Pamper Corporation v. Town of Marksville

208 So. 2d 715
CourtLouisiana Court of Appeal
DecidedJune 7, 1968
Docket2212
StatusPublished
Cited by12 cases

This text of 208 So. 2d 715 (Pamper Corporation v. Town of Marksville) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pamper Corporation v. Town of Marksville, 208 So. 2d 715 (La. Ct. App. 1968).

Opinion

208 So.2d 715 (1968)

PAMPER CORPORATION, Plaintiff-Appellant,
v.
TOWN OF MARKSVILLE, Defendant-Appellee.

No. 2212.

Court of Appeal of Louisiana, Third Circuit.

March 27, 1968.
Rehearing Denied April 22, 1968.
Writ Refused June 7, 1968.

*716 Thompson, Thompson & Sparks, by James D. Sparks and Robert Cudd, III, Monroe, for plaintiff-appellant.

*717 Edwin L. Lafargue, Charles A. Riddle, Jr., Marksville, for defendant-appellee.

Before FRUGE, SAVOY, and LEAR, JJ.

FRUGE, Judge.

Plaintiff, Pamper Corporation, is suing the defendant, Town of Marksville, for sums allegedly owed plaintiff as a result of extra work performed pursuant to a construction contract under which plaintiff paved and improved a number of streets in the Town of Marksville. Plaintiff sought recovery of $33,303.89, but the trial court rendered judgment in its favor for only $20,050.22, which sum represented the amount of retainage which defendant admittedly owed plaintiff. Having been denied recovery on all its contested claims, plaintiff effected this devolutive appeal.

Plaintiff-appellant's claims fall under three general headings:

I. Claims for extra work performed not included in the original contract.
II. The propriety of defendant's assessing $2,520.00 held as liquidated damages.
III. The date from which interest on the amount of $20,050.22 awarded by the trial court should accrue.

I

First, we shall consider plaintiff's claim for expenses incurred over and above that contemplated in the construction contract. Plaintiff, of course, seeks to prove those expenses through evidence extrinsic to the contract itself.

The general rule relative to such proof is that the written contract speaks for itself and all parties thereto are bound by its provisions. Therefore, the contractor usually cannot collect for any "extra costs" incurred it in performing under the contract. See C.C. Arts. 1901, 1945, 2276. Meaux v. Southern Construction Corp., 159 So.2d 156 (La.App. 3d Cir., 1963).

This rule is not absolute, however, and there are some instances where a contractor may be permitted to recover for expenses incurred by him which were not included in the contract. See Civil Code Arts. 2763, 2764; Roff v. Southern Construction Corp., 163 So.2d 112 (La.App. 3d Cir., 1964); Groner v. Cavender, 16 La. App. 565, 133 So. 825 (La.App. 2d Cir., 1931).

Even where the contract had a provision to the effect that the owner shall not be liable for any extra work unless the owner has given written authorization for that work, the consistent actions of the two parties may be found to constitute a "waiver" of this provision, and recovery can be allowed the contractor, notwithstanding that no written authorization was given by the owner to perform such additional work. See Roff v. Southern Construction Corp., supra, and cases discussed therein; Groner v. Cavender, supra.

A. Plaintiff's first item of extra work for which it claims remuneration is its replacing some old culverts with new culverts, where the contract contained no provision therefor. The pertinent contractual provision states:

"All driveway and walkway culverts and bridges shall be removed with care, and immediately replaced * * * [by plaintiff] if in the opinion of the Resident Engineer, such pipe or bridges are of adequate size and suitable condition for reuse."

Plaintiff contends that it replaced culverts which were not suitable for reuse with new ones under the direction of the resident engineer, in spite of the fact that under the above-quoted provision, it was not required to do so. Therefore, plaintiff seeks recovery for the cost to it for replacing those culverts it claimed to be not *718 of "adequate size and suitable condition for reuse".

We agree with the trial court in holding that this claim must be rejected for various reasons. First, the determination of which of the culverts were of adequate size and suitable for reuse is a determination left entirely up to the judgment of the resident engineer under the terms of the contract. The contract is silent as to what is to be done in regard to old culverts not suitable for reuse. The record does not indicate what culverts or how many were not of sufficient size and suitable condition for reuse. Plaintiff's claim, therefore, is based upon the opinion of its engineer, Mr. Poulas, and not the findings of the resident engineer, as required in the contract.

Second, the record reveals the president of the corporation had agreed with the Mayor of the Town of Marksville that (according to the mayor's testimony) it would be permissible under the terms of the contract to allow replacement of some of the old culverts with new culverts, which the plaintiff would install without any charge whatsoever to the defendant, because such would involve no substantial added expense to plaintiff. Thus, the installation of new culverts in the place of old culverts removed was apparently thought by the parties to be consistent with the terms of the contract.

Finally, contrary to the provisions of the contract, the plaintiff submitted no claim for this extra work until after all the work was completed and the construction project was approved by defendant.[1]

In the alternative, plaintiff also seeks recovery of this item in quantum meruit. But the record fails to support the application of this principle, especially since we have already concluded that plaintiff failed to prove that this item constituted "extra work" over and above that called for by the contract.

This item, therefore, was properly rejected.

B. Plaintiff's next item emanates from its being required to use machinery allegedly different from that contemplated by the contract.

Under the contract it was plaintiff's duty to shape the roadways upon which it was working. In regard to the manner in which this was to be done, the specifications provide:

"Ditches shall be pulled, fore slopes and shoulders shaped and the various sections of the roadway, after shaping, shall be not less than the minimum requirements as shown on the Plans, unless otherwise directed by the Engineers.
"Existing side drains to private drives and alleys shall be removed to permit pulling the ditches and shaping the roadway and shall be immediately replaced following the completion of these operations. No payment will be allowed for this work, but the cost therefor shall be included in the prices bid on the various pay items." (Emphasis ours.)

Plaintiff's expert, Mr. Poulas, testified that the above-emphasized language contemplates the use of a "motor patrol" in the ditches and not the use of a "gradeall". He stated that the motor patrol could do the job much more quickly than a gradeall if the drains and the driveways were removed beforehand. Mr. Poulas further testified that the resident engineer issued a written instruction to plaintiff requiring that it perform this work with a gradeall. As a result, plaintiff had to rent a gradeall, at its expense, and the portion of the contract involving its use—that is, the shaping of the roadways section—took plaintiff about *719 twice the time it otherwise would have taken had it been able to use a motor patrol.

Defendant's witnesses testified differently in regard to this matter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Red River Parish Port Commission v. Headwaters Resources Inc.
698 F. Supp. 2d 684 (W.D. Louisiana, 2010)
Taita Chemical Co. v. Westlake Styrene Corp.
246 F.3d 377 (Fifth Circuit, 2001)
L & a CONTRACTING v. Ram Indus. Coatings, Inc.
762 So. 2d 1223 (Louisiana Court of Appeal, 2000)
BIG" D" DIRT SERVICES INC. v. Westwood, Inc.
653 So. 2d 604 (Louisiana Court of Appeal, 1995)
O & M Construction, Inc. v. State, Division of Administration
576 So. 2d 1030 (Louisiana Court of Appeal, 1991)
O & M CONST. v. State, Div. of Admin.
576 So. 2d 1030 (Louisiana Court of Appeal, 1991)
Gravier Co. v. Satellite Business Sys.
519 So. 2d 180 (Louisiana Court of Appeal, 1987)
North Central Utilities, Inc. v. East Columbia Water District
497 So. 2d 326 (Louisiana Court of Appeal, 1986)
Pelican Elec. Contractors v. Neumeyer
419 So. 2d 1 (Louisiana Court of Appeal, 1982)
Welch-Eckman Construction Co. v. Vancouver Plywood Co.
213 So. 2d 134 (Louisiana Court of Appeal, 1968)
Pamper Corp. v. Town of Marksville
210 So. 2d 509 (Supreme Court of Louisiana, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
208 So. 2d 715, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pamper-corporation-v-town-of-marksville-lactapp-1968.