Brown v. Delegal Construction Corp.

445 So. 2d 1251, 1984 La. App. LEXIS 7986
CourtLouisiana Court of Appeal
DecidedFebruary 1, 1984
DocketNo. 83-388
StatusPublished
Cited by3 cases

This text of 445 So. 2d 1251 (Brown v. Delegal Construction Corp.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. Delegal Construction Corp., 445 So. 2d 1251, 1984 La. App. LEXIS 7986 (La. Ct. App. 1984).

Opinion

FORET, Judge.

Jack W. Brown (plaintiff) brought this action to recover the sum of $22,613.50, representing the amount allegedly due him under the terms of a sub-contract, damages to his reputation, and attorney’s fees. Named defendants are St. Jules Catholic Church1 and Delegal Construction Corporation. In turn, defendants filed an answer and reconventional demand in which they sought to recover the sum of $49,734.81: for damage to a mobile home and its contents; expenses incurred in providing supervisors to oversee plaintiff’s employees’ work; the cost of correcting construction defects; the cost of replacing a roof; damage to their reputation; and, expenses incurred in bonding out a lien filed by plaintiff.

After trial on the merits, the trial court rendered judgment in favor of plaintiff on the main demand, awarding him the sum of $12,804.42, together with legal interest thereon. The trial court further rendered judgment in favor of defendants on the reconventional demand, awarding them the sum of $8,980.81, together with legal interest thereon.

Plaintiff appeals and raises the following issues:

(1) Whether the trial court committed manifest error in finding that plaintiff’s employees had damaged the mobile home in question, and that plaintiff was liable for said damage.
(2) Whether the trial court committed manifest error in finding the exist[1254]*1254ence of construction defects in the work done by plaintiffs employees, and in assessing the costs of repairing said defects.
(3) Whether the trial court erred in allowing the introduction of certain alleged hearsay evidence by defendants to prove certain charges deducted from the sum paid plaintiff under the terms of the sub-contract.

FACTS

On April 17, 1979, a contract was entered into between St. Jules Apartments for Retired & Senior Citizens, Inc. (as owner) and Delegal Construction Corporation (as contractor) for the construction of an apartment complex (the project) in Franklin. Thereafter, Delegal and plaintiff entered into a sub-contract which provided that plaintiff would furnish the labor to: construct the slab for the buildings; erect the walls and roof; install the windows; hang the sheetrock; place the interior and exteri- or trim; and, install the cabinets therein. The sub-contract specifically stated that the construction of sidewalks and parking pads were excluded therefrom, as was the mechanical work, electrical work, bricklaying, and cement finishing. The sub-contract further provided that the contractor, Delegal, would handle plaintiff’s payroll, and that workmen’s compensation insurance, old age benefits, and unemployment compensation taxes were to be paid by plaintiff. The total amount of the sub-contract was $88,080.00, including payroll and expenses.

Shortly after the sub-contract was entered into, plaintiff provided the labor, and Delegal provided the materials, for construction on the project to begin. The project was being financed by the Farmers Home Administration (FHA), which conducted periodic inspections of the project to insure that the appropriate construction standards of that entity were being met. Almost immediately, the parties began to run into problems with the FHA inspectors regarding sub-standard construction work on the project. In order to correct these problems, certain portions of the project had to be torn down and reconstructed to

meet FHA standards. Finally, the project was completed and accepted by the FHA.

Problems arose between the parties when DelegaF made the last payment to plaintiff under the terms of the sub-contract. Apparently, Delegal deducted the cost of correcting the defective construction work performed by plaintiff’s employees from the amount it was supposed to pay plaintiff. As a result, plaintiff filed the instant suit. Defendants answered and filed a reconventional demand in which they sought to recover, among other things, damages for the destruction of a mobile home that had been placed at the construction site for use by plaintiff’s employees as required by the sub-contract.

DAMAGES TO THE MOBILE HOME

Plaintiff contends that the trial court committed manifest error in finding that his employees damaged the mobile home. Plaintiff further contends that, even if his employees did damage it, the trial court erred in finding that he was legally responsible for said damage. Finally, plaintiff argues that the trial court erred in awarding defendants $4,000 for damage to the mobile home as they failed to prove the amount of said damage.

Joseph C. Delegal, Jr. testified that the mobile home had been purchased from a dealer in Opelousas for $4,900. At the time of trial, the mobile home was sitting in a field near Milton, where it had been junked. A number of witnesses testified that the mobile home was clean and in very good condition when it was placed at the construction site. Apparently, some of plaintiff’s employees did not live in Franklin, and the mobile home had been provided for them to stay in while working on the project. However, shortly after they moved into it, the condition of the trailer began to deteriorate to the point where it was no longer fit for human habitation. There was testimony indicating that: appliances were intentionally damaged; garbage was swept into the floor-mounted air conditioning ducts; walls and doors had objects driven through them; bathroom fa[1255]*1255cilities were broken beyond repair; and, that dirt and filth were allowed to accumulate throughout the mobile home.

James Wells was one of plaintiff’s employees who stayed in the mobile home. He admitted that he broke a copper water line leading to the toilet in order to prevent it from being used because it had become clogged up. He further admitted that another of plaintiff’s employees had found a dog sleeping on a bed, and that this employee picked the dog up and hurled it against a mirror with such force that the mirror broke and a piece of glass stuck in the dog’s back. Wells also testified that plaintiff’s employees had swept garbage into the air conditioning ducts. This was the only direct evidence regarding damage done to the mobile home by plaintiff’s employees. However, Wells stated that one of plaintiff’s employees consumed large amounts of alcohol while staying in the mobile home, and that it was common practice for plaintiff’s other employees to also consume alcohol while staying there. Finally, and most revealing, Wells testified that:

“We’d give duties to everybody down there in the trailer. They’d keep it up for a day or so, but that’d be it. You know, like washing dishes and all. But what can you expect with all them men in the trailer. I mean, there’s nothing to do, away from home. You know, it’s like doing this on a desk. (Witness indicated by tapping fingers on desk.) Breaking a pencil from tension, and stuff like that.”

Wells did testify that the mobile home had been broken into a number of times on weekends and that food had been strewn about. However, the damage was apparently slight as plaintiff’s employees were able to clean it up each time. Finally, the evidence clearly shows that plaintiff’s employees were the only persons living in the mobile home, although other persons would use the restroom facilities and the telephone on occasion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phillips v. Town of Many
538 So. 2d 745 (Louisiana Court of Appeal, 1989)
Close v. Girard
498 So. 2d 1104 (Louisiana Court of Appeal, 1986)
Danner v. Olivier
467 So. 2d 103 (Louisiana Court of Appeal, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
445 So. 2d 1251, 1984 La. App. LEXIS 7986, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-delegal-construction-corp-lactapp-1984.