Gerald v. Doucette & Associated Contractors, Inc.

229 So. 3d 667
CourtLouisiana Court of Appeal
DecidedOctober 25, 2017
DocketNO. 17-CA-93
StatusPublished
Cited by6 cases

This text of 229 So. 3d 667 (Gerald v. Doucette & Associated Contractors, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gerald v. Doucette & Associated Contractors, Inc., 229 So. 3d 667 (La. Ct. App. 2017).

Opinion

GRAVOIS, J.

|! Defendant/appeilant, Doucette and Associated Contractors, Inc. (“Doucette”), appeals a judgment rendered in favor of plaintiffs/appellees, Donna and Gerald Phillips (“plaintiffs”),1 in the amount of $20,000.00, together with interest from the date of judicial demand, plus all costs of the proceedings, plus an unspecified amount of attorney’s fees. Doucette also appeals the dismissal of its reconventional demand seeking’damages against plaintiffs for unpaid sums allegedly due under the construction contract the parties entered into. After thorough review and consideration of the law and the entirety of the record, we reverse the judgment in part, finding that the trial court committed manifest error in its award of monetary damages, judicial interest, attorney’s fees, and costs to plaintiffs. In all other respects, the judgment is affirmed. . '

FACTS AND PROCEDURAL BACKGROUND

This matter arises out of a contract between the parties for construction of a four-unit apartment building in Jefferson Parish, Louisiana. On May 5, 2005, the parties entered into a fixed-price contract for Doucette to build the apartment building for plaintiffs for $357,032.00. Construction of the building began shortly thereafter, but performance of the contract was soon substantially impaired and delayed by Hurricane Katrina striking the area on August 29, 2005, with the resultant disruption of normal business and scarcity of labor and materials. Though initially a contested point, the evidence shows that as a result of the hurricane’s disruption, the parties, along with Omni Bank, which provided the construction financing for the project, agreed in 2007 to modify the contract to | ¡¡reflect a new price of $383,692.04, an increase of $26,660.04, which was paid to Doucette on August 6, 2007.2

Doucette alleged that when the project was substantially complete around August of 2007, plaintiffs refused to pay any further sums that Doucette claimed were still due on the project. On October 29, 2007, after the parties failed to arrive at a resolution of the dispute, Doucette filed a lien against’ the property in the amount of $40,000.00, the amount it claimed at that time remained owed by plaintiffs on the project “for additional costs due to Hurricane Katrina.” On January 23, 2008, plaintiffs filed a petition to cancel the “improperly filed” lien and for damages, attorney’s fees, and costs incurred by plaintiffs in connection with removal of the lien. In their petition, plaintiffs denied that any remaining amount was due'Doucette on the project. Plaintiffs also: posted a cash bond with the Jefferson Parish Clerk of Court in order to obtain cancellation of the lien.3 Doucette filed an answer and recon-ventiorial demand, seeking damages for sums allegedly still due Doucette under the contact. Plaintiffs filed an answer and reconventional demand as well, denying that any amount remained due on the contract, and claiming damages from Doucette for negligence and breach of contract.

The parties framed the issues for trial in their joint pre-trial order. Plaintiffs contended that Doucette ceased working on the project in July of 2007, claiming that it had not been paid to complete the job. They asserted that on August 6,2007, they made a last payment to Doucette of $47,414.00, which brought the total amount they paid Doucette, to $383,692.04, the amount the parties agreed to after verbally modifying the contract after Hurricane Katrina. However, according to | ^plaintiffs, Doucette failed to complete the project, requiring plaintiffs to hire additional contractors to complete or correct the plumbing, electrical work, and air-conditioning. Plaintiffs also argued that they were additionally damaged by the alleged improper filing of the lien by Doucette, which, though the lien was cancelled on November 15, 2007, allegedly prevented them from securing permanent financing for the building.

Doucette, in the joint pre-trial order, asserted that it completed all of the work contemplated by the contract as amended after Hurricane Katrina, and that plaintiffs failed to pay ifythe full amount owed, which included additional work it performed that was required by the Fire Marshal that was not included in the contract as amended by the parties. Doucette claimed that it was still owed $79,999.60, which included additional costs for interior and exterior work, plus costs incurred for additional work required by the Fire Marshal, plus (as per the contract) 15 percent thereon per month, and attorney’s fees.

The matter went to a bench trial on June 27-28, 2016, after which the parties submitted post-trial memoranda. On September 2, 2016, the trial court rendered judgment, awarding $20,000,00 to plaintiffs, together with interest from the date of judicial demand, plus all costs of the proceedings, plus an unspecified amount of attorney’s fees. The judgment further dismissed Doucette’s reconventional demand with prejudice. No reasons for judgment were provided. It is from this final judgment that Doucette appeals.4

On appeal, Doucette first asserts that the trial court erred in awarding plaintiffs damages, costs, 'and attorney’s fees, arguing that plaintiffs failed to prove by a preponderance of the evidence: 1) that it was Doucette who caused the completion of the project to be delayed; 2) that Dou-cette breached the contract by failing to complete the project; 3) that ‘ Doucette performed defective work on the |4project; and 4) that plaintiffs suffered damages as a result of the lien fíléd by Doucette. 'Dou-cette also.argues on appeal that the trial court erred in dismissing its reconventional demand, asserting that it proved that it was owed additional compensation from plaintiffs due to change orders on the project, and that it is therefore also owed attorney’s fees and liquidated damages pursuant to the contract.

’ In their appellee brief, plaintiffs argue that the' evidence introduced supports the award of $20,000.00 in their favor. Their' brief does not, however, address Dou-cette’s claim on appeal regarding the dismissal of his reconventional demand. '

ANALYSIS

This case concerns causes of action for both negligence (plaintiffs’ claim for damages for Doucette’s alleged improper filing of the lien), and breach of contract:

(1) plaintiffs’ claims for:
a) Doucette’s alleged delay in completion of the project;
b) Doucette’s alleged failure to complete the project; and
c) Doucette’s alleged defective work on the project; and .
(2) Doucette’s claim for-plaintiffs’ alleged failure to pay sums due Dou-cette on the project.

In an action to recover damages for injuries allegedly caused by another’s negligence, the plaintiff has the burden of .proving negligence on the part of the defendant by- a preponderance of the evidence. Hanks v. Entergy Corp., 06-0477 (La. 12/18/06), 944 So.2d 564, 678. Proof is sufficient to constitute a preponderance when the entirety of the evidence, both direct and circumstantial, shows the fact sought to be proved is more probable than not. Id. (Internal citations omitted.) In a breach of contract case, ah obligor is liable for the damages caused by his failure to perform a conventional obligation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
229 So. 3d 667, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gerald-v-doucette-associated-contractors-inc-lactapp-2017.