Industrial Roofing v. Jc Dellinger Mem.

751 So. 2d 928, 1999 WL 632224
CourtLouisiana Court of Appeal
DecidedAugust 20, 1999
Docket32,048-CA
StatusPublished
Cited by20 cases

This text of 751 So. 2d 928 (Industrial Roofing v. Jc Dellinger Mem.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Industrial Roofing v. Jc Dellinger Mem., 751 So. 2d 928, 1999 WL 632224 (La. Ct. App. 1999).

Opinion

751 So.2d 928 (1999)

INDUSTRIAL ROOFING & SHEET METAL WORKS, INC., Plaintiff-Appellee,
v.
J.C. DELLINGER MEMORIAL TRUST, Defendant-Appellant.

No. 32,048-CA.

Court of Appeal of Louisiana, Second Circuit.

August 20, 1999.
Rehearing Denied September 16, 1999.

*932 Gary L. Fox, Shreveport, Counsel for Appellant.

Walter D. White, Counsel for Appellee.

Before NORRIS, C.J., and WILLIAMS, STEWART, PEATROSS and KOSTELKA, JJ.

STEWART, J.

This case arises out of a contractual dispute between the appellant, J.C. Dellinger Memorial Trust (the Trust) and the appellee, Industrial Roofing & Sheet Metal Works, Inc. (Industrial). The Trust appeals the judgment by the Honorable Charles W. Kelly, IV, Shreveport City Court for the Parish of Caddo, in favor of the appellee, finding that Industrial is entitled to the balance due on the contract for the performance of roof repairs, that Industrial is entitled to interest from the date of judicial demand, plus all costs of court and rejecting the Trust's Reconventional Demand. We reverse in part, affirm in part, amend in part and as amended render.

FACTS

On June 21, 1993, the Trust entered into a contract with Industrial for roof work on the B'nai Zion Temple (Temple) located at 800 Common Street, Shreveport, Louisiana. After Industrial allegedly completed the work, the Trust refused to pay for the services rendered alleging defective performance, defective repairs, damages and incomplete repairs. The Trust paid $54,000 of the contract and retained $10,000. Industrial filed suit and the Trust answered the suit claiming offset for defective performance, pleading accord and satisfaction and estoppel. The Trust also reconvened for damages it sustained for defective repairs, damages or incomplete repairs.

Trial was held on October 28, 1997. In response to Industrial's suit for the balance due, the Trust argued that there was an agreement and that Industrial failed to use copper to repair the "hog valleys" on the roof, that Industrial failed to waterproof the parapet wall and to connect an inner roof drain to an outer gutter which resulted in further water damage to the Temple, and that a crack in the parapet wall resulted from Industrial's scaffolding. The Trust further argued that Industrial removed a segment of the hog valley above a historic stain glass window to inspect the wood and that Industrial's failure to replace or reseal this membrane allowed the drainage in this valley to spill over the top and damage this stain glass window and surrounding wood and plaster.

The trial court erroneously rendered an opinion on January 2, 1998 prior to receiving the Trust's Post-trial Brief. The trial court rendered another opinion that revoked the previous opinion in its entirety. In the February 12, 1998 opinion, the trial court found that there was no common intent of the parties to specify copper to be used in repair of the hog valleys, that the contract was written with a base plus alternatives for additional work to be added to the base bid, that these alternatives were specific references to the nature and type of materials and that if there had been any intent to specify copper in repair of the hog valleys, the parties could have specified such in the contract.

The trial court further found that nothing in the contract provided for any work inside the building and not for repair of the down spouts. However, the court did find that a crack in the exterior masonry wall, in the vicinity of the scaffolding erected *933 by Industrial, was attributable to Industrial and reduced the balance due to Industrial. Therefore, the trial court found that Industrial was owed the net sum of $9,548.00 and that the remaining demands of the Trust were denied.

The Trust filed a Motion for New Trial based upon their contention that photographic evidence verified that an Industrial superintendent provided false testimony that Industrial extended the membrane in the hog valley up to the top of the parapet wall and counter flashed this membrane. Industrial's failure to do so resulted in further damage to the Temple. The Motion for New Trial was denied on May 27, 1998. This appeal by the Trust followed. The appeal was answered by Industrial seeking an increase in the sum awarded.

DISCUSSION

Where factual findings are pertinent to the interpretation of a contract, those factual findings are not to be disturbed unless manifest error is shown. Martin Exploration Co. v. Amoco Production Co., 637 So.2d 1202, 93 0349 (La. App. 1st Cir.5/20/94), rehearing denied, writ denied 644 So.2d 1048, 94-2003 (La.11/4/94). However, when appellate review is not premised upon any factual findings made at the trial level, but is, instead, based upon an independent review and examination of the contract on its face, the manifest error rule does not apply. In such cases, appellate review of questions of law is simply whether the trial court was legally correct or legally incorrect. Noel v. Discus Oil Corp., 30,561 (La.App.2d Cir.5/13/98), 714 So.2d 105, 107; McDuffie v. Riverwood Intern. Corp., 27,292 (La. App.2d Cir.8/23/95), 660 So.2d 158; Conoco, Inc. v. Tenneco, Inc., 524 So.2d 1305 (La.App. 3d Cir.1988), writ denied, 525 So.2d 1048 (La.1988).

The contract is the law between the parties. When the words of a contract are clear and explicit and lead to no absurd consequences, no further interpretation may be made in search of the parties' intent. LSA-C.C. art.2046. Courts may not disregard a clear and explicit clause of a contract. Amend v. McCabe, 664 So.2d 1183, 1187 (La.1995); Maloney v. Oak Builders, Inc., 256 La. 85, 235 So.2d 386 (1970).

The courts are bound to give legal effect to all written contracts according to the true intent of the parties and this intent is to be determined by the words of the contract when these are clear, explicit and lead to no absurd consequences. The meaning and intent of the parties of the written contract in such cases must be sought within the four corners of the instrument and cannot be explained or contradicted by parol evidence. Under Louisiana law, when there is any doubt about the meaning of an agreement, the court must ascertain the common intention of the parties, rather than adhering to the literal sense of the terms. If this intent cannot be adequately discerned from the contract itself, the court may then consider evidence as to the facts and circumstances surrounding the parties at the time the contract was made. Liem v. Austin Power, Inc., 569 So.2d 601, 608 (La.App. 2 Cir.1990). Whether a contract is ambiguous or not is a question of law. Id.

CONTRACT FOR USE OF COPPER

In the appellant's first assignment of error, the Trust urges that the trial court erred in finding that there was no contract term requiring copper hog valleys. The Trust urges that Alternate No. 2 of the contract establishes an agreement to install copper hog valleys in the narrow perimeter valleys that drain the entire roof and that the contract term "copper valleys" specified copper hog valleys. The largest portion of the roof, which is the subject of the contract, is bound on all sides by a steep sloping slate roof. The entire roof is drained over the slate roof into hog valleys which are narrow perimeter channels or valleys that collect all of the water.

*934

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robert E. Redstone, III v. John P. Sipes
Louisiana Court of Appeal, 2020
Butler v. Begnauds, LLC
273 So. 3d 412 (Louisiana Court of Appeal, 2019)
Alicia Johnson Butler v. Begnauds, LLC
Louisiana Court of Appeal, 2019
Abushanab v. St. Charles Gaming Co.
103 So. 3d 1197 (Louisiana Court of Appeal, 2012)
Matherne v. Barnum
94 So. 3d 782 (Louisiana Court of Appeal, 2012)
Smith v. Coffman
87 So. 3d 137 (Louisiana Court of Appeal, 2012)
Davis v. Russell
26 So. 3d 950 (Louisiana Court of Appeal, 2009)
Lewis v. La Adrienne, Inc.
17 So. 3d 1007 (Louisiana Court of Appeal, 2009)
Miller v. Miller
1 So. 3d 815 (Louisiana Court of Appeal, 2009)
Regions Bank v. ARK-LA-TEX WATER GARDENS
997 So. 2d 734 (Louisiana Court of Appeal, 2008)
Cascio v. Carpet
968 So. 2d 844 (Louisiana Court of Appeal, 2007)
Allstate Enterprises, Inc. v. Brown
907 So. 2d 904 (Louisiana Court of Appeal, 2005)
Shelter Ins. Co. v. Broan-Nutone, LLC
902 So. 2d 1146 (Louisiana Court of Appeal, 2005)
Mount Mariah Baptist Church, Inc. v. Pannell's Associated Electric, Inc.
835 So. 2d 880 (Louisiana Court of Appeal, 2002)
Mt. Mariah Church v. PANNELL'S ASSOC. ELEC.
835 So. 2d 880 (Louisiana Court of Appeal, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
751 So. 2d 928, 1999 WL 632224, Counsel Stack Legal Research, https://law.counselstack.com/opinion/industrial-roofing-v-jc-dellinger-mem-lactapp-1999.