RHODES STEEL BLDGS. v. Walker Const. Co.

813 So. 2d 1171, 2002 WL 496739
CourtLouisiana Court of Appeal
DecidedApril 3, 2002
Docket35,917-CA, 35,918-CA
StatusPublished
Cited by11 cases

This text of 813 So. 2d 1171 (RHODES STEEL BLDGS. v. Walker Const. Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RHODES STEEL BLDGS. v. Walker Const. Co., 813 So. 2d 1171, 2002 WL 496739 (La. Ct. App. 2002).

Opinion

813 So.2d 1171 (2002)

RHODES STEEL BUILDINGS, INC., Appellant,
v.
WALKER CONSTRUCTION COMPANY and Winn Parish School Board, Appellee.
Walker Construction Co., Inc., Appellee,
v.
Rhodes Steel Buildings, Inc., Appellant.

Nos. 35,917-CA, 35,918-CA.

Court of Appeal of Louisiana, Second Circuit.

April 3, 2002.

*1173 Donald E. Studer, West Monroe, Counsel for Appellant.

Klotz, Simmons & Brainard, By Kermit E. Simmons, Harry D. Simmons, Shreveport, Counsel for Appellee.

Before WILLIAMS, CARAWAY and KOSTELKA, JJ.

KOSTELKA, Judge.

In this Public Works Act action, Rhodes Steel Buildings, Inc. ("Rhodes") appeals *1174 two trial court judgments which sustained an exception of prematurity and thereby dismissed its suit to enforce a lien filed against Walker Construction Co. ("Walker"),[1] ordered cancellation of the lien and awarded attorney fees and damages to Walker. Finding error in these judgments, we reverse and remand for further proceedings.

FACTS

On February 1, 2000, Walker, as general contractor for the construction of additions and improvements to the Winnfield High School, entered into a subcontract with Rhodes to provide labor and materials for certain aspects of the project. On February 7, 2001, Rhodes filed a lien for the amount of $17,736.06, pursuant to La. R.S. 38:2242 of the Louisiana Public Works Act, claiming Walker had refused to pay sums due for work on the project. On March 23, 2001, Rhodes instituted a Petition to Enforce Mechanic's Privilege seeking the amounts claimed because of Walker's alleged breach of contract.

On April 5, 2001, Walker excepted to the suit on the grounds of prematurity, arguing that because it had terminated the contract due to Rhodes's alleged nonperformance, the job was not yet completed and a determination of what, if any, amounts were owed could not be made. On these same grounds, Walker filed a separate Petition For Summary Process on May 22, 2001, seeking to cancel the lien and for damages and attorney fees due to Rhodes's refusal to comply with Walker's written demand to cancel the lien in accordance with La. R.S. 38:2242.1.

On August 6, 2001, a hearing on a rule to show cause why the lien should not be cancelled and penalties and attorney fees awarded in Walker's summary process action was conducted simultaneously with a hearing on the prematurity exception.[2]

At the hearing, the trial court heard testimony from Benjamin Rhodes, Sr. ("Mr. Rhodes"), a principle of Rhodes. Mr. Rhodes testified that he, as the representative of Rhodes, and David Walker ("Mr. Walker"), as President of Walker, entered into a contract for Rhodes to perform work on the Winn Parish School Board project. The agreement provided that Rhodes was to submit monthly invoices to Walker for labor and materials by the 25th of the month. Mr. Rhodes stated that his work was delayed because work to be performed by others was not completed timely.

Mr. Rhodes testified that Mr. Walker first thought Rhodes was responsible for the installation of purlins on the project. However, when Mr. Walker realized that purlin installation was not included in Rhodes's contract, he asked Mr. Rhodes for assistance with the task. When Mr. Rhodes indicated it would be expensive for Rhodes to do that work, Mr. Walker agreed to hire Rhodes's employees on a cash basis solely for the installation of purlins at the site. Mr. Rhodes also indicated that Mr. Walker agreed to compensate Rhodes for truck usage on the purlin installation which occurred on July 28 and 29, 2000. Thereafter, on July 31, 2000, Rhodes invoiced Walker for truck usage in the amount of $912.50. Mr. Rhodes indicated his employees had trouble getting paid by Walker for the purlin *1175 installation. He spoke with Mr. Walker who indicated he would not pay the men because they did not do a good job. Mr. Rhodes testified that he paid the men but did not invoice Walker for that amount.

Mr. Rhodes also claimed Mr. Walker agreed to pay Rhodes overtime and truck usage for work done to further the contract on the weekend of July 22 and 23, 2000. Thereafter, on August 2, 2000, Rhodes invoiced Walker for overtime costs and truck usage in the amount of $1,131.24.

Mr. Rhodes also testified that because taxes were not included in the material costs of the contract, Mr. Walker verbally agreed to pay those amounts to Rhodes. Rhodes invoiced Walker for $4,118.48, representing the taxes due.

At the hearing, Rhodes sought to introduce these three invoices into evidence. Upon objection by Walker, however, the court declined to allow admission of the documents into evidence on the grounds they were outside the scope of the original written contract between Rhodes and Walker and that Rhodes failed to establish a proper business records foundation.

Mr. Rhodes also claimed Mr. Walker had not paid him $11,573.84 for labor performed in the month of July under the contract which was invoiced on July 24, 2000, but not paid. The court allowed the introduction of this exhibit into evidence.

Mr. Rhodes testified that he did not complete the project because Walker refused to pay his invoices. Mr. Rhodes claimed he called Mr. Walker regarding the unpaid invoices in the final week of August, 2000. In that conversation, Mr. Walker informed Mr. Rhodes he was not going to pay the invoices. Mr. Rhodes remembered getting a letter from Mr. Walker dated September 5, 2000, canceling the contract. This letter was received by Mr. Rhodes approximately ten days after the telephone conversation in which Mr. Walker told Mr. Rhodes he would not pay him. Mr. Rhodes testified it was Walker's refusal to pay which caused Rhodes to file the lien and suit to enforce it in the amount of $17,736.06—the total amount represented by Rhodes's invoices.

Mr. Rhodes also stated that after the installation of the bar joists, he checked the elevations which were not level. He believed the weld plates upon which the bar joists were placed were "up and down" which caused the purlins to be uneven as well. Rhodes did not install the weld plates. Mr. Rhodes pointed out the unevenness of the weld plates to Walker or the job superintendent. Mr. Rhodes felt nothing was done to correct the elevation problem prior to the purlin installation. He suggested that Mr. Walker held him responsible, although not in writing, for the unevenness of the purlins. Mr. Rhodes informed Mr. Walker that the men were Walker's employees during the installation of the purlins.

Mr. Walker also testified at the hearing. He stated he never agreed to pay taxes under the contract nor did he agree to pay additional overtime or truck usage to Rhodes. Mr. Walker claimed it was he who cancelled Rhodes's contract due to Rhodes's nonperformance. He first cancelled the contract verbally and then sent a letter to Rhodes on September 5, 2000 in which he canceled the contract for nonperformance and refusal to correct defective work in a timely manner and invoked Article 10[3] of the contract regarding the unpaid *1176 balances claimed by Rhodes. Mr. Walker testified that Rhodes had incorrectly installed bar joists and when requested to correct the installation, failed to do so because the Rhodes employees did not know what they were doing. Walker was forced to employ an independent contractor to complete the job, to buy materials and use some of Walker's employees to assist in completion of the project. Mr. Walker claimed he never told Mr. Rhodes he would not pay him for the job. At the time of Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eric A. Lannon v. Pherian, LLC
Louisiana Court of Appeal, 2025
Driver Pipeline Co. v. Cadeville Gas Storage, LLC
150 So. 3d 492 (Louisiana Court of Appeal, 2014)
Monroe v. Physicians Behavioral Hospital, LLC
147 So. 3d 787 (Louisiana Court of Appeal, 2014)
Grosjean v. Grosjean
50 So. 3d 233 (Louisiana Court of Appeal, 2010)
Red River Parish Port Commission v. Headwaters Resources Inc.
698 F. Supp. 2d 684 (W.D. Louisiana, 2010)
Lantech Construction Co. v. Speed
15 So. 3d 289 (Louisiana Court of Appeal, 2009)
Aqua Pool Ren. v. Paradise Manor Comm. Club
880 So. 2d 875 (Louisiana Court of Appeal, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
813 So. 2d 1171, 2002 WL 496739, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rhodes-steel-bldgs-v-walker-const-co-lactapp-2002.