Hernandez v. Martinez

781 So. 2d 815, 0 La.App. 5 Cir. 1282, 2001 La. App. LEXIS 470, 2001 WL 253915
CourtLouisiana Court of Appeal
DecidedFebruary 28, 2001
DocketNo. 00-CA-1282
StatusPublished
Cited by11 cases

This text of 781 So. 2d 815 (Hernandez v. Martinez) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hernandez v. Martinez, 781 So. 2d 815, 0 La.App. 5 Cir. 1282, 2001 La. App. LEXIS 470, 2001 WL 253915 (La. Ct. App. 2001).

Opinion

I,CANNELLA, J.

Richard Martinez (Defendant and Plaintiff in reconvention) (Martinez), appeals a damage award in a carpentry contract dispute with Albert Hernandez (Plaintiff and Defendant in reconvention) (Hernandez). We affirm.

On October 19, 1996, Martinez contracted with Hernandez for custom carpentry work. Martinez hired Hernandez based on recommendations by friends and Hernandez’s assurance that he could provide and install specialty “high end” trim woodwork. The job included trimming two existing Pella windows using rosettes, fluted casings and keystones, trimming the ceiling of the foyer using a five-part cornice with five-part substrate materials, “according to selected molding”, trimming eleven door units with fluted casings, rosette and plinth blocks, constructing a wood mantel over the existing fireplace, hanging an existing antique mirror above the fireplace, removing a wet bar located under the stairway and converting the space to an entertainment area for a television and bother electronic equipment, providing new baseboard in the foyer and den, and painting the above carpentry work. The price for the job was $19,700.

As the job progressed, some changes were made. Prior to installing the wood mantel, it was redone because Martinez’s dogs damaged it. This cost an extra $557.20. The air return vent in the foyer was re-routed, which cost $325. In addition, Hernandez agreed to terminate the plumbing and perform some electrical work in the wet bar renovation for $410. Hernandez and his crew also re-routed the clothes dryer vent in the garage, patched those walls, and installed a vent for the dryer in the existing roof. This was an additional $201. Extra materials for the electronic cabinet and television configuration was billed at $130.

[817]*817On April 7, 1997, Hernandez and his crew left the job, removed all of their equipment and tools, and subsequently billed Martinez for the balance owed of $4,773.20. However, Martinez refused to pay, claiming that the work was not complete and that the workmanship of some of the wood, the installation and the paint work was poor and/or incomplete. He contended that Hernandez was hired to perform the work himself, but allowed his son and others to do work that is considered specialty work. He complained that Hernandez used inferior lumber for the rosettes, the rosettes were poorly sanded and repainted, the arches over the windows are skewed and visibly uneven, and that Hernandez replaced some defective rosettes with store bought, rather than handmade ones. Martinez further contended that Hernandez failed to install the complete eleven piece crown molding ordered from Driwood, an architectural mill-work specialty company, specifically the trim around the dentils (decorative blocks of wood that resemble teeth). Martinez claimed that the sheet rock around the entertainment area was |4not finished, the casing on the baseboard of the back den wall is uneven, and the fireplace mantel was over painted, obscuring details on the wood and metal. He also complained that other parts of the woodwork were either over or under painted. In addition, Martinez asserted that the antique mirror that was hung by Hernandez and/or his crew was destroyed when someone cleaned the back of the mirror with a solvent, causing streaks, which cannot be removed, to appear on the mirror surface.

As a result of Martinez’s refusal to pay the balance billed to him, Hernandez filed suit on September 9, 1997. Martinez responded with an answer and reconventional demand on October 29, 1997, demanding the amount of money it would cost to redo the unsatisfactory work.

A judge trial was held on November 17, 1999. On March 3, 2000, judgment was rendered in favor of Hernandez in the amount of the balance owed, $4,516, with judicial interest. The trial judge further awarded Martinez the amount of $2,000 for his damages, with judicial interest, to be offset against the amount owed to Hernandez. Further, Hernandez was ordered to release all liens filed against Martinez, his wife, and his house. In her reasons for judgment, the trial judge found that Hernandez had completed the scope of the work and that he had done more than was required in some instances. However, she also found that there were areas that were not satisfactory and needed to be redone. She only awarded $2,000 because she found that some of the complaints were trivial and that Martinez was difficult to communicate with toward the end of the job. In addition, although the trial judge found Martinez’s expert, Melvin Ziegler (Ziegler), to be credible, he failed to give a breakdown of the costs to redo the individual items.

|ROn appeal, Martinez contends that the trial judge abused her discretion in awarding inadequate damages for the incomplete and/or poor workmanship. He contends that the lowest amount that the trial judge could have awarded was $11,000 to redo all of the unsatisfactory work, based on the testimony of Ziegler.

Hernandez testified that he has been doing custom trim work for 35 years and that he receives his contracts by referrals. When he and Martinez met, they went over the job. At that time he informed Martinez that he worked with a crew that was under his supervision, but that he would also do some of the work. Hernandez stated that he is not as “hands on” in recent year’s as he used to be. The crew consisted of Hernandez’s son, Chris, Thor [818]*818Rohr, who had been with him since 1992, and his son-in-law, Mark Carroza, who worked with him from 1991 until 1998.

Hernandez testified that when he looked at the various areas of work, he noticed that the jambs on the arches over the windows were not even and did not line up with the jambs on the rectangular windows below. Because of this, he told Martinez that the work on the arches would not be perfect unless he reinstalled the windows. Martinez did not want to do that and Hernandez thought he understood that without doing so, the work over the jambs would not be perfect.

Hernandez stated that at the time the contract bid was executed, Martinez did not know what style of cornice he wanted, so Hernandez drew a rough picture of one for him to consider that was within the price quoted. Martinez did not like it, but instead supplied Hernandez with a catalog of moldings and architectural millwork made by Driwood. Martinez chose an eleven piece crown molding from the cata-logue. Hernandez stated that he did not install one piece of the molding that went around the dentils because Martinez told him that he did not want that |fipiece. According to Hernandez, he informed Martinez that the Driwood molding was more expensive than the type he had put in the estimate, but without the extra piece, the price was within the job cost. In addition, he stated that Martinez and his wife thought it was too ornate with the extra bit of molding. Hernandez said that his crew heard this discussion and Chris Hernandez, Thor Rohr and Mark Carroza testified like-wise. Both Martinez and his wife testified to the contrary. They stated that the first time this question arose was after the cornice was installed.

Hernandez testified that all of the wood he used in the job was C quality and better hardwood, which is the best grade of hardwood and does not have knots. The mill work was purchased from Ed Goldman (Goldman), who does first class specialty mill work and who enjoys an excellent reputation in the construction community. Goldman cut all of the rosettes, but some were not acceptable. Hernandez stated that he returned those to Goldman, who agreed and redid them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DBR Associates, L.L.C. v. Burnell
186 So. 3d 1225 (Louisiana Court of Appeal, 2016)
Storey v. Weaver
139 So. 3d 1079 (Louisiana Court of Appeal, 2014)
Lingoni v. Hibernia National Bank
33 So. 3d 372 (Louisiana Court of Appeal, 2010)
Davis v. Russell
26 So. 3d 950 (Louisiana Court of Appeal, 2009)
Taaffe v. Factory Direct Installations, Ltd.
13 So. 3d 562 (Louisiana Court of Appeal, 2009)
Tallulah Const. v. Ne La Delta Development
982 So. 2d 225 (Louisiana Court of Appeal, 2008)
Elliott v. Normand
976 So. 2d 738 (Louisiana Court of Appeal, 2008)
Mount Mariah Baptist Church, Inc. v. Pannell's Associated Electric, Inc.
835 So. 2d 880 (Louisiana Court of Appeal, 2002)
Mt. Mariah Church v. PANNELL'S ASSOC. ELEC.
835 So. 2d 880 (Louisiana Court of Appeal, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
781 So. 2d 815, 0 La.App. 5 Cir. 1282, 2001 La. App. LEXIS 470, 2001 WL 253915, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hernandez-v-martinez-lactapp-2001.