Winford Co. v. Webster Gravel & Asphalt

571 So. 2d 802, 1990 La. App. LEXIS 2844, 1990 WL 194184
CourtLouisiana Court of Appeal
DecidedDecember 5, 1990
Docket21,994-CA
StatusPublished
Cited by21 cases

This text of 571 So. 2d 802 (Winford Co. v. Webster Gravel & Asphalt) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winford Co. v. Webster Gravel & Asphalt, 571 So. 2d 802, 1990 La. App. LEXIS 2844, 1990 WL 194184 (La. Ct. App. 1990).

Opinion

571 So.2d 802 (1990)

WINFORD COMPANY, INC., Plaintiff,
v.
WEBSTER GRAVEL AND ASPHALT, INC., Ark-La-Tex Auto Auction, Inc., et al., Defendants.

No. 21,994-CA.

Court of Appeal of Louisiana, Second Circuit.

December 5, 1990.

*803 Campbell, Campbell & Johnson by James M. Johnson, Minden, for appellee.

Fish & Montgomery by John W. Montgomery, Minden, for defendant Webster Gravel & Asphalt Co., Inc.

Robert J. Donovan, Jr., Shreveport, for defendants-appellants Edward L. Blakey, Katherine Dees Blakey and Ark-La-Tex Auto Auction, Inc.

Before SEXTON, NORRIS and HIGHTOWER, JJ.

HIGHTOWER, Judge.

This is an appeal from a judgment awarding the contract price for construction of an asphalt parking lot and recognizing a Private Works Act lien. For the reasons hereinafter expressed, we affirm in part and reverse in part.

FACTS AND BACKGROUND

In 1983, Webster Gravel and Asphalt, Inc. ("Webster") orally contracted to construct a parking lot for Ark-La-Tex Auto, Inc. ("Ark-La-Tex") for a total price of $71,409. The facility would be placed upon *804 land owned by Edward Blakey and his wife, but leased to Ark-La-Tex, a corporation owned entirely by the Blakeys and engaged in the automobile auction business. Webster subcontracted all phases of the project, with Haddox Contractor's, Inc. ("Haddox") to prepare the soil or base, and with Winford Company, Inc. ("Winford") to do the surfacing. Haddox and Winford would receive $49,960.30 and $16,332.40, respectively, leaving the remaining $5,090.30 to Webster.

Blakey, acting on behalf of Ark-La-Tex, furnished no written plans or specifications. He prescribed, however, that the soil preparation be accomplished with lime only and that an asphalt penetration seal then be applied to the surface. Apparently, his knowledge of the technical aspects had been acquired through conversations with other persons involved in such work. Although the testimony conflicted, there is evidence that the presidents of the three construction companies, J.W. Dickinson, Lamar Haddox, and Jim Winford, voiced their concerns that the chosen method of construction might be inadequate. Indeed, Blakey declined suggestions for the utilization of soil cement as a ground stabilizer.

Haddox performed the ground preparation sometime before September 17, 1983, the day that Winford applied the penetration seal to the surface. Winford's job superintendent testified that he mentioned the instability of the base in several conversations with Blakey. Nevertheless, the Ark-La-Tex president did nothing, and the surface laying proceeded. Upon completion of the work, the lot rapidly deteriorated. Thereafter, in February 1984, the lessee corporation employed another contractor to construct a new parking lot on the site.

In August 1984, Winford filed suit against Webster, Ark-La-Tex, and the Blakeys, for the $16,332.40 amount and recognition of a lien previously filed on the Blakey property. Webster answered and also sought, by third party demand, recovery of its $71,409 contract price from Ark-La-Tex and the Blakeys (that corporation and those individuals to be sometimes collectively referred to as "defendants"). Claiming to be a party to the general contract, Haddox intervened against defendants. In addition to answering all claims, Ark-La-Tex and the Blakeys presented third party and reconventional demands against the three contractors, alleging damages for defective construction and improper workmanship.

After one day of trial on January 15, 1987, the proceedings adjourned to a later date. Subsequent deaths of Webster's president and an attorney's family member extended the postponement until December 21 and 22, 1988. In a written opinion, the trial court found that a contract existed between Ark-La-Tex and Webster. The decision thus rejected Haddox's intervention, that corporation and Winford being held to be subcontractors.

The trial court further concluded that the failure of the parking lot surface did not result from improper workmanship or materials, but from improper design for which responsibility rested with Ark-La-Tex. Applying LSA-R.S. 9:2771, which relieves a contractor from liability for deterioration or defects resulting from the insufficiency of plans and specifications which he does not provide, the trial court deemed Webster, Haddox, and Winford blameless. Hence, the court awarded the full contract sum to Webster, and granted Winford judgment against Webster for its subcontract price. Additionally, the judgment recognized Winford's lien. Haddox, not having made demand against Webster, received no award after rejection of the intervention. Claims by the Blakeys and Ark-La-Tex against the three contractors were rejected. This appeal, by only Ark-La-Tex and the Blakeys, followed the overruling of a motion for new trial.

ACCOUNTABILITY OF THE CONTRACTORS

Several assignments of error concern the judgment in favor of Webster and the rejection of appellants' demands against the construction firms. Appellants maintain the trial court did not hold the contractors to the duty, implicit in every building contract, of constructing work that is suitable *805 for its intended purpose and free from defects in materials and workmanship. Additionally, LSA-R.S. 9:2771 is asserted to be inapplicable since written plans and specifications did not exist. Appellants further contend that the evidence failed to preponderate that the oral contract allocated the risk of loss for defects to Ark-La-Tex.

Of course, this court's review is constrained by the manifest error standard, which demands that findings of fact by the trial court be given great deference and disturbed only when clearly wrong. Even if there is conflict in the testimony, reasonable inferences of fact should not be disturbed. Arceneaux v. Domingue, 365 So.2d 1330 (La.1978), on remand, 370 So.2d 1262 (La.App. 3d Cir.1979), writ denied, 374 So.2d 660 (La.1979). Also, when findings of fact are based on decisions regarding the credibility of witnesses, respect should be given those conclusions, for only the factfinder can be aware of the variations in demeanor and tone of voice that bear so heavily on understanding and believing what is said. Rosell v. ESCO, 549 So.2d 840 (La.1989). Indeed, this court is mandated not to substitute its own evaluations and inferences for those of the trier of fact. Wood v. Haas, 451 So.2d 160 (La.App. 1st Cir.1984), writ denied, 458 So.2d 124 (La. 1984).

The record discloses that Blakey discussed the project with several people knowledgeable in the field of parking lot construction and obtained a soil analysis from Southwest Laboratories. His specifications for the job, which he described as being "in his head," required treatment of the soil base with lime only, followed by application of a sealant consisting of an asphalt and pea gravel mixture. The evidence preponderates that subsequent construction of the lot occurred in accordance with that plan.

The testimony of R.E. Dillon, an expert in the field of civil engineering and the design and construction of parking lots and highways, indicated that the project met the requirements of the plans and specifications. He further concluded that no deficiencies existed in the actual work methods employed by the contractors. Instead, he stated, defective design caused the facility's failure. From his analysis, the structural base, although complying with the plans and specifications, inadequately supported the repetitive loading which occurred on the area.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gilley v. Gilley Enterprises, Inc.
222 So. 3d 885 (Louisiana Court of Appeal, 2017)
Lingoni v. Hibernia National Bank
33 So. 3d 372 (Louisiana Court of Appeal, 2010)
Allstate Enterprises, Inc. v. Brown
907 So. 2d 904 (Louisiana Court of Appeal, 2005)
Jones v. Hernandez
880 So. 2d 245 (Louisiana Court of Appeal, 2004)
Tristar Construction Co. v. Housing Authority
833 So. 2d 556 (Louisiana Court of Appeal, 2002)
Peterson Contractors, Inc. v. Herd Producing Co., Inc.
811 So. 2d 130 (Louisiana Court of Appeal, 2002)
Smith v. Riverwood Intern.
792 So. 2d 863 (Louisiana Court of Appeal, 2001)
Furlough v. Union Pacific RR Co.
766 So. 2d 751 (Louisiana Court of Appeal, 2000)
Haile v. City of Monroe
722 So. 2d 1192 (Louisiana Court of Appeal, 1998)
Griffin v. International Ins. Co.
727 So. 2d 485 (Louisiana Court of Appeal, 1998)
Parker v. National Linen Service
671 So. 2d 963 (Louisiana Court of Appeal, 1996)
Succession of Coddington v. Time Insurance Co.
658 So. 2d 1326 (Louisiana Court of Appeal, 1995)
Townsend v. Westinghouse Elevator Corporation
641 So. 2d 1022 (Louisiana Court of Appeal, 1994)
Sledge v. Continental Cas. Co.
639 So. 2d 805 (Louisiana Court of Appeal, 1994)
Rivnor Properties v. Herbert O'Donnell, Inc.
633 So. 2d 735 (Louisiana Court of Appeal, 1994)
McCraw v. Louisiana State University Medical Center
627 So. 2d 767 (Louisiana Court of Appeal, 1993)
Johns v. American Isuzu Motors, Inc.
622 So. 2d 1208 (Louisiana Court of Appeal, 1993)
Savannah v. Anthony's Auto Sales, Inc.
618 So. 2d 676 (Louisiana Court of Appeal, 1993)
Bolton v. Louisiana St. U. Med. Center
601 So. 2d 677 (Louisiana Court of Appeal, 1992)
Arceneaux v. Daggett
594 So. 2d 1001 (Louisiana Court of Appeal, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
571 So. 2d 802, 1990 La. App. LEXIS 2844, 1990 WL 194184, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winford-co-v-webster-gravel-asphalt-lactapp-1990.