BIG" D" DIRT SERVICES INC. v. Westwood, Inc.

653 So. 2d 604, 1995 WL 81901
CourtLouisiana Court of Appeal
DecidedMarch 1, 1995
Docket94-1234
StatusPublished
Cited by7 cases

This text of 653 So. 2d 604 (BIG" D" DIRT SERVICES INC. v. Westwood, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BIG" D" DIRT SERVICES INC. v. Westwood, Inc., 653 So. 2d 604, 1995 WL 81901 (La. Ct. App. 1995).

Opinion

653 So.2d 604 (1995)

BIG "D" DIRT SERVICES, INC., Plaintiff-Appellant,
v.
WESTWOOD, INC. and Capital College Funding Bonding Co., Defendants-Appellees.

No. 94-1234.

Court of Appeal of Louisiana, Third Circuit.

March 1, 1995.
Rehearing Denied May 15, 1995.

Kathy Fontenot Deshotel, Ville Platte, for Big "D" Dirt Services, Inc.

John Isidore Feduccia, Hammond, for Westwood, Inc. and Capital College Fund.

David Carlyle Voss, Baton Rouge, for State of La., DOTD.

Before PETERS, AMY and SULLIVAN, JJ.

SULLIVAN, Judge.

This contractual dispute involves $5,539.93 allegedly owed to plaintiff-appellant, Big "D" *605 Dirt Services, Incorporated, by defendants-appellees, Westwood, Incorporated and American Bonding Company. Big "D" initially sued Westwood and Capital College Funding Bonding Company, then later amended its petition to name the State of Louisiana, Department of Transportation and Development (DOTD) and American Bonding Company as defendants. During trial, DOTD was dismissed as a party defendant pursuant to its motion for involuntary dismissal. DOTD is not a party to this appeal.

Westwood, the general contractor on State Project XXX-XX-XX involving the construction of the Coulee de Manuel bridge, subcontracted with Big "D" for the application of asphaltic concrete to the roadway bridge approaches. The contract price was $13,455.00. Because the DOTD rejected Big "D"'s work, Westwood hired a third party, James Construction, to correct the defects in Big "D"'s work. The corrective work cost $5,539.93. Westwood then refused to pay Big "D" for its work on the project.

Big "D" then sued defendants, seeking the payment of the subcontract amount, $13,455.00. Westwood deposited the amount not in dispute, $7,915.07, into the registry of the court. By court order, Big "D" removed this money from the court registry and, thereafter, the case proceeded to trial. After trial, the district court dismissed Big "D"'s claim against Westwood and American Bonding. The trial judge concluded that Westwood was justified in obtaining the services of James Construction to do the remedial work because of Big "D"'s delay in informing Westwood that it had contracted with H & S Construction to do the work. In addition, he found that the amount paid to James Construction, $5,539.93, was reasonable. On appeal, plaintiff asserts the following specifications of error:

1) the trial court erred in failing to apply the written provisions of the contract, specifically paragraph 22 regarding termination of the contract; and
2) the trial court erred in failing to award damages and attorneys fees for defendants' failure to pay the undisputed amount until after suit was filed.

For the following reasons, we affirm the denial of Big "D"'s claim for the balance owed on the subcontract, $5,539.93. However, we remand this case to the trial court for a hearing on the issue of whether defendants are liable to plaintiff pursuant to La.R.S. 9:2784(C) for penalties and attorney fees for defendants' failure to promptly pay the undisputed amount, $7,915.07.

FACTS

The events pertinent to this case occurred in 1992. The subcontract at issue was executed on April 14 by Dallas Leger, the owner of Big "D", and Janice Amar, the owner of Westwood. Pursuant to the agreement, Big "D" was to overlay the bridge approaches with approximately 207 tons of asphaltic concrete. Big "D" performed the work on May 4 and 5. The paving covered between 150 and 200 feet of roadway on each side of the bridge. On May 14, Amar called Leger to inform him that the DOTD engineer, Woodson Harvey, recommended rejection of Big "D"'s overlay work. She also told him of a May 20 DOTD inspection meeting at the site.

Leger went to the meeting where DOTD project engineer Irvin Deranger informed him that his work was unacceptable and needed correction. Also present at this meeting were DOTD engineer Harvey, DOTD inspector Larry Fontenot, and Westwood representatives Amar and Eric Arender.

The details of what actions followed this meeting are subject to dispute. Leger testified that DOTD ordered him to "mill" or grind off one to one and one-half inches in depth of the road surface at a distance of 40 feet on each side of the bridge. After the meeting, Leger had lunch with Amar and Arender to discuss how to correct the defects in his work. Leger did not own a milling machine and would have to rent one from another construction company. He told Amar and Arender that he would attempt to locate one. Leger stated that, after the lunch meeting, he contacted H & S Construction on the same day. H & S Construction informed him that it could do the milling on July 13. He agreed. However, Leger did not thereafter inform Westwood of the arrangements *606 made with H & S Construction. He stated that Westwood did not impose a time limit within which to complete the corrective work. Also, neither Amar or Arender informed him that Westwood would actively solicit a contractor to do the corrective work. He did not speak again with anyone representing Westwood until sometime in July.

Leger further explained that, on July 9, he returned to the construction site and observed a James Construction milling machine. He spoke to Patrick Morein, a James Construction employee, then returned to his office. That day, Leger called H & S Construction to advise them to not do the milling work because it had already been done. Thereafter, Leger had no contact with Westwood's Amar or Arender.

On July 17, Big "D" filed a notification of contract dispute with the DOTD seeking payment of the total amount owed, $13,455.00. The dispute form states that, on July 17, Big "D" contacted Westwood to notify them that it would begin milling operations in the next week. This statement indirectly contradicts Leger's testimony that, on July 9, he knew the work was being done by James Construction. On July 28, Big "D" filed a lien against Westwood and American Bonding in the Evangeline Parish public records.

Kathy Wheller,[1] Big "D"'s office manager, also testified at trial. She stated that, at some point around July 10, Arender informed her that James Construction had already done the milling work. This conversation took place when she called Arender to inform him that H & S Construction would do the work. She did not recall receiving any notice from Westwood with regard to its hiring of James Construction to do the milling work. She then contradicted her prior testimony by stating that the DOTD contract dispute form, which reflected that July 17 was the date upon which Big "D" discovered that Westwood hired James Construction, accurately represented what had occurred.

Amar testified on behalf of Westwood. Her version of the events was different from that of Leger and Wheller. She stated that at the May 20 lunch meeting, Leger told her that there was no way for him to do the milling work because he did not have the proper equipment. Leger allegedly then stated he wanted to talk to Deranger first to try to change Deranger's decision to reject his work.

On May 26, Amar spoke to Deranger, who had not changed his mind. She called Leger to inform him of this, and Leger allegedly said that he would try to contact James Construction to do the milling work. On June 3, Amar spoke to Leger and told him she would call James Construction herself. The next day, she spoke to Leger again and informed him that she would try to keep the price of the milling below $6,000.00 so that Leger would not lose money.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meagan Lemoine v. Lionel Augustine
Louisiana Court of Appeal, 2017
Guinn Bros., LLC v. Jones Brothers, Inc. of Tennessee
287 F. App'x 298 (Fifth Circuit, 2008)
Cajun Constructors v. Fleming Const. Co.
951 So. 2d 208 (Louisiana Court of Appeal, 2006)
Carmouche Law Firm, APLC v. Pias
880 So. 2d 49 (Louisiana Court of Appeal, 2004)
The Carmouche Law Firm, Aplc v. Scott J. Pias
Louisiana Court of Appeal, 2004
Taita Chemical Co. v. Westlake Styrene Corp.
246 F.3d 377 (Fifth Circuit, 2001)
L & a CONTRACTING v. Ram Indus. Coatings, Inc.
762 So. 2d 1223 (Louisiana Court of Appeal, 2000)
Four Rivers Gaming, Inc. v. Reliable Amusement Co.
737 So. 2d 938 (Louisiana Court of Appeal, 1999)
Robinson v. Thornton
705 So. 2d 745 (Louisiana Court of Appeal, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
653 So. 2d 604, 1995 WL 81901, Counsel Stack Legal Research, https://law.counselstack.com/opinion/big-d-dirt-services-inc-v-westwood-inc-lactapp-1995.