DESIGN & CORROSION ENG., INC. v. Piggly Wiggly of Mansfield, Inc.
This text of 408 So. 2d 292 (DESIGN & CORROSION ENG., INC. v. Piggly Wiggly of Mansfield, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
DESIGN & CORROSION ENGINEERING, INC., Plaintiff-Appellee,
v.
PIGGLY WIGGLY OF MANSFIELD, INC., Defendant-Appellant.
Court of Appeal of Louisiana, Second Circuit.
*293 Wiener, Weiss, Madison & Howell by John M. Madison, Jr., Shreveport, for defendant-appellant.
Rothell & Cohn, Ltd. (A Professional Law Corp.) by David A. Rothell, Mansfield, for plaintiff-appellee.
Before HALL, MARVIN and FRED W. JONES, Jr., JJ.
FRED W. JONES, Jr., Judge.
Plaintiff contractor sued a defendant property owner to recover the total amount allegedly due under a contract involving the asphalt overlay of a parking lot and incidental work. From a judgment in favor of plaintiff as prayed for, defendant appealed, contending that the trial judge erred in:
(1) Holding that plaintiff substantially performed its obligations under the contract, rather than limiting recovery to quantum meruit.
(2) Failing to reduce the amount of plaintiff's recovery by the sum proven necessary to perfect or complete the work.
(3) Finding, alternatively, that use of the parking lot by defendant constituted acceptance of the work, thus entitling plaintiff to recover the full contract price.
We affirm.
In June 1980 plaintiff and defendant entered into a written contract under which plaintiff was to fill in pot holes, sweep and overlay with asphalt cement defendant's grocery store parking lot in Mansfield for a contract price of $23,112. A subsequent agreement concerning additional work increased that total contract price to $24,512. Work under the contract commenced on June 10, 1980 and was purportedly completed a week later.
Defendant refused to pay any part of the contract price, contending that plaintiff's work was totally unsatisfactory. Consequently, plaintiff filed suit for $24,512. Defendant answered, denying owing plaintiff anything, and reconvened for $340.32 paid to engineers to conduct tests with reference to plaintiff's work. Trial was had on February 12, 1981.
In a written opinion the trial judge concluded that, although there were deficiencies in plaintiff's work, these were not of sufficient seriousness to prevent a finding of substantial performance of its contractual obligations; that defendant failed to prove either the extent of the claimed defects *294 or what it would cost to cure them; and that, even if the cost of remedying the defects had been proven, defendant was barred from recovering that cost because it had accepted the contract work.
As acknowledged by the parties, the written agreement involved in this litigation is a building contract as defined by Louisiana Civil Code Article 2756[1]. Consequently, Louisiana Civil Code Article 2769[2] contains the basic applicable law.
According to the consistent jurisprudential interpretation of Article 2769, substantial performance of a building contract entitles the contractor to recovery under the contract. Whether there has been substantial performance is a question of fact. Among factors to consider in determing substantial performance are the extent of the claimed defects or incomplete work, the degree to which the purpose of the contract is defeated, the ease of correction, and the use or benefit to the owner of the work performed. Airco Refrigeration Service, Inc. v. Fink, 242 La. 73, 134 So.2d 880 (1961); Lane Wilson Co., Inc. v. Gregory, 322 So.2d 369 (La.App. 2d Cir. 1975); Neel v. O'Quinn, 313 So.2d 286 (La.App. 3rd Cir. 1975); Florida Ice Machine Corp. v. Branton Insulation, Inc., 290 So.2d 415 (La.App. 4th Cir. 1974); Maloney v. Oak Builders, Inc., 224 So.2d 161 (La.App. 4th Cir. 1969).
Where there has been substantial performance of the contract, the remedy of an owner who complains of defective or incomplete work is to prove (a) the existence of the defects or omissions and (b) the cost of repairing the defective work or completing the unfinished work. If the owner discharges his burden of proof, recovery by the contractor of the total contract price will be reduced by the cost of correcting or completing the work. Airco Refrigeration Service, Inc. v. Fink, supra; Neel v. O'Quinn, supra; Florida Ice Machine Corp. v. Branton Insulation, Inc., supra.
Defendant argues that plaintiff's principal obligation under the contract was to overlay the parking lot with a 1½ inch layer of asphalt; that tests revealed the average thickness of the asphalt actually laid to be 1.36 inches; and that loose gravel, loose joints and rough spots on the parking lot evidenced defective workmanship. Because of this, defendant contends that plaintiff did not prove substantial performance of its contractual obligations.
J. R. Hunter, an employee of plaintiff who had been doing asphalt work for about 20 years, negotiated the contract on behalf of plaintiff, was in charge of the project and actually operated a machine which "rolled out" the asphalt on the surface encompassed by the contract. Hunter understood that under the contract he was to "patch all the holes ... sweep the lot with a sweeper, and clean it up and lay an inch and one-half asphalt." The area to be covered, including an access road, measured 5478 square yards. An industrywide "rule of thumb" calculated that, for a 1½ inch overlay, one ton of asphalt should cover an area of 12.12 square yards. Applying this formula to the area in question, something less than 500 tons would have been required. Hunter testified that, in fact, he applied 528.54 tons of asphalt on defendant's parking lot and access road.
Hunter further stated that, because certain areas of the parking lot were in good condition, he was requested by defendant's president, Thompkins, to take some of the asphalt intended for those areas and use it on a back access road which had been worn down by heavy delivery trucks. When this was done, asphalt placed on the access road was four or five inches thick in places.
According to Hunter, Thompkins was leaving town a day or so before the job was completed and offered at that time to pay *295 him the contract price. Hunter refused to accept the payment, suggesting that Thompkins wait until the job was completed.
Hunter testified that he inspected the parking lot on the morning of the trial and found it was "holding up real good, was real serviceable ..."
Mukesh Patel, a certified asphalt concrete technician employed by a Shreveport engineering laboratory, testified that at plaintiff's request he took from defendant's parking lot (including both old and new) a core sample of asphalt which tested 2¼ inches in thickness. Patel explained that the generally accepted method in the asphalt business for determining whether the required amount of asphalt has been applied is by use of a total tonnage criterion because:
"... when you overlay any kind of existing surface, and if they call for an inch and a half or two inch you are not going to have an inch and a half all the way down every place of the parking lot, because you have already got the existing surface, and you have to follow your contour and level it ... so when you overlay that's why it doesn't come out an inch and a half all the time ..."
Defendant's president, Thompkins, testified that during the course of the asphalt work he discussed with Hunter certain deficiencies in the work, such as areas that were not level and loose rocks.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
408 So. 2d 292, 1981 La. App. LEXIS 5584, Counsel Stack Legal Research, https://law.counselstack.com/opinion/design-corrosion-eng-inc-v-piggly-wiggly-of-mansfield-inc-lactapp-1981.