Robert E. Redstone, III v. John P. Sipes

Louisiana Court of Appeal·Decided April 22, 2020·No. 53,416-CA·Published

Opinion

Judgment rendered April 22, 2020.

Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.

No. 53,416-CA

COURT OF APPEAL

SECOND CIRCUIT

STATE OF LOUISIANA

*****

ROBERT E. REDSTONE, III Plaintiff-Appellee versus

JOHN P. SIPES Defendant-Appellant

*****

Appealed from

Shreveport City Court for the Parish of Caddo, Louisiana Trial Court No. 2018R08345

Honorable Sheva M. Sims, Judge

*****

JOEY W. HENDRIX Counsel for Appellant

GREENWALD LAW FIRM, L.L.C. Counsel for Appellee By: Joseph W. Greenwald, Jr.

*****

Before MOORE, GARRETT, and THOMPSON, JJ.

THOMPSON, J.

This contract dispute matter arises from Shreveport City Court, Caddo Parish, Louisiana, the Honorable Sheva M. Sims presiding. Defendant John P. Sipes (“Sipes”) appeals the trial court’s judgment granting Plaintiff Robert E. Redstone, III (“Redstone”), damages resulting from Sipes’ alleged incomplete and faulty renovation work on a building Redstone owned. For the following reasons, we affirm.

FACTS

In 2018, Redstone hired Sipes to renovate portions of a building Redstone owned in Shreveport, Louisiana, to be used for his insurance business. The “contract,” drafted by Sipes, consisted of one small piece of paper with general items listed and “$25,000” written under Sipes’ name. A copy of the contract is reproduced below.

The work consisted of remodeling the interior of the building to create a conference room, two offices, a hallway, and the contested allocation of costs for a bathroom. Redstone was responsible for paying for the items identified.

Sipes began the renovation work in the last week of May 2018. By July

20, 2018, Redstone had paid the total Figure 1: Redstone’s Exhibit A - the contract price of $25,000 to Sipes, including “contract” between the parties

an additional $3,000 as an advance for plumbing work in the bathroom to be performed by Sipes. By the end of July, the project, now seriously delinquent, was still not finished so Redstone terminated Sipes’ services and hired new contractors to complete the renovation.

There was substantial and widespread substandard work performed by Sipes which required replacement and repair before the uncompleted items could be addressed and the project completed. Multiple photographs depicting the state of the work were introduced in the record. The new contractors undertook repair and replacement of the defects and then completed the building of the bathroom and completion of the building. Redstone, already having paid Sipes $28,000 for the project, incurred $17,089.72 in additional costs to repair and complete the project.

On August 22, 2018, Redstone sent a demand letter to Sipes requesting payment for a portion of the damages incurred from hiring new contractors. This effort was fruitless. On October 11, 2018, Redstone filed suit against Sipes, asserting that he incurred substantial costs to complete the renovation and that Sipes is liable unto him for, inter alia, breach of contract, negligently performing the renovation work, and failing to perform the renovation in a timely manner. In reply, on October 25, 2018, Sipes filed an answer, admitting that there was a contract between the parties, but asserting that that Sipes had completed 90% of the project before being fired from the job.

A bench trial was held on April 30, 2019. Redstone sought a total reimbursement of the $17,089.72 incurred to remedy and complete the project. Submitted into evidence were photographs and videos of Sipes’

work, as well as a list of expenses incurred by Redstone to hire new contractors.1 Paramount to the appeal before us was the issue of who was responsible for paying for the construction of the bathroom.

Conflicting testimony was provided regarding the scope of the contract and the responsibilities of the parties. Redstone testified that, over the course of the project, Sipes readily began renovating the bathroom. Specifically, after Redstone paid the full contract price, Sipes requested and received an additional $3,000 as an advance for plumbing work. Sipes and his crew spent a considerable amount of time sawing out concrete and used a jackhammer to run the plumbing into Redstone’s office. However, Redstone terminated Sipes because of the poor quality of the work done and the delays in completing the project.

Redstone noted that he had planned to relocate his office, so he disconnected telephone and internet connections along the timeline given to him by Sipes for the project to be completed. When the project was continually delayed he and his employees were unable to work and operate Redstone’s insurance business for four weeks. No damages were sought or awarded for the business interruption expenses which may have been occasioned to Redstone. The delays and quality of the work were unacceptable to Redstone and were what led to Sipes’ termination.

Harold Myers (“Myers”), Sipes’ plumber, testified that he was hired by Sipes to perform the plumbing work in the bathroom. Myers stated that he performed the plumbing work at Sipes’ direction and was paid by Sipes for his services.

1 See Figure 2: list of expenses submitted by Redstone at trial.

Sipes testified that the contract clearly listed “plumber (bath) labor” as expenses covered by Redstone. Sipes stated that the $3,000 advance was to prepare the room to install the plumbing. At trial, Sipes provided receipts which represented the amount he spent on labor and plumbing. Otis Smalley, Sipes’ subcontractor, testified that Sipes told him that he (Sipes) was not finishing out the bathroom.

Sipes claimed that he was wrongfully terminated and that, when he left on his vacation, everything was fine. Sipes asserted he could complete the project, remedy any defects, and that in so doing the costs would have been much less than the amount sought by Redstone.

The trial court found that “the contract [was] ambiguous in part” and that Redstone “tendered a total of approximately [$28,000] to the defendant for work to be performed.” The court ruled that “the work was faulty and/or not completed in a timely manner” and therefore ruled in favor of Redstone against Sipes for the full and final amount of $17,089.72 incurred to remedy and complete the project, plus court costs. The trial court signed a judgment to that accord on May 30, 2019. This appeal ensued.

STANDARD OF REVIEW

In the case of ambiguity in a contract, where factual findings are pertinent to the interpretation of a contract, those factual findings are not to be disturbed unless manifest error is shown. Campbell v. Melton, 01-2578 (La. 05/14/02), 817 So. 2d 69; BRP LLC (Delaware) v. MC Louisiana Minerals, LLC, 50,549 (La. App. 2 Cir. 05/18/16), 196 So. 3d 37.

DISCUSSION

In his appeal, Sipes asserts two assignments of error:

1. The trial court erred in finding that Sipes was responsible for building the bathroom.

2. The trial court erred in awarding $17,089.72.

In his first assignment of error, Sipes argues that the cost of finishing out the bathroom was not contemplated in the contract. Sipes asserts the contract listed the items Redstone was to pay for, which clearly included “plumber (bath) labor.” Citing La. C.C. art. 2046, Sipes states that the contract was clear and explicit, and thus, no further interpretation may be made in search of the parties’ intent.

A contract is an agreement by two or more parties whereby obligations are created, modified, or extinguished. La. C.C. art. 1906. Interpretation of a contract is the determination of the common intent of the parties. La. C.C. art. 2045. When the words of a contract are clear and explicit and lead to no absurd consequences, no further interpretation may be made in search of the parties’ intent. La. C.C. art. 2046.

Free access — add to your briefcase to read the full text and ask questions with AI

Robert E. Redstone, III v. John P. Sipes, (La. Ct. App. 2020).

Robert E. Redstone, III v. John P. Sipes (Robert E. Redstone, III v. John P. Sipes) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Slocum-Stevens Ins. Agency, Inc. v. International Risk Consultants, Inc.
666 So. 2d 352 (Louisiana Court of Appeal, 1995)
Perow v. Lenzly
716 So. 2d 519 (Louisiana Court of Appeal, 1998)
Miller v. Miller
1 So. 3d 815 (Louisiana Court of Appeal, 2009)
UNITED INVESTORS LIFE v. Alexander
662 So. 2d 831 (Louisiana Court of Appeal, 1995)
Industrial Roofing v. Jc Dellinger Mem.
751 So. 2d 928 (Louisiana Court of Appeal, 1999)
Rosell v. Esco
549 So. 2d 840 (Supreme Court of Louisiana, 1989)
Campbell v. Melton
817 So. 2d 69 (Supreme Court of Louisiana, 2002)
MB Industries, LLC v. CNA Insurance Co.
74 So. 3d 1173 (Supreme Court of Louisiana, 2011)
Akers v. Bernhard Mechanical Contractors, Inc.
137 So. 3d 818 (Louisiana Court of Appeal, 2014)
Mosley v. Griffin
191 So. 3d 16 (Louisiana Court of Appeal, 2016)
BRP LLC v. MC Louisiana Minerals LLC
196 So. 3d 37 (Louisiana Court of Appeal, 2016)