Caubarreaux v. Hines
This text of 442 So. 2d 898 (Caubarreaux v. Hines) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Elvis CAUBARREAUX, Plaintiff-Appellant,
v.
Cicero E. HINES, et al., Defendants-Appellees.
Court of Appeal of Louisiana, Third Circuit.
Harold J. Brouillette, Marksville, for plaintiff-appellant.
Trimble, Randow, Percy, Wilson & Foote, James T. Trimble, Jr., Eugene P. Cicardo, Alexandria, for defendants-appellees.
Before DOMENGEAUX, STOKER and YELVERTON, JJ.
DOMENGEAUX, Judge.
This is a contract warranty case. The appellant, Elvis Caubarreaux, entered into a construction contract with Cicero E. Hines and John W. Fuqua (d/b/a Hines and Fuqua Construction Company and as Hines and Fuqua Swimming Pools) [hereafter referred to as "Hines and Fuqua"] to build a swimming pool in the back yard of the Caubarreaux residence. The contract specified the total cost as $15,000.00. The contract further provided that the "Contractor warrants the work to be free from defects in materials and workmanship for one year from the date of completion." The appellant sued under this clause of the contract. At trial on the merits, the trial judge determined that the defendants had breached the express warranty provisions of the contract, and therefore, judgment was rendered *899 in favor of plaintiff. From this judgment, plaintiff has devolutively appealed, seeking an increase in the damages award. Defendants answered the appeal, alleging error on the part of the trial judge in finding them liable for breach of contract.
FACTS
On August 11, 1981, Elvis Caubarreaux signed a contract for $15,000.00 with Hines and Fuqua for construction of a swimming pool in Mr. Caubarreaux's back yard. Construction commenced soon afterwards, and the pool was completed on September 1, 1981. Mr. Caubarreaux paid $7,500.00 on August 14, 1981, and a remaining amount of $7,600.00 on August 28, 1981, upon completion of the swimming pool. The extra $100.00 included the purchase of a swimming pool ladder.
Some time in October, 1981, Mr. Caubarreaux and his wife noticed a crack on the bottom of the pool, and they notified Hines and Fuqua. Mr. Hines assured the owners that a hairline crack would have no effect upon the use of the swimming pool.
In November, 1981, the crack became larger; more cracks appeared on the bottom and along the sides of the pool. During this time Mr. Fuqua drained the pool, repaired the cracks, and refilled the pool. The conditioned worsened, however; the pool lost water continuously; mud seeped through the hull and into the pool. The repaired concrete became discolored. During this time, Mr. Caubarreaux telephoned Hines and Fuqua. The testimony at trial reveals a discrepancy: Mr. Caubarreaux stated that he telephoned Hines and Fuqua repeatedly (for a total of approximately forty times for a five-month period) to report the problem with the swimming pool, and that the calls were never returned; whereas Mr. Hines testified that he received only one telephone call from Mr. Caubarreaux which he promptly returned.
In May, 1982, the pool was drained again, this time by Mr. Hines and his employee, John Cobb. For four days Mr. Cobb, under Mr. Hines' supervision, attempted to repair the cracks and fissures to stop the mud and water which was seeping into the swimming pool. At that time, the hull of the pool "floated" (a term which refers to lifting of the hull). The floating resulted in cracked and broken decking which surrounded the pool. The entire pool tilted which shifted the diving board, slide, and ladder. The whole filtration system, including the main drain, failed to function after the hull floated. Voids were created under the swimming pool because of the radical movement of the hull.
Mr. Caubarreaux notified Hines and Fuqua of the severity of the problems with the swimming pool. Mr. Caubarreaux filed suit on July 15, 1982, against Hines and Fuqua when the defects were not corrected.[1] The suit sought damages consisting of a refund of the purchase price paid for the pool ($15,000.00), the cost of demolition and removal, and for inconvenience and loss of use.[2]
A written opinion was rendered by the trial court on January 3, 1983, which held: (1) The express warranty provisions of the contract were breached by Hines and Fuqua due to negligent acts of both commission and omission; (2) The evidence clearly established that the pool was beyond repair; (3) Richardson Industries, Inc. was not a manufacturer nor did it have any agency or franchise relationship with Hines and Fuqua; therefore claims against Richardson Industries, Inc. were dismissed with prejudice to the plaintiff; (4) The cost of *900 demolition and removal of the pool was established to be $15,570.00; to replace the pool, an additional $15,100.00; and to fill in the hole left by the defective pool, without replacing the pool, $1,225.00; (5) That plaintiff was "at the very least entitled to have his back yard returned to him in its original condition" but that the Court was "unwilling to award plaintiff a new pool," and accordingly; (6) Plaintiff was entitled to judgment for the cost of demolition and removal ($15,570.00), plus the cost of refilling the hole ($1,225.00), for a total of $16,795.00, plus legal interest and costs. The trial judge held that the plaintiff was not entitled to attorney's fees and therefore denied an award of such.
ISSUE
The plaintiff alleges that the trial court erred by awarding judgment only for a portion of the damages incurred as a result of a breach of the warranty provision of the contract. The issue on appeal is whether appellant is entitled to judgment for reimbursement of the cost paid for the defective swimming pool, and for inconvenience and loss of use.
The contract entered into between Mr. Caubarreaux and defendants is a construction contract governed by La.C.C. Art. 2756.[3] We conclude that the rights and obligations of the parties under the contract in question are governed by the legal principles set forth in the Civil Code. La. C.C. Arts. 2756, 2762, 2768, and 2769. The legal principles derived from these code articles concerning construction contracts are applicable in the present suit. In Neel v. O'Quinn, 313 So.2d 286 (La.App. 3rd Cir.1975), writ denied, 319 So.2d 440 (La. 1975), we stated:
"It is implied in every building contract that the work of the builder be performed in a good workmanlike manner, free from defect either in material or workmanship. Nichols Ford Co., Inc. v. Hughes, 292 So.2d 345 (La.App. 2nd Cir. 1974).
The basic law in regard to a contractor's liability for failure to properly perform a building contract is found in LSA-C.C. Art. 2769...."
At 289.
The Code expressly provides for damages when the contractor is liable for non-compliance with the contract:
"If an undertaker fails to do the work he has contracted to do, or if he does not execute it in the manner and at the time he has agreed to do it, he shall be liable in damages for the losses that may ensue from his non-compliance with his contract."
La.C.C. Art. 2769. Further, if the defects of the work performed are such that cannot be corrected except by removing and replacing the construction, under the jurisprudence the owner may require the contractor to remove the object from his land and restore the premises to their prior condition. In addition, the owner is entitled to damages. Martin v. AAA Brick Company, Inc., 386 So.2d 987, 991 (La.App.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
442 So. 2d 898, Counsel Stack Legal Research, https://law.counselstack.com/opinion/caubarreaux-v-hines-lactapp-1983.