2×8 rafters for the roof. Tom Sander's list called for 2×6 rafters, and Moore delivered 2×6 rafters for use in the house construction. In Thompson's opinion, 2×6's were adequate if they were supported properly and braced off. Dodson testified that "just about every house you build is going to have 2×6 rafters." Maroney testified that although the roof of the house sagged, and the 2×8 rafters would have been stronger, he could not specifically attribute the sagging problem to the difference between the size of the rafters.

Greg Brown testified that after they started hanging sheetrock, he noticed the center dormer was 9" off center to the left, and the dining room chandelier was also off center. The plumber told Brown that the foundation was poured 3" off. Brown stated that "it throwed the whole front of the house off." The dining room chandelier was moved over 9" from the center of the room to improve aesthetics.

The garage floor elevation was lower than the house foundation. Brown testified that rainwater runs through the garage and out the garage door. Although Brown hauled some fill dirt in, he said Thompson was supposed to have formed it, backfilled it and reshot the grade before pouring the concrete. Thompson testified that there was a separate contract between Allstate and Brown to fill the foundation in with dirt after it was framed. *910 However, when Thompson started the job late, Brown told him to go ahead, that the pad was ready and the dirt work had been finished. Maroney testified that the garage elevation should have been about one foot higher. Also, the concrete in the breezeway between the garage and the house was cracked.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ryan v. Case New Holland, Inc.
211 So. 3d 611 (Louisiana Court of Appeal, 2016)
Siragusa v. Bordelon
195 So. 3d 100 (Louisiana Court of Appeal, 2016)
Bolton v. Willis-Knighton Medical Center
116 So. 3d 76 (Louisiana Court of Appeal, 2013)
Caskey v. Merrick Construction Co.
86 So. 3d 186 (Louisiana Court of Appeal, 2012)
Dunlap v. Madison Parish School Board
61 So. 3d 833 (Louisiana Court of Appeal, 2011)
Taylor v. Leger Construction, LLC
52 So. 3d 1098 (Louisiana Court of Appeal, 2010)
John Taylor, Et Ux. v. Leger Construction, LLC
Louisiana Court of Appeal, 2010
Cupit v. Hernandez
48 So. 3d 1114 (Louisiana Court of Appeal, 2010)
Fields v. Walpole Tire Service, L.L.C.
37 So. 3d 549 (Louisiana Court of Appeal, 2010)
Davis v. Sweeney
31 So. 3d 1184 (Louisiana Court of Appeal, 2010)
Lingoni v. Hibernia National Bank
33 So. 3d 372 (Louisiana Court of Appeal, 2010)
Rauch-Milliken International, Inc. v. Halprin
30 So. 3d 879 (Louisiana Court of Appeal, 2009)
Cosman v. Cabrera
28 So. 3d 1075 (Louisiana Court of Appeal, 2009)
Cascio v. Carpet
968 So. 2d 844 (Louisiana Court of Appeal, 2007)
City of Shreveport v. Noel Estate, Inc.
941 So. 2d 66 (Louisiana Court of Appeal, 2006)
Calcasieu Parish School Bd. v. LEWING CONS.
931 So. 2d 492 (Louisiana Court of Appeal, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
907 So. 2d 904, 2005 WL 1523588, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allstate-enterprises-inc-v-brown-lactapp-2005.