Lantech Construction Co. v. Speed

15 So. 3d 289, 8 La.App. 5 Cir. 811, 2009 La. App. LEXIS 975, 2009 WL 1464129
CourtLouisiana Court of Appeal
DecidedMay 26, 2009
Docket08-CA-811
StatusPublished
Cited by12 cases

This text of 15 So. 3d 289 (Lantech Construction Co. v. Speed) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lantech Construction Co. v. Speed, 15 So. 3d 289, 8 La.App. 5 Cir. 811, 2009 La. App. LEXIS 975, 2009 WL 1464129 (La. Ct. App. 2009).

Opinion

MARION F. EDWARDS, Judge.

|2Both plaintiff/appellant, Wilbur J. Ba-bin Jr., as trustee of LanTech Construction Company, LLC (“LanTech”), and defendant/cross-appellant, David Speed d/b/a Driftwood Spur (“Speed”), appeal from a judgment of the district court granting Speed liquidated damages in the amount of $31,400 and the cost of concrete repairs in the amount of $112,212.50.

In January 2000, Speed entered into a contract with LanTech for the renovation/conversion of a Texaco station in Ken-ner. The initial price of the project was $203,507. In its Petition for Breach of Contract and Damages, LanTech averred that change orders increased the price to $217,874 of which $45,598 remained unpaid. Ultimately, Speed filed a Reconven-tional Demand for sums expended to complete and/or repair the project, including the cost of removal and replacement of concrete. Speed also asked for liquidated damages for failure of LanTech to timely complete the project.

| :iTrial commenced on December 13, 2004, at which time only Speed’s testimony was taken. After more delays, the parties agreed in 2008 to submit depositions as trial testimony. On May 22, 2008, the trial court rendered its judgment, finding:

1. That the parties entered into “very sloppy business practices,” and that LanTech failed to show evidence that Speed signed any change orders as mandated by the contract.
2. That Speed benefited by the work done and that LanTech was entitled to the cost of the change orders, subject to setoff for damages due to Speed.
3. That the concrete work in the project was defective because of the poor workmanship of LanTech, and Speed was entitled to $112,212.50 for the cost of repairs.
4. That Speed was entitled to liquidated damages in the amount of $31,400 as per the contract for failure to timely complete the project.

*291 On appeal, LanTech urges that the trial court erred in failing to enforce the express provisions of the contract; that the trial court’s ruling was inherently inconsistent in awarding the cost for the change orders but not the time to perform them; and that Speed’s testimony was contradictory and unreliable and should have been disregarded in toto. On cross-appeal, Speed counters that the court erred- in permitting any recovery by LanTech pursuant to change orders improperly executed and that there was no evidence that the cost of the change orders was approved, or that it was reasonable and justified. Speed also argues that the trial court erred in failing to grant his Motion for Involuntary Dismissal. However, the record was designated by both Lantech and Speed and contains no motion for involuntary dismissal. Therefore, we decline to consider that assignment of error.

In trial testimony, Speed testified that the architect, Charles Ward of Rozas-Ward Architects (“Ward”), designed a renovation of the premises in question. He stated that he did not “think” he had signed a contract with LanTech. Ward orally informed Speed that he knew someone (LanTech) who could handle the Lrenovations. LanTech and Speed orally agreed on a contract price of “around $200,000.” Kevin Marino (“Marino”) was the contractor who worked on the premises. Since Marino left, the roof has been repaired and some of the pipes had recently cracked in the slab. However, Speed stated that recent photographs shown to him at trial depict the premises as they looked when the job was completed, and the station has continued to be in use since August of 2000.

Speed complained to Ward about the renovations several times because of mistakes that were being made. Marino did not come every day. The concrete laid by LanTech is chipping, cracking, and dissolving. The City of Kenner told Speed he needed a “grease trap” behind the building, as well as a dike with a drain. Speed agreed that these items were required. The city also required extra pilings. In addition, Speed told Marino to fence in the property around the dumpster, which had to be moved from one side of the building to the other. Speed also wanted fencing around the air conditioning compressors. The air conditioning units had to be changed because the wrong ones were installed. There was an increase of $5000 in cost regarding the air conditioners, but Speed agreed with Marino to “leave it alone” because he didn’t want to pull the units out. Some changes had to be made because of drainage and lighting problems. The neighbors did not want the big lights that had been installed, and Speed asked Marino to change them. Speed requested an upgrade change in ceiling tiles, which resulted in a delay.

Speed testified that he would pay Mari-no when he was given a bill and when Marino had completed a certain amount of work. He had heard that LanTech was going to go bankrupt and held back on paying Marino because of the problems he saw with the concrete. According to Speed, LanTech did not finish everything when it left the job. When Speed got the final bill, he did not pay it nor did he contact Ward to complain about what had not been completed.

| r,Speed’s deposition, which continued his trial testimony, was taken in 2007. In contrast to that testimony, Speed denied having approved any extensions of time or changes in price. The delays occurred because no one was on the job.

Copies of the Change Orders submitted separately as exhibits by the plaintiff/appellant and the defendant/appellee have significant discrepancies in both the signa *292 tures and dates on which they were signed. They can be summed up as follows:

Change Order # 1 — revision of gas company footings — add five days.
Change Order #2 — remove storefront, add seven days; block work in storefront, add seven days; addition of a grease trap, add five days; additional fencing at the rear, add three days; upgrade of air conditioner, add five days. Change Order # 3 — change of ceiling tiles — add fifty-five days. LanTech’s exhibit shows 400 days, clearly an error according to Architect Charles Ward. Date of substantial completion changed to June 2.
Change Order # 4 — additional concrete footage, add ten days. Speed’s exhibit shows addition of forty days, with a substantial completion date of July 12. Change Order # 5 — canopy drainage, add forty days. The completion date is July 27.
Change Order # 6 — adding gate, enclosure around air compressor, fir down between cigarette rack and ceiling, add ten days. Date of substantial completion is August 10. Speed was given credit for overage on contract time, thirty days at $200 per day or $6000.

Ward testified by deposition that Speed was concerned about the delays in the work. Speed received a credit of $6000 on Change Order # 6 for the number of days that the contractor was late. The change order work was discussed primarily between Speed and Marino. The Application Certification for Payment stated that the work was completed by August 10, 2000, but, due to issues with Speed about the delay of the job and the quality of the concrete finish, the document was not signed until March 21, 2001. Ward, who had authority to reject work that did not conform to the contract, felt that the concrete was within the industry standard.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
15 So. 3d 289, 8 La.App. 5 Cir. 811, 2009 La. App. LEXIS 975, 2009 WL 1464129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lantech-construction-co-v-speed-lactapp-2009.