Charest v. Busby

141 So. 2d 466, 1962 La. App. LEXIS 1967
CourtLouisiana Court of Appeal
DecidedMay 16, 1962
DocketNo. 5546
StatusPublished
Cited by5 cases

This text of 141 So. 2d 466 (Charest v. Busby) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charest v. Busby, 141 So. 2d 466, 1962 La. App. LEXIS 1967 (La. Ct. App. 1962).

Opinion

LANDRY, Judge.

Plaintiff Maurice Charest D/B/A Trans-State Remodeling Company instituted this action to recover the sum of $1,210.00 together with attorney’s fees of 20% of said amount and interest on both sums at the rate of five per cent per annum, allegedly due by defendant Busby under a written contract for the repair and remodeling of defendant’s residence situated in the City of Bogalusa, Louisiana.

Initially named as defendants herein were Mr. and Mrs. Ray O. Busby. Exceptions of no right and no cause of action filed on behalf of Mrs. Busby were sustained by the trial court and plaintiff’s action dismissed as to her. Plaintiff having failed to appeal from the judgment dismissing his action as to Mrs. Busby, said defendant is no longer a party to this litigation.

Pursuant to the written contract between the parties to this suit plaintiff, in consideration of defendant’s agreement to pay the sum of $1,210.00, undertook to perform the following work upon defendant’s residence:

1.Renail all loose weatherboards where necessary.
2. Replace rotten weatherboard where necessary.
3. Check the home for termites; replace the rear sill — -12 Ft. long.
4. Cover the front up to the windows with tan terox and up to the front door on the side of the house.
5. Cover the balance of the house with white “shake” (sic).
6. Caulk and seal around all windows and doors.
7. Use rust proof nails and corners.

Plaintiff completed the foregoing items of construction, tendered the work for defendant’s acceptance and, upon defendant’s rejection thereof because of certain alleged defects therein, instituted this action to recover the sums hereinabove mentioned. After trial on the merits the lower court decreed that although plaintiff had not fully complied with the contract, plaintiff was nevertheless entitled to reimbursement of expenses in the sum of $1,100.59 incurred by plaintiff in the performance of the work and rendered judgment in favor of plaintiff and against defendant in said amount. No disposition was made of defendant’s recon-ventional demand for damages predicated upon plaintiff’s alleged failure to perform the renovation in a workmanlike manner as called for in the contract. From said adverse judgment defendant has taken this appeal. Plaintiff has neither appealed nor answered defendant’s appeal.

Defendant-appellant first complains of error on the part of the learned trial judge in failing to declare the contract null and void on the ground that it contains a potestative condition.

Although Article 2034 LSA-C.C. provides that a contract containing a potestative condition is null and void, it is settled jurisprudence that such an agreement is merely voidable and that if there has been full or partial performance thereof by the obligor, the obligee is not permit[469]*469ted to advance the defense of nullity on the ground that the obligor was at liberty to refrain from performance. Hansman v. Uddo & Taormina Company, La.App., 76 So.2d 753; Owens v. Muslow, 166 La. 423, 117 So. 449. Assuming, arguendo, there were any merit in defendant’s contention with regard to the alleged potestative condition contained in the agreement, defendant having permitted plaintiff to perform the obligation assumed therein, is now es-topped to urge such defense.

In the alternative defendant urges that plaintiff did not perform all of the work called for in the contract; that the work done by plaintiff was not performed in a workmanlike manner; and that the work was so defective virtually the entire project will have to be redone. By far the greater portion of the work called for in the contract consisted of the application of Terox to the exterior of the residence across the entire front and a portion of one side thereof from the ground to a height just below the windows and covering the remainder of the exterior around the entire house with aluminum siding applied over existing weatherboarding. The record reveals that Terox is an imitation stone siding so constructed and applied as to resemble building stone upon installation. To achieve the desired effect imitation stone squares and rectangles of various sizes are affixed to the exterior of a building with cement or mortar much in the manner of bricks or cement building blocks.

The learned trial court found that the following defects existed in the work performed by plaintiff:

“(1) A narrow strip of siding was left off the home over the double windows on the south side of the defendant’s house.
(2)Two pieces of siding were not trimmed off even with the rest of the siding by the rafters on the south side of the house.
(3) The corner caps were loose.
(4) The Terox was placed on the house in such a manner that the vertical joints were not properly staggered.”

The trial court further held that while the above listed defects were not particularly important they nevertheless detracted from the appearance of the house to such extent as to justify the conclusion plaintiff had not complied with the contract. Despite such obvious inconsistency, our esteemed brother below held that plaintiff was entitled to out of pocket expenses.

In so holding our brother below fell into error. Partial performance by a contractor entitles him to the value of the work done and not to the amount of expense incurred therein. It is the settled jurisprudence of this state that where there has been substantial compliance with the terms and conditions of a building contract, the contractor is entitled to the value of the work done by him if a price has been agreed upon even though the work be unfinished or defective and the sole remedy of the owner is to seek a reduction in the contract price by such amount as is necessary to complete the work according to the provisions of the agreement. Jack v. Henry, La.App., 128 So.2d 62; Jones v. Tusa, La.App., 100 So.2d 799.

Besides the defects found by the learned trial court, defendant complains of the following alleged additional imperfections:

(a) No termite inspection was made;
(b) Drip caps were not installed over doors and windows;
(c) Along one side of the house the aluminum siding was not installed so as to conceal the sills;
(d) The aluminum siding was not installed in a straight and level manner; and
[470]*470(e) The siding was not uniformly applied up to and around the rafters.

No citation of authority is needed in support of the proposition that compliance with a building contract is a question of fact to be determined in the light of the circumstances of each particular case.

Regarding plaintiff’s alleged failure to make a termite inspection defendant testified that no such inspection was made whereas plaintiff testified that such an inspection was in fact conducted and defendant notified as to the results thereof. In this connection it is desired to point out that the contract only called for plaintiff to check for termites. If termites were discovered it was not incumbent upon plaintiff to treat the residence against such insects.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ortego v. Dupont
611 So. 2d 792 (Louisiana Court of Appeal, 1992)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)
Maher & Sharkey, Inc. v. Newman
198 So. 2d 162 (Louisiana Court of Appeal, 1967)
U-Finish Homes, Inc. v. Michel
183 So. 2d 101 (Louisiana Court of Appeal, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
141 So. 2d 466, 1962 La. App. LEXIS 1967, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charest-v-busby-lactapp-1962.