Cajun Constructors v. Fleming Const. Co.

951 So. 2d 208, 2006 WL 3302820
CourtLouisiana Court of Appeal
DecidedNovember 15, 2006
Docket2005 CA 2003
StatusPublished
Cited by16 cases

This text of 951 So. 2d 208 (Cajun Constructors v. Fleming Const. Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cajun Constructors v. Fleming Const. Co., 951 So. 2d 208, 2006 WL 3302820 (La. Ct. App. 2006).

Opinion

951 So.2d 208 (2006)

CAJUN CONSTRUCTORS, INC.
v.
FLEMING CONSTRUCTION CO., INC. and Travelers Casualty & Surety Company of America.

No. 2005 CA 2003.

Court of Appeal of Louisiana, First Circuit.

November 15, 2006.
Rehearing Denied January 31, 2007.

*210 R. Gray Sexton, Michael D. Dupree, Tracy Meyer Walker, Baton Rouge, Counsel for Plaintiff/Appellee Cajun Constructors, Inc.

H. Bruce Shreves, James A. Burton, Herman C. Hoffmann, Jr., Denise C. Puente, New Orleans, Counsel for Defendant/Appellant Travelers Casualty & Surety Company of America.

David C. Voss, Matthew G. Tessier, Baton Rouge, Counsel for Defendant/Appellant Fleming Construction Co., Inc.

Before: PARRO, GUIDRY, and McCLENDON, JJ.

McCLENDON, J.

The defendants, Fleming Construction Co., Inc. (Fleming) and Travelers Casualty & Surety Company of America (Travelers), appeal the trial court judgment in favor of the plaintiff, Cajun Constructors, Inc. (Cajun), granting Cajun's motions for partial summary judgment against Fleming and Travelers, and awarding Cajun penalties, attorney fees and costs. For the reasons that follow, we affirm in part and reverse in part.

*211 FACTS AND PROCEDURAL HISTORY

On June 12, 2000, the United States Army Corps of Engineers (Corps), as owner, entered into a construction contract with Fleming, as general contractor, for construction of a project entitled the "Southeast Louisiana Flood Control Project, Pipeline Canal Improvements and Hurricane Protection, Westwego to Harvey Canal, Estelle Pumping Station Floodwall, Jefferson Parish, Louisiana" (the Project). As required by the contract, Fleming entered into a payment bond surety agreement with Travelers, pursuant to 40 U.S.C. § 3131(b) (the Miller Act).[1]

The Project consisted of work on the pipeline canal portion of the Project and work near the Estelle Pumping Station.[2] It is the pumping station portion of the Project that gave rise to the dispute resulting in this lawsuit. As part of the pumping station portion of the Project, Fleming was instructed to construct a large concrete wall in the shape of an inverted "T" on either side of the pumping station for flood protection. According to the plans and specifications of the contract, this T-Wall was to be constructed in an area that was thoroughly drained, so that the concrete could be poured and allowed to set in dry conditions. The task of creating this dry area was Item 0041, entitled "Drainage Control Dikes," of the fifty-four line items in the contract between the Corps and Fleming. The specifications did not describe how Fleming was to keep the area dry, other than to state that Fleming could use either "earthen dikes and or sheeting."[3]

In May of 2000, Fleming had requested Cajun to submit a bid for pile and sheet driving services on the Project. On May 17, 2000, Cajun submitted a written proposal to Fleming to perform nine items, for a total lump sum price of $773,392.50. One item was "0041 Temp. Dikes" to "Install & Remove 200 Wall Feet of PZ-27 × 40' including Bracing" (Item 0041), for the price of $200,520.00. The purpose of the wall of sheet piling was to enable Fleming to "dewater" the area on the unprotected side of the Estelle Pump Station Floodwall, so that Fleming could place required rip-rap (chunks of concrete) in the dewatered area.

Following receipt of Cajun's proposal, Fleming revised its bid on Item 0041 with the Corps to $225,000.00, and on June 12, 2000, entered into the contract with the Corps for the total contract amount of $3,342,411.00. Thereafter, on June 19, 2000, Fleming entered into the subcontract agreement with Cajun, which incorporated *212 Cajun's proposal and called for payments by Fleming to Cajun for the total lump sum price of $773,392.50.

Sometime thereafter, a meeting occurred between representatives of the Corps and representatives of both Fleming and Cajun. During the meeting, the Corps was advised of Fleming's intent to have Cajun install the 200-foot wall as a temporary dam. That plan, however, was vetoed by the Corps, as Fleming was informed by the Corps that it would not require Fleming to completely dewater the area on the unprotected side of the flood-wall to apply the rip-rap. Instead, and as a result of the meeting, Fleming constructed earthen dikes adjacent to and along the two T-wall areas to allow those areas to drain as required by the specifications with the Corps. Fleming verbally contracted with Cajun to drive sheet pilings to shore up the ends of the earthen dikes, but this work was paid on a time and material basis. No written change order was made to the contract between Fleming and Cajun to delete the construction and removal of the wall of sheet piling as set forth in Item 0041.

The Project was successfully completed by Fleming in the fall of 2001, and Fleming was paid all amounts due by the Corps. Fleming deducted $200,520.00 from the total subcontract amount with Cajun and paid Cajun the difference.[4]

On December 23, 2002, Cajun filed a Petition for Breach of Contract against Fleming and Travelers in the Nineteenth Judicial District Court, seeking the remaining contract balance amount of $200,520.00, penalties and attorney fees.[5]

In response to the lawsuit, Fleming and Travelers filed an Exception of Res Judicata, No Right of Action and Lack of Subject Matter Jurisdiction, which were denied by the trial court. Fleming and Travelers then filed their answer and asserted a reconventional demand against Cajun for certain costs relating to sheet pile bracing, sheet rental, and overtime work. Thereafter, on June 28, 2004, the parties filed cross-motions for partial summary judgment. Cajun's motion for partial summary judgment sought dismissal of Fleming's and Traveler's reconventional demand and also sought judgment against Fleming and Travelers for the remaining subcontract balance. Fleming and Travelers sought dismissal of Cajun's claim for the subcontract balance. On December 13, 2004, the trial court denied the cross motions for summary judgment on the main demand, and granted Cajun's motion for summary judgment dismissing Fleming's reconventional demand as to Cajun.[6]

On January 27, 2005, Cajun filed another Motion for Partial Summary Judgment against Fleming only, for the remaining contract balance. Following a hearing on February 14, 2005, the trial court granted the motion and awarded Cajun $200,520.00, reserving the right of Cajun to file a rule to recover penalties, attorney *213 fees and costs. Judgment to this effect was signed on March 16, 2005.

On March 15, 2005, Cajun filed a Rule to Show Cause against Fleming and Travelers to set and assess costs, penalties, and attorney fees. Following a hearing, the trial court rendered judgment in favor of Cajun and against Fleming only. On June 3, 2005, judgment was signed awarding Cajun penalties in the amount of $30,078.00, attorney fees in the amount of $79,402.78, expert costs in the amount of $5,693.47, and deposition costs in the amount of $5,290.36.[7]

On March 15, 2005, Cajun also filed a Motion for Partial Summary Judgment against Travelers on the bond Travelers had posted on behalf of Fleming. Following a hearing on the matter, the trial court rendered judgment in favor of Cajun and against Travelers for the remaining contract amount of $200,520.00. Judgment was signed on June 3, 2005.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Semco, LLC v. Grand Ltd.
221 So. 3d 1004 (Louisiana Court of Appeal, 2017)
Driver Pipeline Co. v. Cadeville Gas Storage, LLC
150 So. 3d 492 (Louisiana Court of Appeal, 2014)
Monroe v. Physicians Behavioral Hospital, LLC
147 So. 3d 787 (Louisiana Court of Appeal, 2014)
Amitech U.S.A., Ltd. v. Nottingham Construction Co.
57 So. 3d 1043 (Louisiana Court of Appeal, 2010)
Lantech Construction Co. v. Speed
15 So. 3d 289 (Louisiana Court of Appeal, 2009)
Superior Steel, Inc. v. Woodrow Wilson Construction Company, Inc.
996 So. 2d 701 (Louisiana Court of Appeal, 2008)
Assaleh v. Sherwood Forest Country Club Inc.
991 So. 2d 67 (Louisiana Court of Appeal, 2008)
Fleming v. JE Merit Constructors, Inc.
985 So. 2d 141 (Louisiana Court of Appeal, 2008)
Opinion Number
Louisiana Attorney General Reports, 2007

Cite This Page — Counsel Stack

Bluebook (online)
951 So. 2d 208, 2006 WL 3302820, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cajun-constructors-v-fleming-const-co-lactapp-2006.