Williams v. Alfred

748 So. 2d 42, 1999 WL 994178
CourtLouisiana Court of Appeal
DecidedNovember 3, 1999
Docket99-743
StatusPublished
Cited by2 cases

This text of 748 So. 2d 42 (Williams v. Alfred) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams v. Alfred, 748 So. 2d 42, 1999 WL 994178 (La. Ct. App. 1999).

Opinion

748 So.2d 42 (1999)

Paul Rodney WILLIAMS et ux., Plaintiffs-Appellants,
v.
Eddie ALFRED, Defendant-Appellee.

No. 99-743.

Court of Appeal of Louisiana, Third Circuit.

November 3, 1999.

*43 Randall Hart, Lake Charles, for Paul Rodney Williams, et ux.

James Edward Burks, Lake Charles, for Eddie Alfred.

Before YELVERTON, SAUNDERS, and GREMILLION, Judges.

GREMILLION, Judge.

The plaintiffs, Paul and Karen Williams, appeal the judgment of the trial court finding the defendant, Eddie Alfred, fifty percent at fault for defective masonry work and awarding them damages as a result of the breach of his implied warranty of good workmanship. For the following reasons, we set aside the judgment of the trial court and render judgment in favor of the Williams awarding them damages.

FACTS

The Williams hired Alfred, a mason, to brick their new home in Carlyss, Louisiana in 1995. The parties agreed that Alfred would provide the labor in exchange for $5,750.00, while the Williams would provide all of the materials necessary to complete the job. The Williams purchased all of the materials, except the masonry sand (sand), from Herman Brown Brick Company, Inc. (HBBC). Ray Johnson, a sales representative of HBBC estimated the amount of bricks, sand, and masonry cement (cement) required for the job. This included 110 bags of cement, 12.2 cubic yards of sand, and 14,610 bricks. HBBC delivered the first load of bricks and 110 bags of cement to the work site on Friday, August 4, 1995. Alfred began work the following Monday, August 7, 1995, and finished the job approximately three weeks later.

Alfred used seventy-seven bags of cement to complete the job. Of the thirty-three bags remaining, the Williams returned twenty-seven to HBBC for credit and kept six for their personal use. When the Williams returned the unused cement to HBBC, Johnson told them, "You've got a problem." He told them that if they used all of the brick, they should have used all of the cement. A total of 15,090 bricks were delivered by HBBC. Paul estimated that approximately 400 bricks remained after Alfred finished bricking the house. One cubic yard of sand remained out of the fourteen cubic yards delivered.

A couple of weeks later the Williams began noticing cracks in the mortar located in the outer walls and the fireplace. They reported the problem to both Johnson and Alfred. When Johnson inspected the house, he noted that the mortar was white and he was able to dig the blade of his pocket knife into the mortar, indicating an insufficient amount of cement in the mortar. Alfred attempted to repair the cracks on three different occasions. However, when the Williams asked him to tear down and redo all of the brick work, Alfred refused to do any more work on the house.

*44 The Williams filed suit against Alfred seeking damages for the breach of his implied warranty of good workmanship. Alfred answered denying such a breach. Following a trial on the merits, the trial court issued oral reasons finding Alfred fifty percent at fault for failing to add sufficient cement to the mortar mix, and allocating the remaining fault to defective cement. Disregarding the estimates submitted by the Williams, the trial court held that it should only cost $8,000.00 to tear down and rebrick the whole house. However, it estimated that the Williams should only have to tear down 25% of the remaining brickwork, and awarded them $2,000.00, or 25% of $8.000.00. The trial court further awarded the Williams $3,976.00 for the amount expended in tearing down and hiring another mason to redo the fireplace. Accordingly, the trial court awarded $6,000.00 to the Williams, reduced by 50% for the defective mortar, for a total of $3,000.00. This appeal followed.

ISSUES

On appeal, the Williams raise two assignments of error. They argue that the trial court erred by not finding Alfred one hundred percent liable for their damages, and that it erred in awarding them only $6,000.00 in damages.

MANIFEST ERROR

Initially, we note that a thorough review of the record leads us to a finding that the trial court, through its actions, committed manifest error. As pointed out by the Williams, the trial court visited their home prior to rendering judgment, during which it conducted tests on the mortar with a metal probe. In rendering its decision, the trial court based its findings, in large part, on what it observed and learned during that visit. In its oral reasons, the trial court stated:

I went out to the site and I brought a piece of metal probe and I tried to chip out mortar around the house, and for the most part I was not able to do so. Most of it was just as hard and as solid as I've ever seen a brick job done. However, there were some areas that was soft and was—there was some cracking. I was not that excited about the cracking except it seemed to be a little more that I would expect. I did take into consideration the fact that Mr. Williams lives on Highway 27 not very far from the road, probably about a hundred yards from the road, and it's a heavily traveled road with a lot of heavy trucks going down that road. It might have some effect, why we had the cracking, but I do believe part of the problem is because there wasn't enough mortar in the sand. But I'm not convinced that was the only problem.
. . . .
... And I also note that the columns I looked at, I didn't see any problems with any of the columns. I mean, I really banged, chiseled away at the columns without any effect.
. . . .
So, I just estimated as probably about from the walk around the house, probably about 25% worth of damage to the outside wall of the house, and I came up with a figure of $8,000, 25% of $8,000 is $2,000 added to the amount of damage that—money Mr. Williams already expended to the fireplace area ... I can't rely upon one piece of material—one sample taken off of an area that is obvious that something's wrong with the masonry and maybe the mix to be representative of the problem throughout the outside of the house and/or chimney because of what I discovered for myself and because what the video showed, as already indicated.
... because I believe this problem will be corrected far shorter what it's going to cost to tear the whole house down, and my thinking is, there was about three or four areas of defect that I noticed of less than three to four square feet in area, and I think this can be *45 corrected pretty easily, and it shouldn't take much more than $1500 to do it.... and I'm just not convinced of that from the evidence and from what I witnessed and viewed for myself when I went out there.

A trial court is usually not permitted to visit an accident site, or in this instance, a work site, to perform tests, take measurements, or make visual observations, and then rely on its findings in deciding the matter at issue. Moncla v. Albertson's Inc., 95-1139 (La.App. 3 Cir. 1/31/96); 670 So.2d 316, writ denied, 96-0555 (La.4/19/96); 671 So.2d 921.

Disputed facts are not in the same vein as the laws of nature, geographic and historical facts, time, laws and other matters of common knowledge. The resolution of disputed issues of material fact by judicial notice is improper. Pierce v. Board of Supervisors of Louisiana State University, 392 So.2d 460 (La.App. 1st Cir.1979). Further, absolutely no foundation was laid for this evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Young
902 So. 2d 461 (Louisiana Court of Appeal, 2005)
Leday v. Safeway Ins. Co. of La.
888 So. 2d 1084 (Louisiana Court of Appeal, 2004)
Leslie Leday v. Safeway Ins. Co. of La.
Louisiana Court of Appeal, 2004

Cite This Page — Counsel Stack

Bluebook (online)
748 So. 2d 42, 1999 WL 994178, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-v-alfred-lactapp-1999.