Robert E. Redstone, III v. John P. Sipes

CourtLouisiana Court of Appeal
DecidedApril 22, 2020
Docket53,416-CA
StatusPublished

This text of Robert E. Redstone, III v. John P. Sipes (Robert E. Redstone, III v. John P. Sipes) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robert E. Redstone, III v. John P. Sipes, (La. Ct. App. 2020).

Opinion

Judgment rendered April 22, 2020. Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.

No. 53,416-CA

COURT OF APPEAL SECOND CIRCUIT STATE OF LOUISIANA

*****

ROBERT E. REDSTONE, III Plaintiff-Appellee

versus

JOHN P. SIPES Defendant-Appellant

Appealed from Shreveport City Court for the Parish of Caddo, Louisiana Trial Court No. 2018R08345

Honorable Sheva M. Sims, Judge

JOEY W. HENDRIX Counsel for Appellant

GREENWALD LAW FIRM, L.L.C. Counsel for Appellee By: Joseph W. Greenwald, Jr.

Before MOORE, GARRETT, and THOMPSON, JJ. THOMPSON, J.

This contract dispute matter arises from Shreveport City Court, Caddo

Parish, Louisiana, the Honorable Sheva M. Sims presiding. Defendant John

P. Sipes (“Sipes”) appeals the trial court’s judgment granting Plaintiff

Robert E. Redstone, III (“Redstone”), damages resulting from Sipes’ alleged

incomplete and faulty renovation work on a building Redstone owned. For

the following reasons, we affirm.

FACTS

In 2018, Redstone hired Sipes to renovate portions of a building

Redstone owned in Shreveport, Louisiana, to be used for his insurance

business. The “contract,” drafted by Sipes, consisted of one small piece of

paper with general items listed and “$25,000” written under Sipes’ name. A

copy of the contract is reproduced below.

The work consisted of

remodeling the interior of the building

to create a conference room, two

offices, a hallway, and the contested

allocation of costs for a bathroom.

Redstone was responsible for paying

for the items identified.

Sipes began the renovation work

in the last week of May 2018. By July

20, 2018, Redstone had paid the total Figure 1: Redstone’s Exhibit A - the contract price of $25,000 to Sipes, including “contract” between the parties an additional $3,000 as an advance for plumbing work in the bathroom to be

performed by Sipes. By the end of July, the project, now seriously

delinquent, was still not finished so Redstone terminated Sipes’ services and

hired new contractors to complete the renovation.

There was substantial and widespread substandard work performed by

Sipes which required replacement and repair before the uncompleted items

could be addressed and the project completed. Multiple photographs

depicting the state of the work were introduced in the record. The new

contractors undertook repair and replacement of the defects and then

completed the building of the bathroom and completion of the building.

Redstone, already having paid Sipes $28,000 for the project, incurred

$17,089.72 in additional costs to repair and complete the project.

On August 22, 2018, Redstone sent a demand letter to Sipes

requesting payment for a portion of the damages incurred from hiring new

contractors. This effort was fruitless. On October 11, 2018, Redstone filed

suit against Sipes, asserting that he incurred substantial costs to complete the

renovation and that Sipes is liable unto him for, inter alia, breach of

contract, negligently performing the renovation work, and failing to perform

the renovation in a timely manner. In reply, on October 25, 2018, Sipes

filed an answer, admitting that there was a contract between the parties, but

asserting that that Sipes had completed 90% of the project before being fired

from the job.

A bench trial was held on April 30, 2019. Redstone sought a total

reimbursement of the $17,089.72 incurred to remedy and complete the

project. Submitted into evidence were photographs and videos of Sipes’

2 work, as well as a list of expenses incurred by Redstone to hire new

contractors.1 Paramount to the appeal before us was the issue of who was

responsible for paying for the construction of the bathroom.

Conflicting testimony was provided regarding the scope of the

contract and the responsibilities of the parties. Redstone testified that, over

the course of the project, Sipes readily began renovating the bathroom.

Specifically, after Redstone paid the full contract price, Sipes requested and

received an additional $3,000 as an advance for plumbing work. Sipes and

his crew spent a considerable amount of time sawing out concrete and used a

jackhammer to run the plumbing into Redstone’s office. However, Redstone

terminated Sipes because of the poor quality of the work done and the delays

in completing the project.

Redstone noted that he had planned to relocate his office, so he

disconnected telephone and internet connections along the timeline given to

him by Sipes for the project to be completed. When the project was

continually delayed he and his employees were unable to work and operate

Redstone’s insurance business for four weeks. No damages were sought or

awarded for the business interruption expenses which may have been

occasioned to Redstone. The delays and quality of the work were

unacceptable to Redstone and were what led to Sipes’ termination.

Harold Myers (“Myers”), Sipes’ plumber, testified that he was hired

by Sipes to perform the plumbing work in the bathroom. Myers stated that

he performed the plumbing work at Sipes’ direction and was paid by Sipes

for his services.

1 See Figure 2: list of expenses submitted by Redstone at trial.

3 Sipes testified that the contract clearly listed “plumber (bath) labor” as

expenses covered by Redstone. Sipes stated that the $3,000 advance was to

prepare the room to install the plumbing. At trial, Sipes provided receipts

which represented the amount he spent on labor and plumbing. Otis

Smalley, Sipes’ subcontractor, testified that Sipes told him that he (Sipes)

was not finishing out the bathroom.

Sipes claimed that he was wrongfully terminated and that, when he

left on his vacation, everything was fine. Sipes asserted he could complete

the project, remedy any defects, and that in so doing the costs would have

been much less than the amount sought by Redstone.

The trial court found that “the contract [was] ambiguous in part” and

that Redstone “tendered a total of approximately [$28,000] to the defendant

for work to be performed.” The court ruled that “the work was faulty and/or

not completed in a timely manner” and therefore ruled in favor of Redstone

against Sipes for the full and final amount of $17,089.72 incurred to remedy

and complete the project, plus court costs. The trial court signed a judgment

to that accord on May 30, 2019. This appeal ensued.

STANDARD OF REVIEW

In the case of ambiguity in a contract, where factual findings are

pertinent to the interpretation of a contract, those factual findings are not to

be disturbed unless manifest error is shown. Campbell v. Melton, 01-2578

(La. 05/14/02), 817 So. 2d 69; BRP LLC (Delaware) v. MC Louisiana

Minerals, LLC, 50,549 (La. App. 2 Cir. 05/18/16), 196 So. 3d 37.

DISCUSSION

In his appeal, Sipes asserts two assignments of error:

4 1. The trial court erred in finding that Sipes was responsible for building the bathroom.

2. The trial court erred in awarding $17,089.72.

In his first assignment of error, Sipes argues that the cost of finishing

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Slocum-Stevens Ins. Agency, Inc. v. International Risk Consultants, Inc.
666 So. 2d 352 (Louisiana Court of Appeal, 1995)
Perow v. Lenzly
716 So. 2d 519 (Louisiana Court of Appeal, 1998)
Miller v. Miller
1 So. 3d 815 (Louisiana Court of Appeal, 2009)
UNITED INVESTORS LIFE v. Alexander
662 So. 2d 831 (Louisiana Court of Appeal, 1995)
Industrial Roofing v. Jc Dellinger Mem.
751 So. 2d 928 (Louisiana Court of Appeal, 1999)
Rosell v. Esco
549 So. 2d 840 (Supreme Court of Louisiana, 1989)
Campbell v. Melton
817 So. 2d 69 (Supreme Court of Louisiana, 2002)
MB Industries, LLC v. CNA Insurance Co.
74 So. 3d 1173 (Supreme Court of Louisiana, 2011)
Akers v. Bernhard Mechanical Contractors, Inc.
137 So. 3d 818 (Louisiana Court of Appeal, 2014)
Mosley v. Griffin
191 So. 3d 16 (Louisiana Court of Appeal, 2016)
BRP LLC v. MC Louisiana Minerals LLC
196 So. 3d 37 (Louisiana Court of Appeal, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Robert E. Redstone, III v. John P. Sipes, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robert-e-redstone-iii-v-john-p-sipes-lactapp-2020.