Regions Bank v. ARK-LA-TEX WATER GARDENS

997 So. 2d 734, 2008 La. App. LEXIS 1415, 2008 WL 4791906
CourtLouisiana Court of Appeal
DecidedNovember 5, 2008
Docket43,604-CA
StatusPublished
Cited by15 cases

This text of 997 So. 2d 734 (Regions Bank v. ARK-LA-TEX WATER GARDENS) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Regions Bank v. ARK-LA-TEX WATER GARDENS, 997 So. 2d 734, 2008 La. App. LEXIS 1415, 2008 WL 4791906 (La. Ct. App. 2008).

Opinion

997 So.2d 734 (2008)

REGIONS BANK, Plaintiff-Appellee
v.
ARK-LA-TEX WATER GARDENS, L.L.C. and John Troy Cash, Jr., Defendants-Appellants.

No. 43,604-CA.

Court of Appeal of Louisiana, Second Circuit.

November 5, 2008.
Rehearing Denied November 25, 2008.

*735 Ray C. Mayo, Jr., for Appellant.

Glenn L. Langley, Shreveport, for Appellee.

Before WILLIAMS, GASKINS and CARAWAY, JJ.

WILLIAMS, J.

The defendants, Ark-La-Tex Water Gardens, L.L.C. and John Cash, Jr., appeal a judgment in favor of the plaintiff, Regions Bank. The trial court awarded damages of $202,878.05 to plaintiff, finding that the defendants failed to complete the contractual obligation in a timely and satisfactory manner. For the following reasons, we amend and affirm as amended.

*736 FACTS

In the summer of 2004, Lewis Norton, who was chairman of the board of directors of the R.W. Norton Art Foundation, contacted John Cash to discuss construction of a water feature on the grounds of the R.W. Norton Art Gallery, which is located in Shreveport and owned by the foundation. Norton had read a magazine article discussing a water feature installed by Cash at a private residence. After visiting the gallery site, Cash presented a drawing depicting a tiered feature with water flowing 35 feet downhill into a holding pond. At the time, Norton approved the plan.

In December 2004, the parties entered into a contract for construction of a water feature by Ark-La-Tex Water Gardens, L.L.C. ("Ark-La-Tex") for a price of $292,616 to be paid in three installments. The contract provided that work would commence in January 2005 and be "substantially completed on or before March 31, 2005. Time is of the essence." The timing was important because of the azalea blooming season, which was a popular public attraction at the art gallery.

During construction, Norton told Cash about problems with workers trampling the azalea bushes and with construction delays after the supervisor, Mike Allen, quit the job in the first month. Ark-La-Tex failed to complete the work by March 31, 2005, as required in the contract. However, Norton allowed Cash additional time to finish the project. The water feature was substantially completed and activated in July 2005, when Ark-La-Tex received the final payment of the total $292,616 price.

A short time later, Norton complained that the water level in the lower pond was dropping approximately two inches daily and that the water flow rate was inadequate to carry leaves and debris down through the system. Cash was called to the site numerous times to address these problems and he adjusted areas where water was spilling over the liner, but he was unable to stop the water loss or improve the flow rate to Norton's satisfaction. In January 2006, Norton discharged Cash after he failed to appear at the site as promised to resolve the continuing problems with the liner in the lower pond.

Norton then consulted Mike Spencer, who was employed by Backyard Superstore, L.L.C. ("Backyard"). Spencer evaluated the water feature and suggested several modifications to correct the problems with the system. Norton then hired Backyard, which took apart and rebuilt the water feature. Norton paid a total of $202,878.05 for the renovation.

Subsequently, the plaintiff, Regions Bank, the trustee of the R.W. Norton Art Foundation, filed a petition for damages against the defendants, Ark-La-Tex and John Cash, Jr., individually, alleging breach of the contract due to defective performance and breach of Cash's professional duty. After a bench trial, the court found that Cash failed to complete his obligation in a timely and satisfactory manner, requiring the plaintiff to hire a third party to rebuild a substantial part of the construction. The court further found that Ark-La-Tex was an alter ego of Cash, making him personally liable for the plaintiff's damages. The trial court rendered judgment awarding damages in the amount of $202,878.05. Defendants appeal the judgment.

DISCUSSION

The defendants contend the trial court erred in its application of law to the facts of this case. Defendants argue that they are not liable under LSA-C.C. art. 2769 because the plaintiff failed to prove that the water loss and flow rate problems *737 were defects caused by faulty workmanship.

When a party fails to do the work he has contracted to perform, or does not execute it in the manner and at the time agreed, he shall be liable in damages for the losses that ensue from noncompliance with the contract. LSA-C.C. art. 2769. In order to recover damages from a contractor for defective workmanship, the landowner must establish: (1) that defects exist, (2) that faulty materials or workmanship caused the defects, and (3) the cost of repairing the defects. Industrial Roofing & Sheet Metal Works, Inc. v. Dellinger Memorial Trust, 32,048 (La.App. 2d Cir.8/20/99), 751 So.2d 928, writs denied, 99-2948, 99-2958 (La.12/17/99), 752 So.2d 166; Nichols Ford Co., Inc. v. Hughes, 292 So.2d 345 (La.App. 2d Cir. 1974).

LSA-C.C. art. 1994 provides that an obligor is liable for the damages caused by his failure to perform a conventional obligation as a result of nonperformance, defective performance or delay in performance. Damages are measured by the loss sustained by the obligee. LSA-C.C. art. 1995. A trial court's factual findings will not be reversed unless clearly wrong. A reviewing court must determine whether the factfinder's conclusions were reasonable based upon the entire record. Stobart v. State DOTD, 617 So.2d 880 (La. 1993).

In the present case, Louis Norton testified that he and John Cash signed a contract in December 2004 providing that Ark-La-Tex would build a water pond feature at the Norton Art Gallery for a price of $292,616. Norton stated that Cash agreed to finish the project within 90 days in time for the blooming of the azalea plants. Norton testified that he looked at two other water features built by Cash that were much smaller than the one proposed for the gallery. Norton stated that Cash represented he could build the significantly larger pond feature even though he had not previously built a project of that size. Norton testified that Cash failed to complete the project by the contract deadline, but he was given additional time and the water feature was activated in July 2005.

Norton stated that a short time later he noticed that the water level in the lower pond was dropping one to one-and-one-half inches daily, indicating that the pond was losing hundreds of gallons of water each day. Norton testified that Cash believed that the water loss was likely due to evaporation and that Cash was unable to find any leaks. Norton stated that another problem was that although he liked the sound of the water flowing down to the pond he was not satisfied with the flow rate, which was not adequate to clear fallen leaves from the water surface. Norton testified that there were ongoing problems with water splashing over the unsecured liner in the stream area and with the liner in the lower pond repeatedly sliding into the water. Norton stated that in response to his complaints Cash and his workers regularly went to the site, but they were unable to repair the problems of water loss and insufficient flow rate. Norton testified that in January 2006 he spoke with Cash, who promised that the problems would be repaired the next day. Norton stated that when the workers did not show up as promised he fired Cash from the job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hester v. Burns Builders
246 So. 3d 40 (Louisiana Court of Appeal, 2018)
Lynton O. Hester, IV v. Burns Builders
Louisiana Court of Appeal, 2018
Jennifer Diane Nunez v. Pinnacle Homes, L.L.C. and Sua Insurance Company
180 So. 3d 285 (Supreme Court of Louisiana, 2015)
Nunez v. Pinnacle Homes, L.L.C.
158 So. 3d 71 (Louisiana Court of Appeal, 2014)
McConnell v. Servinsky Engineering, PLLC
22 F. Supp. 3d 610 (W.D. Virginia, 2014)
Jennifer Diane Nunez v. Pinnacle Homes, LLC
Louisiana Court of Appeal, 2014
Hector v. Mo-Dad Environmental Serv., LLC
134 So. 3d 133 (Louisiana Court of Appeal, 2014)
Ogea v. Merritt
130 So. 3d 888 (Supreme Court of Louisiana, 2013)
Ogea v. Merritt
109 So. 3d 516 (Louisiana Court of Appeal, 2013)
Mary P. Ogea v. Travis Merritt
Louisiana Court of Appeal, 2013
RJAM, Inc. v. Miletello
103 So. 3d 503 (Louisiana Court of Appeal, 2012)
Matherne v. Barnum
94 So. 3d 782 (Louisiana Court of Appeal, 2012)
Maxwell v. Cayse
54 So. 3d 118 (Louisiana Court of Appeal, 2010)
Donald Joe Maxwell v. Daniel (Danny") Cayse "
Louisiana Court of Appeal, 2010
Lewis v. La Adrienne, Inc.
17 So. 3d 1007 (Louisiana Court of Appeal, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
997 So. 2d 734, 2008 La. App. LEXIS 1415, 2008 WL 4791906, Counsel Stack Legal Research, https://law.counselstack.com/opinion/regions-bank-v-ark-la-tex-water-gardens-lactapp-2008.