Siragusa v. Bordelon

195 So. 3d 100, 2015 La.App. 1 Cir. 1372, 2016 WL 1545176, 2016 La. App. LEXIS 733
CourtLouisiana Court of Appeal
DecidedApril 15, 2016
DocketNo. 2015 CA 1372
StatusPublished
Cited by6 cases

This text of 195 So. 3d 100 (Siragusa v. Bordelon) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Siragusa v. Bordelon, 195 So. 3d 100, 2015 La.App. 1 Cir. 1372, 2016 WL 1545176, 2016 La. App. LEXIS 733 (La. Ct. App. 2016).

Opinions

HIGGINBOTHAM, J.

[¡.This litigation concerns construction defects in a new house. The homeowners appeal the trial court’s judgment dismissing all of their claims against the builder.

BACKGROUND

In March 2005, builder, Chad Bradley Bordelon, through his construction company, Bordelon Commercial and Residential Construction, Inc. (“BCRC”), began construction of a new house for homeowners, John F. Hamilton, Jr., and his wife, Barbara Siragusa Hamilton.1 The Hamiltons were long-time friends of Mr. Bordelon’s family and for several years, beginning in 2000, they had many discussions with Mr. Bordelon about building a two-story house set on pilings (rather than a concrete foundation) in Covington, Louisiana. In late 2004, the Hamiltons agreed to have Mr. Bordelon construct their home on a cost-plus basis, with the high end of their budget set at $350,000.00.2 The Hamiltons’ building construction loan was approved in December 2004. Though construction of the Hamiltons’ house began in March 2005, progress slowed tremendously at the end of August 2005, when Hurricane Katrina hit the area. At that time, the house was still in the framing stage.

On April 19, 2006, a little over a year after construction began, Mr. Bordelon gave written notice to the Hamiltons that he would no longer be able to oversee the construction of their house. Mr. Bordelon’s reasons for terminating the agreement |3were related to storm issues (extremely high costs and delays) and a serious personal conflict with his construction foreman. When Mr. Bordelon left the project, the house had a roof, walls, and floorboards/sub-flooring, but no finishing work or insulation had been done, and most significantly, the joists and sills underneath the house had not been caulked/sealed. Because of his family’s relationship with the Hamiltons, Mr. Bordelon returned the unused portion of his builder’s fee to the Hamiltons. Although Mr. Bordelon recommended other builders to oversee the conclusion of the construction, Mr. Hamilton basically self-contracted the remainder of the job, completing the house with the use of subcontractors that had previously worked with Mr. Bordelon. It took another seven months to complete construction of the house. The Hamiltons were issued a cer[103]*103tificate of occupancy - and were finally able to move into their new house on or about December, 15, 2006.-

By January or February, 2007, the Hamiltons noticed water retention on their front porch after a hard rain. They telephoned Mr. Bordelon and asked him to check their porch, but after inspecting it, Mr. Bordelon indicated that the pooled water should not be a problem. During the summer of 2007, the Hamiltons- began to notice that the wood floors on the first floor of their home were buckling. They did not inform Mr. Bordelon of the flooring problem since he indicated that he no longer wanted to have anything to do with the house after terminating their agreement. Instead, the Hamiltons retained a flooring consultant, who advised them to install gutters and drainage (two things that were not included in the original construction plans) to route water away from the house. The gutter work was completed in 2007 at a cost of $5,962.00.

Eventually, because of ongoing issues with moisture inside the house, the Hamil-tons contracted with another residential contractor, Robert L. Gilhaus, of B.G. Contractors, on October 25, 2010, to remedy the house’s moisture problems. The Ham-iltons agreed to have Mr. Gilhaus seal all of the joists/sills and install flashing |4and a vapor/moisture barrier between the front porch and the house, all of which Mr. Gilhaus discovered was missing, .thereby allowing moisture inside of the Hamiltons’ house. The Hamiltons also contracted with Mr. Gilhaus to remove the entire front porch in order to correct the slope of the porch and to replace rotten boards, sills, and sub-flooring where the porch tied into the house. Once the porch was removed, it was discovered that there were no pilings under the front bay window area of the. house, there was no flashing between the porch and house, some floor joists and insulation had been installed incorrectly underneath the house, wood underneath the house was stained with moisture, and some sills underneath the house were in need of extra angle-iron support because the sills were not fully sitting on the foundational pilings. Mr. Gilhaus completed all of the remedial work on the house for a total of $40,957.90.. In November 2013, Mr. Gilhaus gave the Hamiltons an additional estimate of $14,032.50 to repair the upstairs balcony that, had begun to show signs of significant moisture damage. At no point in time during the remedial work did the Hamil-tons move out of their house, nor did they give any kind of notice to Mr. Bordelon concerning the multiple problems discovered by Mr. Gilhaus.

On November 18, 2011, almost five years after moving into the house, the Hamiltons filed a petition for breach of contract against Mr. Bordelon and his construction companies.3 The Hamiltons alleged the house contained numerous and extensive construction defects that were the result of Mr. Bordelon’s bad workmanship, causing them to incur expenses to repair foundation, moisture, and flooring problems. Mr. Bordelon-and his companies denied all allegations. The matter proceeded to a bench trial on November 30,2014, where testimony from Mr. Hamilton, Mr. Bordelon, and Mr. Gilhaus was heard. Numerous exhibits were | ^admitted, including photographs [104]*104taken during Mr. Gilhaus’s remedial work, Mr. Bordelon’s letter terminating the contract, invoices/estimates for the remedial work, and information concerning the construction account.

After considering all of the testimony and evidence, the trial court issued written reasons for judgment on January 28, 2015, finding that the Hamiltons’ exclusive remedy was- governed by the New Home Warranty Act (“NHWA”), because “[a]ll damages alleged in the petition arose out of the work associated with home construction.” Additionally, the trial court concluded that the Hamiltons’ recovery under the NHWA was ultimately precluded for failure to comply with the NHWA’s mandatory notice requirements. Moreover, the' trial court determined that the Hamil-tons’ only possible non-perempted claims pertained to major structural defects, but the actual physical damage to the house’s foundational pilings or flooring did not reflect a major structural defect since the Hamiltons’ house was not unsafe, unsanitary, or unlivable. Accordingly, the trial court signed a judgment dismissing all of the Hamiltons’ claims against Mr. Borde-lon and his construction companies on February 24, 2015.

The Hamiltons appeal, assigning three errors: (1) the trial court erred in finding the NHWA was the Hamiltons’ exclusive remedy; (2) the trial court erred in finding that notice was not given in compliance with the NHWA; and (3) the trial court erred in finding that the Hamiltons’ claims were perempted under the NHWA.

STANDARD OF REVIEW

The trial court’s factual findings in cases involving the NHWA are subject to manifest error review. Hutcherson v. Harvey Smith Const., Inc., 2008-1046 (La.App. 1st Cir.2/13/09), 7 So.3d.775, 778. An appellate court cannot set aside the trial court’s factual findings unless it determines there is no reasonable factual basis for the findings and the findings are clearly wrong. Stobart v. State through Dept. of Transp. and Development, 617 So.2d 880, 882 (La.1993).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
195 So. 3d 100, 2015 La.App. 1 Cir. 1372, 2016 WL 1545176, 2016 La. App. LEXIS 733, Counsel Stack Legal Research, https://law.counselstack.com/opinion/siragusa-v-bordelon-lactapp-2016.