CEC Controls Company, INC. v. H&H Electric, INC.

CourtDistrict Court, E.D. Arkansas
DecidedSeptember 28, 2022
Docket4:21-cv-00125
StatusUnknown

This text of CEC Controls Company, INC. v. H&H Electric, INC. (CEC Controls Company, INC. v. H&H Electric, INC.) is published on Counsel Stack Legal Research, covering District Court, E.D. Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CEC Controls Company, INC. v. H&H Electric, INC., (E.D. Ark. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT EASTERN DISTRICT OF ARKANSAS CENTRAL DIVISION

CEC CONTROLS COMPANY, INC. PLAINTIFF

v. Case No. 4:21-CV-00125-LPR

H & H ELECTRIC, INC., and AUTO-OWNERS INSURANCE COMPANY DEFENDANTS

and

UNITED STATES for the Use of THIRD-PARTY PLAINTIFF H & H ELECTRIC, INC.

v.

HUFFMAN CONSTRUCTION, LLC, and FIDELITY AND DEPOSIT COMPANY OF MARYLAND/ZURICH AMERICAN INSURANCE COMPANY THIRD-PARTY DEFENDANTS

ORDER This case arises from the termination of a public-works contract concerning the construction of a pumping station. The contract was between the United States Army Corps of Engineers and its principal (or general) contractor for the project—Huffman Construction, LLC. As one might expect, the termination of this contract resulted in a bunch of downstream contract terminations. A number of these downstream contract terminations are at issue in the case at bar. Presently pending before the Court is a fairly limited Motion for Partial Summary Judgment from H & H Electric, Inc.1 After being sued by its subcontractor, H & H filed a Third- Party Complaint against Huffman and Huffman’s surety, Zurich American Insurance Company.2 The Third-Party Complaint sets out claims against both entities for breach of contract and a

1 H & H’s Mot. for Summ. J. (Doc. 43). 2 The party’s full name is Fidelity and Deposit Company of Maryland/Zurich American Insurance Company, but, for ease of reading, the Court will refer to it as Zurich. violation of the Miller Act. However, H & H is only asking for summary judgment on its breach- of-contract claims. Further, H & H is only asking for summary judgment as to the existence and scope of liability, not the calculation of damages. For the reasons explained below, H & H’s Motion for Partial Summary Judgment is GRANTED in part and DENIED in part. H & H is entitled to summary judgment against Huffman

on the breach-of-contract claim. However, its breach-of-contract claim against Zurich is a non- starter. In the circumstances of this case, if Zurich has any liability to H & H, that liability would be exclusively under the Miller Act. BACKGROUND We are at the summary-judgment stage. This Background Section thus relies heavily on undisputed facts. Where there are genuine disputes of fact, the Court adopts the most pro- defendant version of such facts that a rational juror could accept.3 Accordingly, the facts set forth in this Background Section are good for purposes of this Partial Summary Judgment Motion only. I. The Contractual Relationships at Issue in this Case The Army Corps of Engineers hired Huffman, a Missouri corporation,4 to be the general

construction contractor for the Grand Prairie Pump Station Project (“the Project”) in DeValls Bluff, Arkansas.5 The Army Corps of Engineers, the owner of the Project, solicited Huffman for construction of “the GPPS Superstructure (Base) and Installation of the final section of Discharge Pipes from pipeline station 13+50 to station 22+00.”6

3 The Defendants are the nonmovants here. 4 H & H’s Compl. (Doc. 24) ¶ 2; Huffman’s Answer to H & H’s Compl. (Doc. 29) ¶ 2. 5 Ex. 1 (The General Contractor Agreement) to H & H’s Mot. for Summ. J. (Doc. 43-1). 6 Id. at 1. The General Contractor Agreement between Huffman and the Army Corps of Engineers recognized that the Corps could terminate that agreement for cause: If the contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in this contract including any extension, or fails to complete work within this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work (or the separable part of the work) that has been delayed.7

The General Contractor Agreement further provided that, in the case of termination, Huffman must immediately “[t]erminate all subcontracts to the extent they relate to the work terminated.”8 Among other things, that agreement required Huffman to obtain a payment bond.9 This requirement is statutorily mandated by the Miller Act, which provides: Before any contract of more than $100,000 is awarded for the construction . . . of any . . . public work of the Federal Government, a person must furnish to the Government . . . [a] payment bond with a surety satisfactory to the officer for the protection of all persons supplying labor and material in carrying out the work provided for in the contract for the use of each person.10

The Supreme Court has explained the purpose of such a payment bond: Ordinarily, a supplier of labor or materials on a private construction project can secure a mechanic’s lien against the improved property under state law. But a lien cannot attach to Government property, so suppliers on Government projects are deprived of their usual security interest. The Miller Act was intended to provide an alternative remedy to protect the rights of these suppliers.11

On September 15, 2014, Zurich issued a payment bond to the United States with Huffman as Principal for $25,414,000.12 (For purposes of this case, Zurich is what we call a “Miller Act surety.”) The Payment Bond reads as follows:

7 Id. at 192–93. 8 Id. at 190. 9 Id. at 1, 22. 10 40 U.S.C. § 3131(b). 11 F.D. Rich Co., Inc. v. United States ex rel. Indus. Lumber Co., Inc., 417 U.S. 116, 122 (1974) (citation omitted). 12 Ex. 2 (Zurich Bonds) to H & H’s Compl. (Doc. 24) at 27–28. We, the Principal and Surety(ies), are firmly bound to the United States of America . . . in the above penal sum [$25,414,000]. For payment of the penal sum, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally. . . . The above obligation is void if the Principal promptly makes payment to all persons having a direct relationship with the Principal or a subcontractor of the Principal for furnishing labor, material or both in the prosecution of the work provided for in [the General Contractor Agreement], and any authorized modifications of the contract that subsequently are made.13

On November 20, 2014, Huffman subcontracted with H & H.14 Under the agreement, H & H would provide certain electrical work on the Project, and Huffman would pay $3,387,961 for this work.15 There are two portions of this Huffman-H & H Agreement that feature heavily in the parties’ arguments on the instant Motion. The Court lays these two portions out in full. The first portion of the Huffman-H & H Agreement is made up of Sections 8.2 (Progress Payments) and 8.3 (Final Payment): 8.2 PROGRESS PAYMENTS[.]

8.2.1 APPLICATIONS[.] The Subcontractor's applications for payment shall be itemized and supported by substantiating data as required by the Subcontract Documents. If the Subcontractor is obligated to provide design services pursuant to Paragraph 3.8, Subcontractor's applications for payment shall show the Designer's fee and expenses as a separate cost item. The Subcontractor's application shall be notarized if required and if allowed under the Subcontract Documents may include properly authorized Subcontract Construction Change Directives. The Subcontractor's progress payment application for the Subcontract Work performed in the preceding payment period shall be submitted for approval of the Contractor in accordance with the schedule of values if required and Subparagraphs 8.2.2, 8.2.3, and 8.2.4. The Contractor shall incorporate the approved amount of the Subcontractor's progress payment application into the Contractor's payment application to the Owner for the same period and submit it to the Owner in a timely fashion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cal's A/C & Elec v. Famous Const Corp
220 F.3d 326 (Fifth Circuit, 2000)
Torgerson v. City of Rochester
643 F.3d 1031 (Eighth Circuit, 2011)
Cajun Constructors v. Fleming Const. Co.
951 So. 2d 208 (Louisiana Court of Appeal, 2006)
Bernard Lumber Co. v. Lanier-Gervais Corp.
560 So. 2d 465 (Louisiana Court of Appeal, 1990)
United States Ex Rel. Metric Electric, Inc. v. EnviroServe, Inc.
301 F. Supp. 2d 56 (D. Massachusetts, 2003)
Joan Roe v. St. Louis University
746 F.3d 874 (Eighth Circuit, 2014)
Lisa Pedersen v. Bio-Medical Applications
775 F.3d 1049 (Eighth Circuit, 2015)
State Ex Rel. Fletcher v. Blair
178 S.W.2d 322 (Supreme Court of Missouri, 1944)
American Creosote Works, Inc. v. Caltoman Contractors, Inc.
160 So. 2d 310 (Louisiana Court of Appeal, 1964)
Kieffer v. Icaza
376 S.W.3d 653 (Supreme Court of Missouri, 2012)
Chochorowski v. Home Depot U.S.A.
404 S.W.3d 220 (Supreme Court of Missouri, 2013)
Chapman v. Kansas City, Clinton & Springfield Railway Co.
48 S.W. 646 (Supreme Court of Missouri, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
CEC Controls Company, INC. v. H&H Electric, INC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cec-controls-company-inc-v-hh-electric-inc-ared-2022.