Rapides Const., Inc. v. Gaspard

411 So. 2d 81, 1982 La. App. LEXIS 6759
CourtLouisiana Court of Appeal
DecidedFebruary 3, 1982
Docket8587
StatusPublished
Cited by4 cases

This text of 411 So. 2d 81 (Rapides Const., Inc. v. Gaspard) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rapides Const., Inc. v. Gaspard, 411 So. 2d 81, 1982 La. App. LEXIS 6759 (La. Ct. App. 1982).

Opinion

411 So.2d 81 (1982)

RAPIDES CONSTRUCTION, INC., Plaintiff-Appellee,
v.
Pierson A. GASPARD, Defendant-Appellant.

No. 8587.

Court of Appeal of Louisiana, Third Circuit.

February 3, 1982.

Charles F. Wagner, Pineville, for defendant-appellant.

Gold, Little, Simon, Weems & Bruser, Larry Feldman, Jr., Alexandria, for plaintiff-appellee.

Before DOMENGEAUX, DOUCET and LABORDE, JJ.

LABORDE, Judge.

This is a suit to recover the balance due in a building contract. Plaintiff-Contractor, Rapides Construction, Inc., sued defendant, Pierson A. Gaspard, seeking to recover the balance due upon a contract's substantial completion and to recover attorney's fees as provided for in the contract. After hearing extensive testimony presented by both plaintiff and defendant, the trial court rendered judgment in favor of plaintiff in the amount of $9,166.05, representing the balance owed less credits for necessary repairs undertaken by defendant. Legal interest was allowed from April 10, 1980. Plaintiff was also awarded $2,500.00 in attorney's fees and its lien was recognized. In defendant's favor, judgment was rendered in the amount of $1,000.00 for his loss of income, with legal interest from date of judicial demand. From the judgment, defendant appeals and plaintiff answers the appeal.

The issues concern the factual findings regarding the construction project's substantial completion; the amounts allowed as credits of the balance due for costs of necessary repairs; the loss of income award; and the attorney's fee award.

*82 The trial judge rendered comprehensive written reasons detailing his findings, conclusions, and awards. Close scrutiny of the extensive trial record reveals not only that the trial judge's conclusions are free of manifest error and that his awards are within the range of his wide discretion, but also that they are fully supported by the evidence adduced. Arceneaux v. Domingue, 365 So.2d 1330 (La.1978); LSA-C.C. art. 1934(3). Hence, we take the liberty of adopting as our own the well-reasoned and considered opinion of the trial court which reads in its entirety as follows:

"This is a suit by plaintiff to recover the balance due upon substantial completion of a building contract.

On April 27, 1979, plaintiff, Rapides Construction, Inc. entered into a building contract, (P-1), with defendant, Pierson Gaspard, to construct a pre-fabricated, metal frame building for the agreed upon consideration of $25,699.00.

Upon 90 per cent completion of each of four phases of construction, the contract provided for step-payments, consisting of 90 per cent of the total contract price of each phase. The remaining 10 per cent of the contract price was to be withheld as a retainage, payable upon final completion and approval of the construction project. All work to be completed under the contract by plaintiff was bonded by American Fidelity Fire Insurance Company as of July 20, 1979, (P-2).

By August 28, 1979, the first phase of construction had been 90 per cent completed, with defendant making his first step-payment on August 31, 1979.

On September 27, 1979, plaintiff requested payment for the second and third phases of the construction project. However, defendant refused payment by letter, dated October 4, 1979, (D-1), indicating that the work had not been performed in a workmanlike manner, nor in the manner agreed upon in their contract.

On October 12, 1979, a certified letter of demand was mailed to defendant by plaintiff's attorney, (P-3).

On October 23, 1979, plaintiff requested Philip Beard, a consulting engineer from Alexandria, Louisiana, to inspect the project, formulate a determination as to its percentage of completion and verify a punch list of items needing correction, submitted by defendant in his above-mentioned letter.

The inspection was carried out and a report was formulated on October 25, 1979, (P-4). According to Beard, the first three phases of the construction project were all at least 90 per cent complete. Included in this report was a list of items enumerated by defendant and additional items noted by Beard as needing completion.

On December 20, 1979, plaintiff filed an affidavit of lien, (P-7), on defendant's property, a copy of which was sent to defendant by certified mail, (P-5 and P-6), on December 21, 1979.

Subsequently, suit was filed by plaintiff against defendant on December 20, 1979, seeking payment for the last three phases of construction, plus attorney's fees and cost. On January 10, 1980, defendant answered and filed a reconventional demand against plaintiff, ordering the latter to complete the unfinished construction, correct all defects as outlined in his pleadings and pay damages resulting from the breach.

Subsequently, the parties, through the efforts of their attorney and Phillip Beard, attempted to negotiate their differences. As a result of the negotiations, a written agreement, modifying the original contract, was formulated on February 7, 1980. This agreement was further modified on February 26, 1980, (P-9), and signed by the parties.

The modified agreement contained eighteen proposals outlining work to be completed by plaintiff. The proposals were divided into four phases, each requiring payment by defendant upon plaintiff's completion. The total new consideration was $17,620.00.

The agreement reads as follows:

`Contractor shall notify Arbitrator of stage completion and forward to Arbitrator *83 written request for payment. Arbitrator will make inspection to verify compliance as required by this document and forward request for payment to Owner. Owner shall make progress payments within 10 days after receipt of Authorization by Arbitrator.

21. Time of Completion: Contract shall accomplish Proposals # 1 through # 18 not later than April 7, 1980.' (P-9, page 6) All other agreements between the parties including the original contract of April 27, 1979, were made a part of this modified agreement by reference and attached thereto.

Upon signing the above agreement, work was recommenced. On March 13, 1980, an invoice (P-10), was sent defendant in care of Beard, authorizing payment for substantial completion of the first phase of construction under the modified agreement. Defendant made this payment of $5,429.63.

On April 1, 1980, Beard sent a letter to plaintiff constituting the third and, what he considered to be, the final attempt to have certain listed items corrected, (D3). The letter went on to read as follows:

`... You have until 5:00 p. m., April 7, 1980 to perform substantial completion. No further payments will be forthcoming until you satisfy all parties concerned with substantial effort.'

On April 10, 1980, three days beyond the stipulated date for completion of the construction project, Beard mailed a letter to defendant, (P-11), authorizing payment for substantial completion of further work done on the construction project. Accompanying this letter was a certificate of substantial completion as of April 9, 1980, (P-12), signed by Beard. Authorized payment was in the amount of $9,330.07, with 10 per cent of the contract price to be held by defendant as retainage for work yet to be completed. Defendant refused to make payment.

On August 27, 1980, plaintiff filed a supplemental and amending petition, seeking the remainder of the contract price, $12,224.97, plus attorney's fees of $5,000.00. Defendant then answered and reconvened for $6,617.80, representing sums he expended to complete the construction. After further negotiations and a pre-trial conference, the matter went to trial February 12, 1981.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Industrial Roofing v. Jc Dellinger Mem.
751 So. 2d 928 (Louisiana Court of Appeal, 1999)
Salard v. Jim Walter Homes, Inc.
563 So. 2d 1327 (Louisiana Court of Appeal, 1990)
Orgeron v. Dobkowski
476 So. 2d 458 (Louisiana Court of Appeal, 1985)
Picard Building Corp. v. Tramonte
432 So. 2d 1151 (Louisiana Court of Appeal, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
411 So. 2d 81, 1982 La. App. LEXIS 6759, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rapides-const-inc-v-gaspard-lactapp-1982.