Guy T. Williams Realty, Inc. v. Shamrock Const.

564 So. 2d 689, 1990 La. App. LEXIS 1567, 1990 WL 79844
CourtLouisiana Court of Appeal
DecidedJune 6, 1990
Docket90-CA-54
StatusPublished
Cited by16 cases

This text of 564 So. 2d 689 (Guy T. Williams Realty, Inc. v. Shamrock Const.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guy T. Williams Realty, Inc. v. Shamrock Const., 564 So. 2d 689, 1990 La. App. LEXIS 1567, 1990 WL 79844 (La. Ct. App. 1990).

Opinion

564 So.2d 689 (1990)

GUY T. WILLIAMS REALTY, INC.
v.
SHAMROCK CONSTRUCTION COMPANY, INC.

No. 90-CA-54.

Court of Appeal of Louisiana, Fifth Circuit.

June 6, 1990.
Rehearing Denied August 17, 1990.

*690 Joseph F. Roy, P.L.C., Metairie, for appellee, Elliot J. Hano.

Stanley McDermott, Jr., Quentin F. Urquhart, Jr., Montgomery, Barnett, Brown, Read, Hammond and Mintz, New Orleans, *691 for plaintiff/appellee, Guy T. Williams Realty, Inc.

J. Mark Rolling, Hammond, for third party-defendant/appellant, Francis J. Mercante.

A.J. Lentini, Hall, Lentini, Mouledoux & Wimberly, Metairie, for defendant-appellant, Shamrock Const. Co.

Before BOWES, GAUDIN and GRISBAUM, JJ.

BOWES, Judge.

Plaintiff, Guy T. Williams Realty, Inc. (Williams) filed suit against defendant, Shamrock Construction Co., Inc. (Shamrock) for damages for breach of contract due to the allegedly defective construction of an office building in Hammond, Louisiana.

Shamrock filed third party demands against its various subcontractors, Henry Gill, d/b/a Skipper's Construction Company, Inc. (Gill), Mid-Parish Roofing and Sheet Metal, Inc., (Mid-Parish), Glen Henson, d/b/a Henson's Refrigeration, (Henson) Jimmy Schliegilmeyer d/b/a J.J.'s Electrical and Plumbing (J.J.'s). Shamrock further filed a third party demand against Francis Mercante, (Mercante) surety in the payment and performance bond furnished by Henry Gill, and against Elliot Hano, the architect for the project. Shamrock also filed a reconventional demand against Williams for work performed outside the scope of the building contract and for maintenance work done by Shamrock for plaintiff.

Francis Mercante filed cross-claims against Gill, Mid-Parish, Henson, and J.J.'s.

Gill filed a cross-claim against Mid-Parish and Henson.

Trial was held on February 13, 1986, April 28, 1986, April 14, 1987 and May 31, 1988.

On June 28, 1989 the trial court rendered judgment in favor of Williams and against Shamrock on Williams' main demand for $21,860.00, plus legal interest and costs. Shamrock's reconventional demand against Williams was denied. The trial court further rendered judgment in favor of Shamrock on its third party demands against Gill and his surety, Francis Mercante, and Mid-Parish for the amount which Shamrock had been cast, plus legal interest and costs.

Both Shamrock and Mercante have filed motions for appeal.

FACTS

In August of 1979, plaintiff entered into a building contract with Shamrock for the construction of a commercial office building in Hammond, La. This building was to be modeled after a building in Covington, which plaintiff believed had also been constructed by Shamrock. Williams later discovered that Shamrock had not constructed the Covington building.

The plans for the Williams building were drawn by Elliot Hano, an architect hired by Shamrock through Tommy Wulff, who was vice president of Shamrock. Hano testified that Shamrock's representative, Tommy Wulff, showed him a set of plans for another building which he said he wanted to duplicate. Wulff told Hano not to make the plans as detailed as the set he was showing Hano because they were going to build an identical building and that the set Hano was to draw up was something to get a permit and to show general intent.

Shamrock did not construct the building itself. Instead, unknown to plaintiff, it contracted the entire job to Henry Gill d/b/a Skipper's Construction Company, an almost completely inexperienced contractor, for a lesser amount.

Gill testified that he contracted with Shamrock, through Tommy Wulff, to handle the entire construction job. Gill and his surety, Mercante, selected the subcontractors hired. However, because Gill did not have a state license, Shamrock handled the financial aspects of the construction project concerning payment to the subcontractors.

Gill further testified that it was his perception that Tommy Wulff was the "field supervisor" for Shamrock. Gill and Wulff communicated on a daily basis via telephone. Such daily conversations were mandatory because Shamrock had furnished *692 Gill with a skeleton-like two page set of plans and no specifications.

Construction of the building began in October 1979. The first tenants moved into the building in December of 1979, shortly before completion. On January 22, 1980, the building was accepted by plaintiff and its financiers.

In September and October of 1980, plaintiff began to receive complaints from tenants of water leakage and water damage. Plaintiff relayed these complaints, first by telephone and then via written correspondence to Shamrock, and requested that the problem be corrected. Shamrock contacted Gill, who took no action to stop the leakage. Shamrock then attempted to correct the leakage problem by itself.

William Hogan, president of Shamrock testified that when he inspected the building he saw visible signs of water on the inside of the building. He later determined that water was coming from around the air conditioning machinery duct work. He attributed the problem to incorrect placement of the air conditioning units. In April of 1981 and in October of 1982, Shamrock conducted repair work, consisting of relocating the air conditioning units, installing new duct work and sheet metal coils, installing roof drains, adding caulking and flashing and making other remedial repairs.

Hogan testified that he conducted another inspection after completion of the repair work in December 1982 or January 1983. He discovered that the roof drain was clogged with dirt and leaves and that a large sign had been nailed to the roof.

Williams testified that, despite Shamrock's efforts, the roof continued to leak.

Because Shamrock appeared unable to remedy the leakage problem in August and September of 1982, plaintiff contacted two independent contractors, Carl Wainwright and Frank Bell, and requested inspections and appraisals to determine the cause of the leakage and the work necessary to correct the problems. Wainwright qualified as an expert in building construction and repair. Wainwright initially inspected the building in July of 1981 and found several deficiencies which relate to the leakage problem. These he relayed to Shamrock in a report, an excerpt of which follows:

General:
1) Flashing not installed on horizontal joints, causing water to leak into the walls. Batt shouldn't be installed on exterior surface.
Roof
1) Plywood not nailed properly. (Plans called for ¾" but roof feels soft).
2) Pitch pockets on air conditioners are not installed.
3) Cant strips as called for on plans are not installed.
4) Flashings as called for on plans not installed, both above windows and on side walls.
5) Air conditioner leaks when it rains caused by no insulation of ducts.
6) Plans do not call for roof drains. Why?

Wainwright inspected the building a second time in August of 1982. In a letter to Williams, he made the following findings:

1) Water 1½" deep by the air conditioner on the northernmost suite.
2) Water generally over most of the roof.
3) Water 1" deep at the roof drain.
4) Plywood buckling on the roof, causing high spots.
5) Trim falling off of window (improperly installed).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gerald v. Doucette & Associated Contractors, Inc.
229 So. 3d 667 (Louisiana Court of Appeal, 2017)
Loconte Partners, LLC v. Montgomery & Associates, Inc.
116 So. 3d 904 (Louisiana Court of Appeal, 2013)
Davis v. Russell
26 So. 3d 950 (Louisiana Court of Appeal, 2009)
Mount Mariah Baptist Church, Inc. v. Pannell's Associated Electric, Inc.
835 So. 2d 880 (Louisiana Court of Appeal, 2002)
Mt. Mariah Church v. PANNELL'S ASSOC. ELEC.
835 So. 2d 880 (Louisiana Court of Appeal, 2002)
Hernandez v. Martinez
781 So. 2d 815 (Louisiana Court of Appeal, 2001)
Industrial Roofing v. Jc Dellinger Mem.
751 So. 2d 928 (Louisiana Court of Appeal, 1999)
Dixie Roofing v. Allen Parish Sch. Bd.
690 So. 2d 49 (Louisiana Court of Appeal, 1996)
National Tea Co. v. Plymouth Rubber Co.
663 So. 2d 801 (Louisiana Court of Appeal, 1995)
Mac Sales, Inc. v. E.I. du Pont de Nemours & Co.
24 F.3d 747 (Fifth Circuit, 1994)
Bourgeois v. Louisiana Power & Light Co.
620 So. 2d 306 (Louisiana Court of Appeal, 1993)
In Interest of Baby Boy Smith
602 So. 2d 144 (Louisiana Court of Appeal, 1992)
Century Pools, Inc. v. Pinkstaff
598 So. 2d 1189 (Louisiana Court of Appeal, 1992)
Bourgeois v. Arrow Fence Co., Inc.
592 So. 2d 445 (Louisiana Court of Appeal, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
564 So. 2d 689, 1990 La. App. LEXIS 1567, 1990 WL 79844, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guy-t-williams-realty-inc-v-shamrock-const-lactapp-1990.