Brigette Swayzer v. Jeffery Scoby

CourtLouisiana Court of Appeal
DecidedFebruary 28, 2024
Docket55,416-CA
StatusPublished

This text of Brigette Swayzer v. Jeffery Scoby (Brigette Swayzer v. Jeffery Scoby) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brigette Swayzer v. Jeffery Scoby, (La. Ct. App. 2024).

Opinion

Judgment rendered February 28, 2024. Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.

No. 55,416-CA

COURT OF APPEAL SECOND CIRCUIT STATE OF LOUISIANA

*****

BRIGETTE SWAYZER Plaintiff-Appellant

versus

JEFFERY SCOBY Defendant-Appellee

Appealed from the Monroe City Court for the Parish of Ouachita, Louisiana Trial Court No. 2021CV01296

Honorable Jefferson Bryan Joyce, Judge

BRIGETTE SWAYZER In Proper Person, Appellant

JEFFERY SCOBY In Proper Person, Appellee

Before STONE, HUNTER, and ELLENDER, JJ. STONE, J.

This appeal by Brigette Swayzer (the “plaintiff”) arises from Monroe

City Court, the Honorable Jefferson B. Joyce presiding. Neither the plaintiff

nor the defendant-appellee, Jeffery Scoby (the “defendant”), was represented

by counsel at trial. Nor is either party represented by counsel in this appeal.

The plaintiff filed this action seeking an award of money damages for breach

of contract in relation to the parties’ agreement that the defendant would

completely remodel the plaintiff’s house in Wisner, Louisiana. Due to her

dissatisfaction with the quality of the defendant’s work and the rate of his

progress, the plaintiff partially terminated her contract with the defendant,

demanded a refund from him (which he refused), and hired Charles Jones to

remedy the defendant’s work and finish the job. Approximately one month

later, she filed a petition requesting $14,200 in damages. At the bench trial,

the plaintiff essentially alleged that the defendant agreed to a completion

date that he clearly would not be able to satisfy, that the work he did perform

was defective, and that the plaintiff paid him far more than the value of the

work he actually performed. The trial court rendered a judgment awarding

the plaintiff only $2,500 in damages. The plaintiff appealed, seeking to have

her award increased.

Evidence introduced at trial

Because there were no attorneys or jury involved, the trial did not take

the usual form (i.e., opening statements, then direct and cross-examination

of witnesses and introduction of exhibits, and then closing arguments);

instead, the parties and witnesses were sworn, then the plaintiff provided a

factual narrative, and then the defendant provided a factual narrative.

Afterwards, others who were involved in the remodeling of the home were called as witnesses, namely: (1) Terry Swayzer (the plaintiff’s brother)1; (2)

Charles Jones, whom the plaintiff paid about $4,000 to cure the deficiencies

in the defendant’s work; (3) James Carroll, whom the defendant claimed

worked under him at the plaintiff’s house; and (4) Billy Harris, an electrician

brought in to help Charles Jones finish the job. Once the witnesses began

speaking, the trial became a multilateral conversation in which all seven

people (i.e., the two parties, four witnesses, and the trial judge) took turns

speaking in no particular order. Additionally, the plaintiff and defendant

introduced numerous photographs and documents into evidence, but did not

mark them individually for identification.

The following narrative is synthesized from the evidence introduced

at trial. The house suffered from substantial flood damage, and prior to the

subject agreement, had been completely “gutted” in preparation for

extensive renovation.2 The written contract, which was signed by both

parties on June 22, 2021, and specified a start date of June 22, 2021, was

introduced into evidence. The total price of the contract between plaintiff

and defendant was $38,500, which was to be paid in 5 draws of $7,700 each.

The written contract provides only an extremely vague outline of the work to

be done, and does not include a completion date for the total job or for any

phase of the job. However, the plaintiff insisted that she and the defendant

orally agreed that the whole job would be finished by Thanksgiving of 2021,

so she could host Thanksgiving dinner in the home; the defendant adamantly

1 Terry Swayzer testified that he did preparatory work inside the house for which the defendant agreed to pay him $8 per hour, but after this work was done, the defendant refused to pay for all the hours expended and would only pay $7 per hour. 2 The plaintiff introduced into evidence multiple pictures of the interior of the house, which reflect that there were no interior walls or ceiling when the defendant commenced work. 2 denied such an agreement, and further testified that he never agrees to a

completion date on any job that he does. Apparently, the parties did agree

that draws would be due upon completion of certain phases of the work.

However, the evidence does not provide an intelligible definition of any

such phase of the job. The record likewise does not contain any detailed

description of the work to be done. There were many disputed facts at trial,

and the timeline of the events is difficult, if not impossible, to ascertain.

On June 22, 2021, the parties signed the agreement and the plaintiff

paid the first draw by check,3 and the defendant began work. The plaintiff

did not live near the home while the work was to be done and thus was not

present to observe the defendant’s comings and goings. She testified that the

defendant agreed to work on the house four or five days per week, but the

defendant testified that he only agreed to work two or three days per week.

The plaintiff began to distrust the defendant because her brother (who was

initially involved in the remodel as a laborer) and a neighbor of the home

told her the defendant was not showing up to work. The plaintiff testified

that the defendant only showed up two days per week, except that there were

two weeks which he worked three days. Furthermore, she testified that he

only worked about 4 hours per day when he did go to the house. The

defendant responded that some of the work, such as building the custom

cabinets, had to be done off site.

The plaintiff testified that the defendant was supposed to be finished

hanging the sheetrock before he would be entitled to the second draw.

However, the defendant requested the second draw and the plaintiff paid it

3 This check was drawn on the account of Prince of Peace Auto Sales, LLC. 3 by check4 dated July 23, 2021, even though the defendant had not completed

hanging sheetrock by that time. He admitted not being finished with the

sheetrock at that point and said that this was because there was still rotten

wood that had to be replaced first.

Upon receiving the second draw, the defendant admittedly left town

and went to Birmingham, Alabama, supposedly to get a divorce from his

wife; he stayed a few extra days to visit family there. The defendant

allegedly contracted COVID-19 and became sick around the time that he

returned from Birmingham. He claimed that he was too sick to work until

after his first negative COVID-19 test on August 22, 2021, i.e., a month after

receiving the second draw. The plaintiff alleged that the defendant had

claimed that he had a “crew” that he would send to work on the house if he

was unable to go himself; however, the plaintiff testified that no such crew

was ever sent nor did he ever have one, but instead, tried to subcontract the

work on the house to “crackheads” in the neighborhood.

It was during this time when the defendant was not working due to his

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stevens v. Winn-Dixie of Louisiana
664 So. 2d 1207 (Louisiana Court of Appeal, 1995)
Stiltner v. National Union Fire Ins. Co.
798 So. 2d 1132 (Louisiana Court of Appeal, 2001)
Simon v. Lacoste
918 So. 2d 1102 (Louisiana Court of Appeal, 2005)
Earls v. McDowell
960 So. 2d 242 (Louisiana Court of Appeal, 2007)
Bradford v. Jury
139 So. 3d 39 (Louisiana Court of Appeal, 2014)
Gerald v. Doucette & Associated Contractors, Inc.
229 So. 3d 667 (Louisiana Court of Appeal, 2017)
Antley v. Rodgers
251 So. 3d 607 (Louisiana Court of Appeal, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Brigette Swayzer v. Jeffery Scoby, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brigette-swayzer-v-jeffery-scoby-lactapp-2024.