Calcasieu Parish School Bd. v. LEWING CONS.

931 So. 2d 492, 2006 WL 1472514
CourtLouisiana Court of Appeal
DecidedMay 31, 2006
Docket05-928
StatusPublished
Cited by4 cases

This text of 931 So. 2d 492 (Calcasieu Parish School Bd. v. LEWING CONS.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Calcasieu Parish School Bd. v. LEWING CONS., 931 So. 2d 492, 2006 WL 1472514 (La. Ct. App. 2006).

Opinion

931 So.2d 492 (2006)

CALCASIEU PARISH SCHOOL BOARD
v.
LEWING CONSTRUCTION CO., INC. et al.

No. 05-928.

Court of Appeal of Louisiana, Third Circuit.

May 31, 2006.

*493 Joseph A. Delafield, Lake Charles, LA, for Defendant-Appellant, Lewing Construction Co., Inc.

Michael G. Gaffney, Nolan P. Lambert, New Orleans, LA, for Defendant-Appellant-Appellee, D & T Tile and Terrazzo, Inc.

Kraig T. Strenge, Lafayette, LA, for Third Party Defendant-Appellant-Appellee, Lafayette Insurance Co.

Court composed of ULYSSES GENE THIBODEAUX, Chief Judge, JIMMIE C. PETERS, and J. DAVID PAINTER, Judges.

PAINTER, Judge.

This appeal arises from a trial court judgment apportioning fault for a defective floor among the Defendants, Lewing Construction Co., Inc. ("Lewing"), D & T Tile and Terrazo, Inc. ("D & T"), and Key Resin ("Key"), and finding coverage under a policy of insurance issued by Lafayette Insurance Company ("Lafayette") to D & T.

FACTS & PROCEDURAL HISTORY

In November 1996, the Calcasieu Parish School Board ("the School Board") contracted with Lewing to build an addition to the R.W. Vincent School ("the school") in Sulphur, Louisiana. C. Ray Fugatt was the architect for the project and, as such, drew the plans and set the specifications for the project. The plans called for an epoxy terrazzo floor. Lewing, the general contractor, lacking the expertise needed for installation of such a floor, subcontracted this part of the project to D & T. D & T obtained the epoxy resin needed for the floor from Key Resin Company. The floor was installed both in the new addition to the school and in part of a pre-existing *494 cafeteria. Shortly after installation, an oily substance began to appear on the surface on the floor. Upon inspection, the substance appeared to be rising out of the floor through pinholes in the surface. Efforts at remediation were made by Lewing and D & T. Ultimately, Lewing paid for a different flooring installer to replace the epoxy terrazzo floor with a cement-based terrazzo floor.

The School Board filed this suit against Lewing and D & T. Lewing filed a cross-claim against D & T. D & T filed third-party demands against Key Resin and its own commercial general liability insurer, Lafayette. Prior to trial, the School Board dismissed its claim against Lewing. The third-party claims proceeded to trial.

At trial, much evidence was adduced to determine whether the problems with the floor were caused by defects in the slab, defects in the flooring materials, or defects in the installation of the floor. The trial court concluded that the oily substance was brought to the surface of the floor as a result of water vapor transmission from below and rendered written reasons in which it found as follows:

This was the first time that C.R. Fugatt, the architect under the contract, had used this particular type of flooring, which was utilized to save money. His specifications for the job were that it conform to national standards, without really investigating what those standards were or whether or not they were obtainable in Southwest Louisiana. Lewing Construction took particular care with the job, since they understood that there may be a problem with water vapor transmission, but did no further investigation about what standards might be appropriate or what were obtainable and in particular, did not know what the terrazzo industry flooring standards were. D & T tested the floors using one of the manufacturer's suggested tests and D & T knew or should have known of the industry standards for water vapor transmissions. Key Resin instructed its suppliers on a method to test the water vapor transmission that was not trustworthy.
As between the contractor and the subcontractor, Lewing and D & T tile, D & T Tile had the greater responsibility and knowledge to inform and advise the contractor about what the requirements were for the proper installation of a floor. However, the contractor is not free from fault and should have done some investigation of their own. I assess 20% of the fault for this floor's failure to Lewing Construction and the architect, which they will share equally, as I believe that the architect had an obligation to do a little further investigation as it concerns this type of flooring for which he had no prior experience. As between the installer and the manufacturer, I believe that they equally had a responsibility to know the capabilities of the product that they were selling and installing. Consequently, I assess 80% of the fault to the installer, who is entitled to recover 50% of what he is required to pay because of the fault of the manufacturer in failing to warn them of the particular problems with the test that it recommends be done.
I am not convinced that any exclusions apply, consequently the insurance was in full force and effect for this work and therefore, D & T is entitled to recover what it has to pay from Lafayette Ins. Co.

The trial court rendered judgment as it set out in its reasons. The court assessed costs twenty-five percent to each of the Defendants. Lewing, D & T, and Lafayette appeal.

*495 DISCUSSION

Contractor's Liability

Lewing asserts that the trial court erred in assessing it with twenty percent of the fault for the failure of the floor, because it fully complied with the architect's plans and specifications in pouring the slab on which the floor was installed. D & T argues that the trial court erred in finding it liable for the failure of the floor because it also followed the architect's plans and specifications. D & T contends that it had no reason to believe a hazardous condition was present because it was impossible to know the floor would, at certain times and under certain conditions, have a vapor transmission rate over that recommended by the manufacturer. Finally, D & T argues that the trial court erred in finding it liable for the floor's failure without finding that it improperly installed the floor. Key Resin has not appealed the trial court judgment. Therefore, we will not examine the trial court's finding as to its liability.

Both Lewing and D & T assert that the provisions of La.R.S. 9:2771 apply to relieve them of liability for the floor's failure. La.R.S. 9:2771 provides that:

No contractor, including but not limited to a residential building contractor as defined in R.S. 37:2150.1(9), shall be liable for destruction or deterioration of or defects in any work constructed, or under construction, by him if he constructed, or is constructing, the work according to plans or specifications furnished to him which he did not make or cause to be made and if the destruction, deterioration, or defect was due to any fault or insufficiency of the plans or specifications. This provision shall apply regardless of whether the destruction, deterioration, or defect occurs or becomes evident prior to or after delivery of the work to the owner or prior to or after acceptance of the work by the owner. The provisions of this Section shall not be subject to waiver by the contractor.

"La.R.S. 9:2771 does not require the contractor to prove fault or insufficiency of plans and specifications, but, rather, immunity results from proof of compliance alone. City of Covington v. Heard, 428 So.2d 1132 (La.App. 1st Cir.1983)." Bernard v. State Through Dept. of (Highways) Transp. & Dev., 93-1376, p. 10 (La. App. 3 Cir. 6/1/94), 640 So.2d 694, 700, writ denied,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cupit v. Hernandez
48 So. 3d 1114 (Louisiana Court of Appeal, 2010)
Lingoni v. Hibernia National Bank
33 So. 3d 372 (Louisiana Court of Appeal, 2010)
Calcasieu School Bd. v. Lewing Const.
971 So. 2d 1275 (Louisiana Court of Appeal, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
931 So. 2d 492, 2006 WL 1472514, Counsel Stack Legal Research, https://law.counselstack.com/opinion/calcasieu-parish-school-bd-v-lewing-cons-lactapp-2006.