Rudy Brown Builders v. St. Bernard Linen
This text of 428 So. 2d 534 (Rudy Brown Builders v. St. Bernard Linen) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
RUDY BROWN BUILDERS, INC.
v.
ST. BERNARD LINEN SERVICE, INC.
Court of Appeal of Louisiana, Fourth Circuit.
Amato & Creely, Robert G. Creely, Gretna, for plaintiff-appellant.
Ewell C. Potts, Chalmette, for defendant-appellee.
Before REDMANN, C.J., and GULOTTA and KLEES, JJ.
GULOTTA, Judge.
In this building contract case, Rudy Brown Builders, Inc., the contractor, appeals from a judgment denying its claim for the final installment payment of $6,100.00 retained by the owner, St. Bernard Linen Service, Inc. We affirm.
On August 10, 1976, St. Bernard Linen contracted with Rudy Brown Builders for the construction of a $61,000.00 building. Following completion and acceptance, the owner refused to make the final payment because of the alleged defects in construction. Payments for extras claimed by the *535 contractor were also withheld. This suit followed, seeking recovery of $15,658.40, representing $6,426.72 in extras together with the $6,100.00 unpaid final payment and attorneys fees. The owner in reconvention claimed entitlement to $24,854.67, which includes replacement costs of the slab, correction of defects and expert fees for slab testing.
Following a trial on merits, the trial judge awarded to the plaintiff contractor $5,844.59 for the "extras", but also awarded the defendant-owner $4,480.00 for correction of roof defects. Further, concluding that the contractor had not performed according to the contract, the trial judge denied recovery to the contractor for the $6,100.00 payment.
In written reasons, the trial judge stated:
"The contract provided that the slab of the building was to be of six (6") inches uniform thickness. The testimony shows it was not, but that it varied from 6.15" to 3.90" with an average thickness of 5.13". An expert ... testified that 13 core samples were taken and that only one (1), sample six (6), met the 6" slab thickness requirement and that that sample was taken from the center of the building... He also testified than an allowable of between ¼" and ½" was acceptable and in his deposition stated that ¾" in isolated instances was acceptable, but that he felt very uncomfortable with a 3.90" core sample. Even if 5.25" would be acceptable, the slab delivered to defendant was still .12" below acceptable standards and .87" below that which was contracted for."
Although recognizing that the slab was deficient, the court believed that the defendant had not "proved the present necessity of a new slab", and held that the "deprivation of the balance of the contract price should be sufficient to cover the deficiency."
Appealing, the contractor objects only to that portion of the judgment concerning the retainage. In this regard, the contractor argues that it is entitled to the full contract price because it has substantially completed the construction and the owner has failed to prove any specific damages from the slab deficiencies. Rudy Brown Builders further points out that the trial judge's conclusion of non-performance of the contract contradicts its finding that the slab does not require replacement. We disagree.
When a contractor has "substantially performed" a building contract, he is entitled to recover the contract price, even though defects or omissions are present. Airco Refrigeration Service, Inc. v. Fink, 242 La. 73, 134 So.2d 880 (1961); Neel v. O'Quinn, 313 So.2d 286 (La.App. 3rd Cir. 1975), writ denied 319 So.2d 440 (La.1975). "Substantial performance" means that, despite the deficiencies, the construction is fit for the purpose intended. Pete's Plumbing & Heating, Inc. v. Geissert, 413 So.2d 554 (La.App. 4th Cir.1982); Neel v. O'Quinn, supra. Factors bearing on this factual determination include: the extent of the defect or non-performance, the degree to which the purpose of the contract is defeated, the ease of correction, and the use or benefit to the owner of the work performed. Airco Refrigeration Service, Inc., v. Fink, supra; Pete's Plumbing & Heating, Inc. v. Geissert, supra; Design & Corrosion Eng. v. Piggly Wiggly, 408 So.2d 292 (La. App. 2nd Cir.1981).
In our case, the evidence supports a finding of substantial performance. William Hansel, a civil engineer who took core samples of the concrete slab, was of the opinion that the slab could accommodate the load, although he would not have accepted the slab because it exceeded normal variances in thickness. Similarly, Woodrow Ellis Alfred, a civil engineer who supervised the construction, also acknowledged the slab was not as thick as contracted but could support the load. The owner and its machinery have occupied the building since December, 1976. Under these circumstances, despite the slab deficiencies, the building has served its intended purpose. Accordingly, the contractor has "substantially performed" the contract.
*536 Once the contractor proves substantial performance, the burden shifts to the owner to show the defects or omissions entitling him to a reduction in the contract price for the cost of repair or completion. Pete's Plumbing & Heating, Inc. v. Geissert, supra; Design & Corrosion Eng. v. Piggly Wiggly, supra. The defendant-owner in our case has proven variances in the slab thickness that exceed tolerances and fail to meet the contractual requirement of a uniform slab. Although the evidence established no necessity for replacement of the slab, nonetheless, the owner has not received a slab of the agreed thickness. Despite the owner's failure to show with mathematical certainty the cost to correct the deficiencies, we cannot say the trial judge erred in denying recovery for the balance due under the contract.
Accordingly, the judgment is affirmed.
AFFIRMED.
REDMANN, C.J., concurs and assigns reasons.
REDMANN, Chief Judge, concurring.
Perhaps no one would contend that laying a four-inch concrete slab is "substantial" performance of a contract to lay a six-inch slab (just as installing an 80-hp boiler is not substantial performance of a contract for a 120-hp boiler, notwithstanding the useability of the smaller boiler, Manitowoc Steam B. Wks. v. Manitowoc Glue Co., 120 Wis. 1, 97 N.W. 515 (1903), cited in Corbin, Contracts, § 706). If a six-inch slab were the only provision of a contract between owner and contractor, the contractor certainly should not recover the contract price of a six-inch slab for laying a four-inch slab. Even if the slab were fully satisfactory for the owner's purposes, the most the contractor could recover would be the value of the four-inch slab, on the basis of unjust enrichment, La.C.C. 1965 (quantum meruit). The burden of proving that value would be the contractor's.
Our contract is for an entire building, however, and the slab is not uniformly only two-thirds of specified thickness. Our case is thus more complex, but the principles are the same. The concrete slab of a slab-foundation building is a substantial element of the entire building contract. It was therefore the province of the trier of fact to conclude, notwithstanding that the building is usable for the owner's purposes, that the substantial failure of performance on so substantial an element as the concrete slab defeats the contractor's claim of substantial performance of the contract, and thus defeats the claim for the contract price. That was the trial judge's conclusion, and it should remain undisturbed on review as not "clearly wrong," Arceneaux v. Domingue, 365 So.2d 1330 (La.1978).
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
428 So. 2d 534, 1983 La. App. LEXIS 8046, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rudy-brown-builders-v-st-bernard-linen-lactapp-1983.