Costanza v. Cannata

36 So. 2d 627, 214 La. 29, 1948 La. LEXIS 933
CourtSupreme Court of Louisiana
DecidedJune 1, 1948
DocketNo. 38057.
StatusPublished
Cited by9 cases

This text of 36 So. 2d 627 (Costanza v. Cannata) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Costanza v. Cannata, 36 So. 2d 627, 214 La. 29, 1948 La. LEXIS 933 (La. 1948).

Opinion

FOURNET, Justice.

The plaintiffs, Michael A. Costanza and Paul S. Spedale, after having recorded their written acceptance of a building constructed for them by the defendant Bernard A. Cannata, provoked this concursus proceeding under the provisions of Act No. 298 of 1926, depositing the amount retained by them under the contract in the registry of the court and impleading the contractor; the New Amsterdam Casualty Company, the surety on the contractor’s bond; and all of the materialmen who had filed liens against the building. In this same proceeding the plaintiffs sought to recover damages caused by the contractor’s alleged failure to complete the building in accordance with the plans and specifications. They are now appealing from the judgment of the district court awarding them damages in the sum of $1,089, with attorney fees of $400. The defendant surety, answering the appeal, is asking that the judgment be reversed in so far as it awards the appellants damages and that it be amended to reduce the attorney fees to an amount not in excess of $250.

On March 31, 1941, the plaintiffs entered into a contract with Cannata for the construction, on property belonging to them on Bayou Sara Road (also referred to as Scenic Highway) near the city of Baton Rouge, of a one-story concrete block commerical building in accordance with the plans and specifications prepared by L. P. Manson, attached to and made a part of the contract. This building was to be erected “in a perfect and thoroughly workmanlike manner” at a cost of $9,800, 90% to be paid in installments as the work progressed and the *33 remaining 10% to be retained by the plaintiffs until the building was completed and turned over to them free of liens and privileges. It was to be ready for occupancy on or before June 23, 1941, in default of which the contractor was to forfeit by way of liquidated damages $3 a day. In accordance with the provisions of Section 2 of Act No. 298 of 1926, the plaintiffs exacted of the contractor a bond, the condition of which was that he would truly and faithfully perform the contract and pay all subcontractors, laborers, and materialmen. The contractor furnished as the surety on this bond the New Amsterdam Casualty Company. The contract and bond were then recorded.

It appears that during the progress of the work Mr. Manson, who was checking for the owners, called their attention to the failure of the contractor to comply with the plans and specifications on a number of occasions and that when they remonstrated with the contractor he refused to proceed with the construction unless permitted' to pursue the course he was following, leaving the job several times in protest. The plaintiffs reported these conditions to the local agent of the surety from time to time. Because of these delays and heavy rains, the building was not ready for occupancy on June 23, 1941. Shortly after July 1 the tenants who had leased half of the store from the plaintiffs 'appeared with' their stock and fixtures loaded on trucks but were denied admittance to the building by the contractor. Inasmuch as it was raining at the time, the contractor finally consented to this equipment being placed in the store, but he refused to turn over the keys to the building until the plaintiffs formally accepted the job. This they did on July 14, but only after the contractor had agreed to correct certain defects and complete the unfinished parts. The acceptance was recorded on July 16 following. In the meanwhile, in an effort to expedite matters, the plaintiffs had, on July 8, agreed to cancel their right to the liquidated damages for delay in delivering the building on June 23-Under these conditions, the plaintiffs and and their tenants occupied the building.

On August 4, 1941, the defects not having been corrected and the building not having been completed, the owners, through their architect, formally notified the contractor in writing of the items that had to be taken care of before the building would meet the requirements of the plans and specifications, as amended by the addenda, sending' a copy of this letter to the agent of the bonding company. The agent, in turn, referred the matter to the contractor who, becoming ill on August 7, sought to have the work done from his bed with the assistance of his wife and, under her supervision, some of these items were taken care of. However, some of the work still not being acceptable and, in certain instances,, not completed, the plaintiffs, in November,, secured estimates of the cost of finishing' the job from three contractors,- these esti *35 mates being for $1,049, $1,310, and $1,407.50. Despite the submission of these estimates to the surety, no further action was taken in the matter and the plaintiffs, in January of 1942, instituted this concursus proceeding seeking to have the liens recorded against the building by the materialmen and subcontractors cancelled and to recover damages in the amount of $1,533.05,.the amount of the highest bid submitted to them the previous November, plus an amount of $125.55 for the correction of defective electrical equipment not included in the bid.

In its answer the surety company denied that the building had been constructed in a defective and unworkmanlike manner, pleading specially that the plaintiffs, by their formal acceptance of the building as it was, were estopped from questioning the quality of the work or the materials incorporated therein. When none of the impleaded materialmen answered the suit, many of them having filed separate suits against the surety previous to the institution of the concursus proceeding, the surety, on October 5, 1942, asked that each of these materialmen be served with a rule compelling them to assert their claims in this proceeding instead of in the Separate actions filed by them and, in compliance with this rule, all of the parties formally appeared and asserted their respective claims.

On December 11 thereafter the plaintiffs, in order to meet the increased cost of material and labor, sought, in a supplemental and amended petition, to have the amount originally prayed for increased to $2,782, listing as remaining unfinished-and defective with the estimated cost of each, the following: (1) Setting terra cotta coping on walls ($51.60) ; (2) calking all windows and door frames ($30)-; (3) painting all exterior wood, metal, and masonry including a coat of bondex on outside exposed surfaces ($351.60); (4) connecting downspouts from roof to storm sewer ($105.60) ; (5) reinforcing five trusses supporting roof ($480); (6) raising skylights on roof so water can run off ($108); (7) installing standard 20-year guaranteed roof and flashing ($681.60) ; (8). refinishing wood floors and levelling concrete in drug store ($853.56); and (9) replacing structural glass where broken ($120). They also sought to have the attorney fees increased to $766.63, and, while they sought to recover $125 as damages for merchandise ruined in one of the stores because of leaks, this claim has apparently been abandoned.

The defendant surety excepted to this petition on the ground that it was prescribed by the prescription of one year under the laws of this state, and particularly Section 14 of Act No. 298 of 1926.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charles C. Cloy, General Contractors, Inc. v. DiVincenti Brothers, Inc.
308 So. 2d 495 (Louisiana Court of Appeal, 1975)
Palmer v. Asaff
297 So. 2d 487 (Louisiana Court of Appeal, 1974)
Popich v. Fidelity & Deposit Co.
245 So. 2d 394 (Supreme Court of Louisiana, 1971)
Popich v. Fidelity & Deposit Co. of Maryland
231 So. 2d 604 (Louisiana Court of Appeal, 1970)
Moran & McGoey, Inc. v. Trinity Universal Insurance
183 So. 2d 367 (Louisiana Court of Appeal, 1966)
Dinon Terrazzo & Tile Co. v. Tom Williams Construction Co.
148 So. 2d 329 (Louisiana Court of Appeal, 1963)
Justiss-Mears Oil Company v. Pennington
132 So. 2d 700 (Louisiana Court of Appeal, 1961)
Jack v. Henry
128 So. 2d 62 (Louisiana Court of Appeal, 1961)
Svendson v. American Indemnity Co. of Galveston
76 So. 2d 737 (Louisiana Court of Appeal, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
36 So. 2d 627, 214 La. 29, 1948 La. LEXIS 933, Counsel Stack Legal Research, https://law.counselstack.com/opinion/costanza-v-cannata-la-1948.