Hancock v. Northcutt

808 P.2d 251
CourtAlaska Supreme Court
DecidedApril 8, 1991
DocketS-3470, S-3483
StatusPublished
Cited by27 cases

This text of 808 P.2d 251 (Hancock v. Northcutt) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hancock v. Northcutt, 808 P.2d 251 (Ala. 1991).

Opinion

OPINION

MATTHEWS, Chief Justice.

STATEMENT OF THE FACTS

This case involves a dispute between the owner-builders of an earth-sheltered concrete house, Carol and Melvin Northcutt, and the concrete contractors for the house, Herb and Marge Hancock. The house consists of seven joined pods which may be covered with dirt for insulation. The Northcutts made an oral contract with the Hancocks for construction of the pods. The terms of the contract are in dispute. *253 The Northcutts claim that for $65,000 the Hancocks agreed to complete all structural concrete work. The Hancocks dispute the original price, and claim that they performed extra work not contemplated in the original contract, for which they were to be paid on a time and material basis. Construction was delayed. Each side blames the other for the delay. Following delays, all seven pods were poured. The North-cutts believed some of the work to be defective. The Hancocks offered to cure the problems but the Northcutts refused, ordering them off the job.

The Hancocks then filed a lien for $13,-100 and sued to enforce the lien. The suit was dismissed because the Hancocks had not complied with the registration requirements for contractors in Alaska.

The Northcutts then sued the Hancocks. The Northcutts’ amended complaint states that the Hancocks breached the contract by failing to perform in a timely and professional manner, and by changing the design of the Northcutts’ structure. In addition, the Northcutts allege that the Hancocks wrongfully liened the property. The Northcutts also plead a tort claim for misrepresentation and negligent and intentional infliction of emotional distress. The Northcutts claim that the house leaks and that it is structurally unsafe. The North-cutts sought damages associated with the costs to repair the house, and for emotional distress. They also asked for punitive damages. The Hancocks counterclaimed for the amount allegedly due under the contract plus extra work performed.

The contract was made in May of 1982. The Hancocks first poured concrete in September of 1982 and made their last pour on October 30, 1982. The Hancocks were ordered off the job prior to filing a lien in November of 1982. The Northcutts finished the house and closed on their $160,-000 mortgage about 90 days later. They have lived in the house since that time. However, they do not occupy pod seven because they believe it may collapse and they have installed timber cribbing in certain sections of the house to prevent a sudden collapse. This action was brought on September 15, 1984. After lengthy motion practice the case went to trial in March of 1989. Following a four-week trial, the jury returned a verdict in favor of the Northcutts.

The jury, guided by a special verdict form, awarded the Northcutts $455,984 as the cost of demolishing and rebuilding the house, $19,600 for moving and storage costs and temporary housing during reconstruction, $7,200 for past lost use of portions of the house, $28,486 for costs incurred by construction delays, and $175,000 for emotional distress. Compensatory damages thus totaled $686,271. 1 This amount plus prejudgment interest, costs and attorney’s fees was entered as a judgment against the Hancocks.

The Hancocks appeal. They assert that the judge erred in allowing the Northcutts to pursue their claim for emotional distress damages and in instructing the jury that it could award the Northcutts the cost of demolishing and replacing the house, even if it determined that replacement would constitute economic waste. The Hancocks also allege that various aspects of the conduct of the jury require the decision to be reversed.

The Northcutts have filed a cross-appeal, arguing that the trial court erroneously dismissed their tort claims for misrepresentation and intentional infliction of emotional distress. They also claim that the court erred in refusing to allow ■ the issue of punitive damages to go to the jury. In addition, they claim that the court erred in its award of costs and attorney’s fees to them and in restricting recovery of prejudgment interest.

DISCUSSION

A. HANCOCKS’ APPEAL

1. Did the trial court’s instruction concerning demolition and rebuilding costs constitute prejudicial error?

The trial court instructed the jury on alternative methods of computing dam *254 ages. Instruction 40 told the jury in general that if repair was feasible, the reasonable cost of putting the house in the condition promised by the contract should be the measure of damage. If, however, repair was not feasible, the jurors were told to award the difference between the value the house would have had if it had been built as promised and the actual value of the house. The jury was also instructed that even if repair was impractical and grossly wasteful, the cost of the repair method could be used if the jury found any one of the following: (1) that the house has a special significance to the Northcutts; (2) that the Northcutts were more likely than not to demolish and rebuild the house; or (3) that the house creates a dangerous condition. 2

The jury, in answer to the questions posed in the special verdict form, found that it would be impractical and grossly wasteful to put the house in the same condition it would have been in had the Hancocks kept their promise. However, the jury also found that at least one of the three conditions existed. It thus awarded the Northcutts $455,894 as the “reasonable cost to put the house in the condition it would have been in had the defendants kept their promise.” The parties agree that this represents the sum of $68,465 for removing the present house and $387,519 for rebuilding the house.

The Hancocks contend that the instruction is erroneous because the jurors should have been told that if expending funds to construct the house as contracted for would be impractical and grossly wasteful, damages should be the difference between what the house would have been worth if the contract had not been broken and its actual value, plus consequential damages. The Hancocks note that the most the house would have been worth if it had been properly built was $190,000 3 as of the time of its completion in 1982. As of the time of trial, because of a depressed real estate market, the house would have been worth approximately $142,500.

The Northcutts contend that the instruction was a correct reflection of the law. 4

*255 In our view, the instruction was a misstatement of the law. In Advanced, Inc. v. Wilks, 711 P.2d 524 (Alaska 1985), a case which involved another earth-sheltered concrete house, we approved a jury instruction which told the jury that damages should be the reasonable cost of remedying construction defects unless such costs were impractical and grossly wasteful, in which case a difference in value approach should be used. We stated:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Todeschi v. Sumitomo Metal Mining Pogo, LLC
394 P.3d 562 (Alaska Supreme Court, 2017)
Cornelison v. TIG Insurance
376 P.3d 1255 (Alaska Supreme Court, 2016)
Blake v. Guthy-Renker, LLC
965 F. Supp. 2d 1076 (D. Alaska, 2013)
Beckie Price v. High Pointe Oil Co Inc
828 N.W.2d 660 (Michigan Supreme Court, 2013)
Hagen Insurance, Inc. v. Roller
139 P.3d 1216 (Alaska Supreme Court, 2006)
Larson v. State
79 P.3d 650 (Court of Appeals of Alaska, 2003)
Hinsberger v. State
53 P.3d 568 (Alaska Supreme Court, 2002)
Liimatta v. Vest
45 P.3d 310 (Alaska Supreme Court, 2002)
Kallstrom v. United States
43 P.3d 162 (Alaska Supreme Court, 2002)
City of Seward v. Afognak Logging
31 P.3d 780 (Alaska Supreme Court, 2001)
Cole v. Bartels
4 P.3d 956 (Alaska Supreme Court, 2000)
Wilson v. United States
190 F.3d 959 (Ninth Circuit, 1999)
Erlich v. Menezes
981 P.2d 978 (California Supreme Court, 1999)
Titus v. State
963 P.2d 258 (Alaska Supreme Court, 1998)
Nome Commercial Co. v. National Bank of Alaska
948 P.2d 443 (Alaska Supreme Court, 1997)
Breck v. Moore
910 P.2d 599 (Alaska Supreme Court, 1996)
Chizmar v. MacKie
896 P.2d 196 (Alaska Supreme Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
808 P.2d 251, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hancock-v-northcutt-alaska-1991.