Manitowoc Steam Boiler Works v. Manitowoc Glue Co.

97 N.W. 515, 120 Wis. 1, 1903 Wisc. LEXIS 173
CourtWisconsin Supreme Court
DecidedDecember 11, 1903
StatusPublished
Cited by16 cases

This text of 97 N.W. 515 (Manitowoc Steam Boiler Works v. Manitowoc Glue Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manitowoc Steam Boiler Works v. Manitowoc Glue Co., 97 N.W. 515, 120 Wis. 1, 1903 Wisc. LEXIS 173 (Wis. 1903).

Opinion

Dodge, J.

Tbe Result of tbis action, whereby the defendant is required to pay the full contract price for a boiler of only about one half the capacity or valúe of that for which it agreed to pay it, is somewhat startling, especially in view of the consideration, understood by both parties, that its only reason for buying a new boiler at all was that the operation of the factory required more steam than the old one could supply. Before reaching such a result, a court should pause to re-examine the rules of law or processes of reasoning upon which it is based. If the law warrants it, the force or value of a contract seems to have vanished. The contractor receives the same compensation for nonperformance as for performance. The general rule of law is firmly established that he who makes an entire contract can recover no pay unless he performs it entirely and according to its terms. Moritz v. Larsen, 70 Wis. 569, 36 N. W. 331; Cohn v. Plumer, 88 Wis. 662, 60 N. W. 1000; Widman v. Gay, 104 Wis. 277, 80 N. W. 450. This general rule has, with considerable hesitation, been relaxed for equitable considerations in certain ■exceptional situations where it is believed to work hardship: First, in favor of laborers who contract to perform personal services, and without fault of either party fail of complete performance (Diefenback v. Stark, 56 Wis. 462, 466, 14 N. W. 621; Walsh v. Fisher, 102 Wis. 112, 78 N. W. 437; Hildebrand v. Am. F. A. Co. 109 Wis. 171, 85 N. W. 268); secondly, in building contracts, where the contractor constructs something on the land of another which by oversight, but in good-faith effort to perform fails to entirely satisfy the contract, but is so substantially in compliance therewith that the structure fully accomplishes the purpose of that contracted for, and the other party voluntarily accepts the benefit thereof, or where the failure is mere inconsiderable incompleteness, and the expense of completion is easy of ascertainment (Malbon v. Birney, 11 Wis. 107; Fuller-W. Co. v. Shurts, 95 Wis. 606, 70 N. W. 683; Williams v. Thrall, 101 Wis. [6]*6337, 76 N. W. 599; Laycock v. Parker, 103 Wis. 161, 79 N. W. 327; John Pritzlaff H. Co. v. Berghoefer, 103 Wis. 359, 79 N. W. 564; Taft v. Montague, 14 Mass. 282; Smith v. School Dist. 20 Conn. 312; Bozarth v. Dudley, 44 N. J. Law, 304; Smith v. Brady, 17 N. Y. 173; Dermott v. Jones, 2 Wall. 1); and, thirdly, where the contractor supplies an article different from or inferior to that promised, and the-recipient, having full opportunity to reject -without loss or injury, decides to accept and retain the thing furnished. This third phase is hardly an exception, for such voluntary acceptance may well be deemed the making of a new contract to take and pay reasonably for the article which does not satisfy the original contract. Fuller-W. Co. v. Shurts, supra; Williams v. Thrall, supra. In case of either of these exceptions,, great caution is due in order that the innocent purchaser shall not suffer. If loss must fall anywhere, it should rest on him who breaks the contract. As said in Allen v. Mc-Kibbin, 5 Mich. 449, 455, and quoted approvingly in Walsh v. Fisher, supra, “the party in default can never gain by his default, and the other party can never be permitted lose by it.” Bishop v. Price, 24 Wis. 480. The question,, therefore, in such cases, is never what will reasonably compensate the contractor, but what can the purchaser pay without being put in worse position than if the contract had been performed ? The recovery is quantum valebat from the innocent purchaser’s point of view.

Proceeding to ascertain how far these principles are applicable to the situation at bar, we are confronted by the fact that substantial performance of the express contract is wholly wanting. The finding is that the boiler furnished was about eighty-two per cent, of the capacity of the old one, instead of 150 per cent., and that the increase of capacity was the vital and essential part of the contract. This is in no sense substantial performance. The boiler does not serve at all the purpose which the larger one would have served, and for [7]*7wliicb it was purchased. Defendant can obtain that for which it contracted, and for which it agreed to pay $2,035, and which is necessary to the purpose which induced the contract, in only one of two ways: either it can remove this hoiler from its premises at large expense, if plaintiff does not remove it, and purchase and put in place another of the required size; or it can retain it, and put in another of substantially equal capacity as auxiliary to it, and at a cost equal to or greater than the original contract price, and probably necessitating reconstruction of its boiler house. One in such predicament cannot be said to have received in substance that for which he contracted. Malbon v. Birney, 11 Wis. 107; Fuller-W. Co. v. Shurts, 95 Wis. 606, 70 N. W. 683. Neither do we discover either finding or proof that defendant had accepted the boiler, had decided to keep it, and use it so far as it will go toward supplying the needed steam. True, the trial court argues that it would be inequitable to allow defendant to' keep the boiler and pay nothing for it, but does not find that it has elected to do so. The only finding is that it is not shown by a preponderance of the evidence that defendant rejected the boiler, or demanded its removal, though he did protest that it did not satisfy the contract. The evidence is that defendant never in words ordered plaintiff to remove the boiler, but from the testimony of the same witness (plaintiff’s manager) it appears that defendant, at the time of protesting the insufficiency, did convey to plaintiff its wish and expectation that it be removed. That witness testified that upon such protest he agreed that he would remove the boiler if on test it did not come up to contract requirement. The test was made, the capacity ascertained, hut the plaintiff’s contention thereafter was that the contract was other than it is now found to have been, and for that reason did not remove it. This testimony fully confirms that of defendant’s manager that he desired to have the boiler removed, and negatives any inference that it remained on [8]*8defendant’s premises pursuant to an election on its part to keep it. Another important consideration was that defendant’s entire pleading was based on the theory of nonacceptance. The answer denied performance of the contract, and sought by counterclaim to recover back the portion of the purchase price paid, and the expenses which must fall on defendant and be lost if the boiler was removed, but did not ask to recover the difference in value between the contract boiler and the actual one, which would be the principal element of damage if the boiler were to be retained. Boothby v. Scales, 27 Wis. 626; Park v. Richardson & B. Co. 81 Wis. 399, 51 N. W. 572. Doubtless the fact, unexplained, that defendant made use of the boiler, which had been built into its boiler house and connected with the steam pipes in its factory, is an evidentiary circumstance having some tendency to show acceptance, but such conduct is by no means conclusive when a party cannot forego use of the appliance without at the same time giving up the use of his own premises. Thus one whose land has been plowed by another cannot be said to accept that plowing as a service merely because he sows seed and raises a crop on the land. Smith v. Brady, 17 N. Y. 188.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rudy Brown Builders v. St. Bernard Linen
428 So. 2d 534 (Louisiana Court of Appeal, 1983)
Plante v. Jacobs
103 N.W.2d 296 (Wisconsin Supreme Court, 1960)
Nees v. Weaver
269 N.W. 266 (Wisconsin Supreme Court, 1936)
Wagner-Larscheid Co. v. Fairview Mausoleum Co.
208 N.W. 241 (Wisconsin Supreme Court, 1926)
Beuret v. Stahl
129 N.E. 407 (Indiana Court of Appeals, 1921)
Cointe v. Congregation of St. John the Baptist
143 N.W. 180 (Wisconsin Supreme Court, 1913)
Edmunds v. Welling
110 P. 533 (Oregon Supreme Court, 1910)
Tilton v. J. L. Gates Land Co.
121 N.W. 331 (Wisconsin Supreme Court, 1909)
Mueller v. Burton
121 N.W. 152 (Wisconsin Supreme Court, 1909)
Foeller v. Heintz
118 N.W. 543 (Wisconsin Supreme Court, 1908)
Price v. Grzyll
114 N.W. 100 (Wisconsin Supreme Court, 1907)
Manthey v. Stock
113 N.W. 443 (Wisconsin Supreme Court, 1907)
American Foundry & Furnace Co. v. Board of Education
110 N.W. 403 (Wisconsin Supreme Court, 1907)
Klug v. Sheriffs
109 N.W. 656 (Wisconsin Supreme Court, 1906)
Manning v. School District No. 6
102 N.W. 356 (Wisconsin Supreme Court, 1905)
Sherry v. Madler
101 N.W. 1095 (Wisconsin Supreme Court, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
97 N.W. 515, 120 Wis. 1, 1903 Wisc. LEXIS 173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manitowoc-steam-boiler-works-v-manitowoc-glue-co-wis-1903.