Hebert v. McDaniel

479 So. 2d 1029
CourtLouisiana Court of Appeal
DecidedDecember 11, 1985
Docket84-956
StatusPublished
Cited by14 cases

This text of 479 So. 2d 1029 (Hebert v. McDaniel) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hebert v. McDaniel, 479 So. 2d 1029 (La. Ct. App. 1985).

Opinion

479 So.2d 1029 (1985)

Essay J. HEBERT, Jr., Plaintiff-Appellee,
v.
Wallace McDANIEL, d/b/a Wallace McDaniel Welding Works, Defendant-Appellant.

No. 84-956.

Court of Appeal of Louisiana, Third Circuit.

December 11, 1985.

*1031 Wade A. Mouton, Kaplan, for defendant-appellant.

James E. Fontenot, Abbeville, for plaintiff-appellee.

Before FORET, YELVERTON and KING, JJ.

FORET, Judge.

In this suit for damages incurred as a result of a breach of a construction contract, the main issue is whether the roof was repairable as opposed to replaceable. Plaintiff, Essay J. Hebert, Jr. (Hebert), contracted with defendant, Wallace McDaniel, d/b/a Wallace McDaniel Welding Works (McDaniel), to have a metal building constructed on his property. Plaintiff contends that defendant's faulty workmanship caused the roof and other parts of the building to leak. The trial court found the leaks to be the result of defendant's faulty construction and awarded plaintiff the cost of replacing the roof ($10,400), two windows ($300), and the cost of long-distance phone calls expended in connection therewith ($25.81). Defendant has appealed, urging four specifications of error.

FACTS

On or about May 17, 1979, Hebert and McDaniel entered into a building contract. Hebert gave McDaniel the dimension specifications for the metal building, and McDaniel agreed to construct it at a cost of $23,286. Construction commenced on June 6, 1979, and the building was completed approximately two months later. McDaniel was paid in full at the time the building was completed.

During a rainstorm approximately one month after the building was completed, the building began to leak through the roof ledge onto the east and west sides throughout the entire structure and through the main door and windows. Hebert called McDaniel after this first rainstorm, and McDaniel and his crew arrived the following day in an attempt to seal and caulk to prevent further leakage. Unfortunately, the leaks persisted. Hebert continued to call McDaniel, and McDaniel continued to make several, apparently good-faith, attempts to repair the leaks.[1] Because the *1032 problems worsened after every attempt to repair, Hebert requested that McDaniel cease his attempts. During his last telephone conversation with McDaniel, Hebert asked McDaniel to decide on how he was going to correct the leakage problems. McDaniel was never heard from again.

A catalog of defects appears from the record: the incorrect door was installed in the 10 ft. x 10 ft. opening and thereafter another door was installed; the leaks persisted and defendant had the overhead door company try to stop the leaking; the gutters leaked due to improper installation resulting in rusted metal sheeting around the areas which leaked; vents were improperly installed with leaking as a result; the roofing screws were improperly tightened, and they were responsible for some of the leaks; a weather-approved caulking was never used; there were pinholes in the peaks of the roofcaps; the overhang was not long enough; the window flashing was improperly installed; the lap sheets were not properly caulked, and as a result, the insulation must be changed, the rusted metal sheeting must be replaced, the windows must be repaired, and some of the secondary structure also needs replacing. A litany of these problems with the building continued for five years, and none of defendant's stop-gap efforts were successful. Hebert, disgusted and worn out from several years of moving pots, pans, and pails around the attic and home, finally filed suit. One portion of the building has never been used as intended, due to the leaking.[2]

After not having heard from defendant for several months, Hebert requested estimates for the repair or replacement of the roof from several contractors. However, most of the metal building contractors he consulted would not guarantee repairs to the building and would only bid on replacing the entire roof. The contractors apparently were of the opinion that the only remedy was to replace the entire roof.

Hebert built a $70,000 home within the metal building structure. All of the woodwork was done around the metal building structure and no alterations were made to the building constructed by McDaniel. The stud walls follow the sides of the metal building all around. Plaintiff testified that thirty-nine leaks were detected in July of 1981. The leaks were so severe that even the carpet was wetted. However, plaintiff has not claimed any damages to his home. He has only requested that the roof be replaced.

THE ISSUES

Defendant has advanced four specifications of error which may be condensed into two major issues: whether or not the roof in question was repairable as opposed to replaceable, and whether or not this is a contract to build as opposed to a contract for the sale of a building. Appellant contends that this was a sale, and that therefore the court should have sustained its peremptory exception of prescription.

We believe this is a case which involves a contract to build as opposed to a contract for the sale of a building. Three major factors are used to determine whether or not a contract is one of sale or one to build: (1) The buyer has some control over the specifications of the object, (2) the negotiations generally take place before the object is constructed, and (3) the parties contemplate that one of them will supply the materials and his skill and labor in order the construct the specified object. Duhon v. Three Friends Homebuilders Corp., 396 So.2d 559, 561 (La.App. 3 Cir. 1981); Keglers, Inc. v. Levy, 239 So.2d 450 (La.App. 4 Cir.1970), writ denied, 256 La. 1150, 241 So.2d 253 (1970); Airco Refrigeration Service, Inc. v. Fink, 242 La. 73, 134 So.2d 880 (1961).

In this case, Hebert asked McDaniel to build the structure according to his specifications. *1033 He and McDaniel discussed the project on several occasions prior to the commencement of construction in June of 1979. McDaniel contracted to provide the materials and his skill and labor to build the housing. Consequently, we hold, as did the learned trial judge, that the contract entered into between the two was a building contract as opposed to a contract of sale. Wurst v. Pruyn, 250 La. 1109, 202 So.2d 268 (1967).

In brief, appellant argues that this is a redhibitory action and that prescription has run on Hebert's cause of action. However, the law in Louisiana is that redhibition applies only to contracts of sale and not to contracts to build. Duhon v. Three Friends Homebuilders Corp., supra; Caubarreaux v. Hines, 442 So.2d 898 (La.App. 3 Cir.1983), writ denied, 446 So.2d 1225 (La.1984); Catalina Pools v. Sellers, 322 So.2d 812 (La.App. 4 Cir.1975); LSA-C.C. Art. 2762. Because we have found this is a contract to build, redhibition is not applicable.

LSA-C.C. Art. 2756 defines a construction contract as:

"To build by a plot, or to work by the job, is to undertake a building or a work for a certain stipulated price."

Because the contract in the present suit is a construction contract, the rights and obligations of the parties are governed by C.C. Arts. 2756, 2762, 2768 and 2769.

"It is implied in every building contract that the work of the builder be performed in a good workmanlike manner, free from defect either in material or workmanship. Nichols Ford Co., Inc. v. Hughes, 292 So.2d 345 (La.App. 2nd Cir. 1974).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Loconte Partners, LLC v. Montgomery & Associates, Inc.
116 So. 3d 904 (Louisiana Court of Appeal, 2013)
Berkshire Medical Center, Inc. v. U.W. Marx, Inc.
644 F.3d 71 (First Circuit, 2011)
Hai Nam Chin. Rest. Part. v. B & B Const.
942 So. 2d 97 (Louisiana Court of Appeal, 2006)
Austin Homes, Inc. v. Thibodeaux
821 So. 2d 10 (Louisiana Court of Appeal, 2002)
Williams v. Alfred
748 So. 2d 42 (Louisiana Court of Appeal, 1999)
Martinez v. Reno
742 So. 2d 1014 (Louisiana Court of Appeal, 1999)
Nicholson & Loup v. Carl E. Woodward
596 So. 2d 374 (Louisiana Court of Appeal, 1992)
Guy T. Williams Realty, Inc. v. Shamrock Const.
564 So. 2d 689 (Louisiana Court of Appeal, 1990)
Hageman v. Foreman
539 So. 2d 678 (Louisiana Court of Appeal, 1989)
Brown v. Smith
527 So. 2d 606 (Louisiana Court of Appeal, 1988)
Karam v. DeSoto
520 So. 2d 1032 (Louisiana Court of Appeal, 1987)
Huguet v. Musso Partnership
509 So. 2d 91 (Louisiana Court of Appeal, 1987)
Degeneres v. Burgess
486 So. 2d 769 (Louisiana Court of Appeal, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
479 So. 2d 1029, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hebert-v-mcdaniel-lactapp-1985.