Jenkins Building Supply, Inc. v. Thigpen

34 So. 3d 867, 2009 La.App. 1 Cir. 0903, 2009 La. App. LEXIS 2173, 2009 WL 4980396
CourtLouisiana Court of Appeal
DecidedDecember 23, 2009
Docket2009 CA 0903
StatusPublished
Cited by5 cases

This text of 34 So. 3d 867 (Jenkins Building Supply, Inc. v. Thigpen) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jenkins Building Supply, Inc. v. Thigpen, 34 So. 3d 867, 2009 La.App. 1 Cir. 0903, 2009 La. App. LEXIS 2173, 2009 WL 4980396 (La. Ct. App. 2009).

Opinion

PETTIGREW, J.

| .¿Defendants/appellants, Wanda J. McClain Thigpen and Lionel K. Thigpen, appeal from the trial court’s judgment in favor of plaintiff/appellee, Jenkins Building Supply, Inc. (“Jenkins”), awarding Jenkins damages for out-of-pocket expenses it incurred for materials and subcontractors in connection with the construction of the Thigpens’ residence in St. Tammany Parish. For the reasons that follow, we affirm.

PERTINENT FACTS AND RULING OF THE LOWER COURT

According to the record, the Thigpens initially met with Barrett Jenkins, part owner of Jenkins, in August 2004, to discuss the construction of their home, at which time the Thigpens presented house plan specifications to Barrett. It was agreed by the parties that Jenkins would build the Thigpen home for a fixed price of $95,300.00. Because of title problems with the land, construction did not actually begin until April 2005, with an updated bid proposal dated February 2, 2005. The agreed upon price, $95,300.00, remained the same. As construction progressed, several changes to the original plan specifications were made by the Thigpens, causing an increase in cost. However, the Thigpens assured Barrett that they had borrowed more money than the original bid called for and that the changes would be taken care of at the end of the job.

Construction on the home continued, as did inspections by both the Parish of St. Tammany and Parish National Bank, the bank that provided the loan to the Thig-pens. No workmanship problems or code violations were noted. By August 2005, the home was 75-80 percent complete, and Jenkins had received 3 of 4 draws from Parish National Bank for approximately $70,000.00. Like many other properties in Louisiana, the Thigpen home suffered damage from Hurricane Katrina in August 2005. Barrett worked with the Thigpens’ insurance company to secure insurance funds for the damage sustained as a result of Hurricane Katrina. The Thigpens ultimately received a $30,500.00 check from their insurance company for them property damage claim. After the insurance funds were received by the Thigpens, Jenkins proceeded with salvage work on the home, advancing money out-of-pocket to pay for labor, materials, and appliances. In February 2006, Jenkins requested payment from the Thigpens to cover these out-of-pocket expenses. [sWhen the Thigpens refused, Jenkins ceased all work on the Thigpen home and left the jobsite.

On March 27, 2006, Jenkins filed the instant suit to recover costs it paid out-of-pocket for material and subcontractors for work performed on the Thigpen home. The Thigpens responded, claiming Jenkins’ work was unsatisfactory, and reconvened for alleged damages as a result of breach *869 of contract and pursuant to the New Home Warranty Act (“NHWA”), La. R.S. 9:3141, at seq. The Thigpens sought damages for emotional distress, loss of enjoyment and use, lost opportunities, frustration and concern, and time and energy, as well as all additional costs incurred by them over and above the contract price as a result of the alleged breach of contract by Jenkins.

The matter proceeded to a bench trial on August 20, 2008, and was taken under advisement by the trial court. In a judgment rendered December 16, 2008, the trial court found in favor of Jenkins, awarding damages in the amount of $45,339.44, plus interest from the date of judicial demand until paid. The Thigpens subsequently filed a motion for new trial, which was denied by the trial court. This appeal by the Thigpens followed.

ISSUES PRESENTED

The Thigpens assign legal error by the trial court in finding that the NHWA was the only remedy available to them under the facts of this case and that notice was required under the NHWA. The Thigpens assign manifest error by the trial court in its factual finding that Jenkins was entitled to damages in the amount of $45,339.44 and in its factual finding that the Thigpens were not entitled to attorney fees and costs or compensatory damages for the amounts they paid to complete their residence and for delay in construction and loss of use.

DISCUSSION

The trial court’s factual findings in cases involving the NHWA are subject to manifest error review. Hutcherson v. Harvey Smith Const, Inc., 2008-1046, p. 3 (La.App. 1 Cir. 2/13/09), 7 So.3d 775, 778. An appellate court cannot set aside the trial court’s factual findings unless it determines there is no reasonable factual basis for the findings and the findings are clearly wrong. Stobart v. State through Dept. of Transp. and Development, 617 So.2d 880, 882 (La.1993). Thus, if the findings are reasonable in light of the record reviewed in its entirety, this court may not reverse even though convinced that had it been sitting as the trier of fact, it would have weighed the evidence differently. Rosell v. ESCO, 549 So.2d 840, 844 (La.1989). With regard to questions of law, the appellate review is simply a review of whether the trial court was legally correct or legally incorrect. On legal issues, the appellate court gives no special weight to the findings of the trial court, but exercises its constitutional duty to review questions of law and render judgment on the record. Pierce v. State, Office of Legislative Auditor, 2007-0230, p. 7 (La.App. 1 Cir. 2/8/08), 984 So.2d 61, 67, writ denied, 2008-0542 (La.4/25/08), 978 So.2d 369.

In ruling in favor of Jenkins, the trial court issued the following detailed written reasons for judgment:

This matter came to be heard on the merits August 20, 2008 and was taken under advisement with a briefing schedule (which was later extended due to Hurricane Gustav.) Plaintiff seeks relief for the alleged failure of defendants to pay sums due to it for expenses incurred due to its performance of a building contract. Defendants denied those allegations and reconvened for alleged damages as a result of breach of contract and under the [NHWA].
The Court has no difficulty in determining that plaintiff supplied extra materials and construction that was not contemplated in the building contract. Although all parties could have operated in a more businesslike manner, it is clear that the Thigpens made several changes and knew they would have to *870 pay more for those changes. The Court finds that defendants owe $45,339.44 for those changes. The Court also has no difficulty in finding the defendants breached the building contract and not plaintiff. Defendants never paid the complete draw from Parish National Bank to the contractor and plaintiffs hadn’t gotten anything from the repairs necessitated by Hurricane Katrina. In February, 2006 plaintiff was totally justified in leaving the job. It had done numerous add-ons without compensation as well as not receiving all of the draw nor anything for hurricane repairs. The claim of defendants that plaintiff breached due to time delays is spurious. Mr. Thigpen notes that there was no specific time period agreed upon in the contract and only approximate time frames given in conversation. It appears that even the approximated time might have been met but for Hurricane Katrina. The Court finds that there had been no indications of any dissatisfaction with the construction expressed by the Thigpens until the plaintiff left the job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robinson v. Wayne & Beverly Papania & Pyrenees Investments, LLC
207 So. 3d 566 (Louisiana Court of Appeal, 2016)
Siragusa v. Bordelon
195 So. 3d 100 (Louisiana Court of Appeal, 2016)
Nunez v. Pinnacle Homes, L.L.C.
135 So. 3d 1283 (Louisiana Court of Appeal, 2014)
Jennifer Diane Nunez v. Pinnacle Homes, LLC
Louisiana Court of Appeal, 2014
Ledbetter v. Homes by Paige, L.L.C.
110 So. 3d 141 (Louisiana Court of Appeal, 2012)
Cupit v. Hernandez
48 So. 3d 1114 (Louisiana Court of Appeal, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
34 So. 3d 867, 2009 La.App. 1 Cir. 0903, 2009 La. App. LEXIS 2173, 2009 WL 4980396, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jenkins-building-supply-inc-v-thigpen-lactapp-2009.