Advanced, Inc. v. Wilks

711 P.2d 524, 1985 Alas. LEXIS 329
CourtAlaska Supreme Court
DecidedDecember 27, 1985
DocketS-550
StatusPublished
Cited by9 cases

This text of 711 P.2d 524 (Advanced, Inc. v. Wilks) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Advanced, Inc. v. Wilks, 711 P.2d 524, 1985 Alas. LEXIS 329 (Ala. 1985).

Opinion

OPINION

RABINOWITZ, Chief Justice.

In June of 1980, Advanced, Inc. (Advanced) contracted with Michael and Jody Wilks to construct an elliptical earth-sheltered concrete house. The original contract price, was $81,875.00. The Wilks were not satisfied with the workmanship and thereafter brought suit against Advanced for breach of contract, breach of warranty, and violation of the Unfair Trade Practices and Consumer Protection Act, AS 45.50.471. The jury returned a special verdict in favor of the Wilks, awarding damages of $150,402.75. 1

On appeal Advanced does not contest the jury’s determination of liability, but argues that the jury’s damage award was excessive and based on erroneous instructions. Advanced also contends that the superior court erred in denying its motion for remit-titur or new trial and erred in not excluding certain testimony after discovery violations had occurred. We affirm.

I. Damages.

Among the instructions the jury received on damages was the following:

In determining damages to the plaintiffs, if you find that repair is feasible, you must compute the reasonable cost of putting the house in the condition which *526 was promised by the contract. If you find that repair is not feasible, you must compute the reasonable difference between the value the house would have had if it had been built as promised, and the value the house actually has. In other words, there are two different methods which can be used to decide the amount of the plaintiffs’ damages.
The normal way of deciding what damages to award to the plaintiffs is to give them the reasonable cost of putting the house in the same condition it would have been in had the defendant kept his promise.
However, if you find that it would be impractical and grossly wasteful, in proportion to the benefit to be gained, to repair the house so that it matches its promised condition, then you should not use this first method. Instead, for all conditions that can be repaired at disproportionate and wasteful expense, you should use the following method of measuring damages. You should award to the plaintiffs a sum which represents the difference between the value of the performance that the defendant promised and the value of the performance that the defendant actually gave.
If you decide that some defects are repairable, but that others can be repaired only at a disproportionate and wasteful expense, then you should use the cost of repair to measure damages for the repairable defects, and the drop in value to the measure of damages for the remaining non-repairable defects.

Advanced does not object to the above instruction, and for good reason. It is well established that the cost of completion or repair is the preferred measure for calculating damages when a building contractor breaches a construction contract by incomplete or defective performance. As Professor Dobbs notes in his treatise, this measure “gives the landowner the ability to get, with the damages awarded, a performance equivalent to what he has contracted for. This is a strong and worthy policy and naturally commends itself.” D. Dobbs, Remedies, § 12.21, at 899 (1973). See also 5 Corbin, Contracts §§ 1089-90 (1964). The diminution in value measure is to be used only when necessary to avoid unreasonable waste (as where a house would have to be torn down to replace plumbing that deviated only in a minor way from contract specifications). 2

The jury specifically found that Advanced had not substantially performed, and that it would not be impractical and grossly wasteful for the Wilks to repair the house. 3 The jury also found, in accordance with the Wilks’ testimony, that the value of the house without any defects would be between $150,000-$160,000.

Advanced’s primary contention is that, given the above finding as to the value of the house as promised, the award of $150,402.75 for the cost of repairs is excessive as a matter of law. More specifically, Advanced argues that the jury should have used the value measure of damages and awarded the difference between the value of the house as promised and the present value of the house. The jury, however, had before it insufficient evidence to calculate damages according to the value formula. It was specifically noted on the special verdict form that the jury could “not determine” the actual value of the house with defects. If Advanced thought that the cost of repairs was an unreasonable measure of damages given what it believed to be the relatively small decrease in value resulting from the breach, it clearly had the burden to present evidence from which the jury could find the diminution in value. The house was appraised twice, once at $98,000 in May, 1980, before construction began, and once at $114,000 in November, 1980, before completion of the *527 project. Many of the defects in the workmanship, however, did not become apparent until later. No appraisal was made of the house at the time of trial in 1984. The jury thus; correctly concluded that it could not determine the present value of the house as constructed without resorting to impermissible speculation.

Further, Advanced incorrectly states the rule of law. An owner’s recovery is not necessarily limited to diminution in value whenever that figure is less than the cost of repair. 4 It is true that in a case where the cost of repair exceeds the damages under the value formula, an award under the cost of repair measure may place the owner in a better economic position than if the contract had been fully performed, since he could pocket the award and then sell the defective structure. On the other hand, it is possible that the owner will use the damage award for its intended purpose and turn the structure into the one originally envisioned. He may do this for a number of reasons, including personal esthetics or a hope for increased value in the future. If he does this his economic position will equal the one he would have been in had the contractor fully performed. 5 The fact finder is the one in the best position to determine whether the owner will actually complete performance, or whether he is only interested in obtaining the best immediate economic position he can. In some cases, such as where the property is held solely for investment, the court may conclude as a matter of law that the damage award can not exceed the diminution in value. Where, however, the property has special significance to the owner and repair seems likely, the cost of repair may be appropriate even if it exceeds the diminution in value. 6

Advanced also contends that the court erred in giving the following damage instruction to the jury.

The plaintiffs are entitled to the greater of the following amounts:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Landis v. William Fannin Builders, Inc.
951 N.E.2d 1078 (Ohio Court of Appeals, 2011)
Breck v. Moore
910 P.2d 599 (Alaska Supreme Court, 1996)
Hancock v. Northcutt
808 P.2d 251 (Alaska Supreme Court, 1991)
Sirotiak v. H.C. Price Co.
758 P.2d 1271 (Alaska Supreme Court, 1988)
Ault v. Dubois
739 P.2d 1117 (Court of Appeals of Utah, 1987)
State v. Doyle
735 P.2d 733 (Alaska Supreme Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
711 P.2d 524, 1985 Alas. LEXIS 329, Counsel Stack Legal Research, https://law.counselstack.com/opinion/advanced-inc-v-wilks-alaska-1985.