Cupit v. Hernandez

48 So. 3d 1114, 2010 La. App. LEXIS 1293, 2010 WL 3768100
CourtLouisiana Court of Appeal
DecidedSeptember 29, 2010
DocketNo. 45,670-CA
StatusPublished
Cited by12 cases

This text of 48 So. 3d 1114 (Cupit v. Hernandez) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cupit v. Hernandez, 48 So. 3d 1114, 2010 La. App. LEXIS 1293, 2010 WL 3768100 (La. Ct. App. 2010).

Opinion

BROWN, Chief Judge.

|, The plaintiff homebuilder filed a petition seeking to recover the balance due on a construction contract. The defendants filed a reconventional demand in which they asserted a claim under the New Home Warranty Act (“NHWA”) and sought, inter alia, repair costs. After a bench trial, the court awarded plaintiff, Joe Cupit, $8,178.64 on his contractual claim, and defendants, Lyda and Isidro Hernandez, $80,000 on their NHWA claim. Costs were apportioned between the parties, and defendants were awarded attorney fees in the amount of $5,000. It is from this judgment that plaintiff, Joe Cu-pit, has appealed.

Discussion

The trial court’s factual findings in cases involving the NHWA are subject to manifest error review. Craig v. Adams Interior, Inc., 34,591 (La.App.2d Cir.04/06/01), 785 So.2d 997; Sowers v. Dixie Shell Homes of América, Inc., 33,390 (La.App.2d Cir.05/15/00), 762 So.2d 186 writ denied, 00-1770 (La.09/22/00), 768 So.2d 1286.

Notice of Defects

In his first assignment of error, plaintiff asserts that the trial court erred in failing to dismiss defendants’ reconventional demand based upon the fact that defendants did not comply with the mandatory notice requirement of the NHWA.

La. R.S. 9:3145(A) provides that: Before undertaking any repair himself or instituting any action for breach of warranty, the owner shall give the builder written notice, by registered or certified mail, within one year after knowledge of the defect, advising him of all defects, and giving the guilder a reasonable opportunity to comply with the provisions of this Chapter.

|2Absent compliance with the notice requirement set forth in La. R.S. 9:3145, recovery under the NHWA is precluded. Thorn v. Caskey, 32,310 (La.App.2d Cir.09/22/99), 745 So.2d 653; Jenkins Building Supply, Inc. v. Thigpen, 09-0903 (La.App. 1st Cir.12/23/09), 34 So.3d 867.

It is undisputed that defendants, prior to filing their reconventional demand, failed to provide plaintiff with the written notice required by La. R.S. 9:3145(A). Recently, however, several courts have held that the owners’ failure to comply with the technical requirements of La. R.S. 9:3145(A) is not necessarily fatal to their NHWA claim when they have provided actual notice of specific defects within the time limits to the builder.

In Frank v. Tran, 07-983 (La.App. 3d Cir.01/30/08), 974 So.2d 861, the home-builder sued the owner for failure to make the final two payments on the parties’ residential construction contract. In a re-conventional demand, the owner asserted, inter alia, a claim under the NHWA. The trial court dismissed the owner’s reconven-tional demand based upon its finding that the owner did not provide proper notice of the complained of defects to the builder as required by La. R.S. 9:3145(A).

In reversing the trial court, the Third Circuit found that the builder had actual written notice of the owner’s specific complaints and concerns. Therefore, strict compliance with La. R.S. 9:3145 was not required under the facts of the case. The record showed that during the home’s construction, the owner began voicing complaints. The affidavit of the vice-president of the bank which financed the construction loan for the owner also evidenced |sthat the owner made complaints during construction. Furthermore, the lender, at the owner’s request, discussed with the builder (and provided a copy of) a list of specific concerns to be corrected that the owner prepared. A similar notification of [1118]*1118the owner’s specific concerns and complaints was sent by the owner’s attorney to the builder’s attorney. All of these communications were made during or shortly after construction. The court also observed that the builder was given an opportunity to remedy the alleged deficiencies, given that the dates of the above notifications were before he was ultimately prevented from returning to the home in April 2004.

In Barrack v. J.F. Day & Co., Inc., 07-97 (La.App. 4th Cir.08/29/07), 966 So.2d 1064, the homeowners began experiencing immediate problems with customized, specially installed windows. They notified their contractor, who contacted the manufacturer of the windows. After several repairs were unsuccessful, a senior sales representative from the manufacturer opined that while there was product design failure, there was also a problem with the installation and/or mulling by the contractor. In defending the NHWA claim filed by the owners, the contractor contended lack of notice in accordance with La. R.S. 9:3145.

The Fourth Circuit observed that not only did the owners give the contractor verbal notice of the specific defects within the statutory time limits, they allowed him several opportunities to remedy the defects. Furthermore, they provided the contractor with written notice of the specific notice prior to filing suit (although after the time limits had run). The court emphasized that the fact that the contractor notified the window | manufacturer and salespeople of the problems on numerous occasions was proof that he had notice/notification within the intendment of the statute.

In the instant case, defendants moved into the main house in June 2007; construction of the cook house was still ongoing. Almost immediately, defendants noticed problems with movement and vibration of the structure, as well as doors sticking and uneven floors. After rains in July 2007, the structure of the house shifted further and became more unstable. The Hernandezes made repeated verbal complaints about these specific problems to Cupit, who disputed that there were any problems, except with the doors. To remedy defendants’ complaints about the doors, plaintiff cut off several of the doors so they could open. Defendants continued to voice concerns about the stability of their home, and plaintiff installed diagonal and horizontal 2" x 4" braces between the support columns, but this stopped neither the vibration nor shifting of the floors. When defendants informed plaintiff that the bracing had failed to address their foundation problems, he refused to make any further efforts to address their complaints.

Defendants refused to make their final payment to plaintiff based upon their dissatisfaction with his response to their continued complaints about, inter alia, the instability of their home’s foundation. At that time, in September 2007, plaintiff refused to undertake any further repairs. Cupit filed his claim in November 2007, and the Hernandezes hired a structural engineer, Mark Thomey, to investigate the stability of their home.

Thomey inspected defendants’ home in December 2007 and took photographs of the foundation and joist structure. He also prepared a twoj¡oage5 blueprint showing how the main home’s foundation could be repaired.1 This blueprint was attached [1119]*1119to a letter sent by defendants’ attorney to plaintiffs counsel in December 2007, informing him that defendants had their home inspected by a structural engineer who had prepared a plan showing what needed to be done for the house to be structurally secure. Defendants offered Cupit the opportunity to undertake the repairs or to pay for defendants to have them done by another contractor. They received no response to this letter.

Thereafter, defendants filed their answer and counterclaim in June 2008.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
48 So. 3d 1114, 2010 La. App. LEXIS 1293, 2010 WL 3768100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cupit-v-hernandez-lactapp-2010.