Guinn Bros., LLC v. Jones Brothers, Inc. of Tennessee

287 F. App'x 298
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 10, 2008
Docket07-30931
StatusUnpublished
Cited by1 cases

This text of 287 F. App'x 298 (Guinn Bros., LLC v. Jones Brothers, Inc. of Tennessee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guinn Bros., LLC v. Jones Brothers, Inc. of Tennessee, 287 F. App'x 298 (5th Cir. 2008).

Opinion

PER CURIAM: *

Plaintiff-Appellant Guinn Brothers, LLC (“Guinn”) appeals the district court’s grant of summary judgment to Defendant-Appellant Jones Brothers, Inc. (“Jones”) on its claim for damages arising from Jones’s alleged breach of contract. For the reasons discussed below, we affirm in part and reverse in part the district court’s grant of summary judgment.

I.

On March 23, 2000, Jones was awarded a contract with the Louisiana Department of Transportation (“DOTD”) for road and bridge construction on Louisiana Highway 171. Jones and Guinn entered a subcontract agreement under which Guinn would remove and construct four bridges for a price of $1,747,883.81. This subcontract incorporated by reference all of the terms and conditions of the DOTD contract, as well as all of the plans, specifications, and schedules between Jones and the DOTD. The subcontract also contained a mandatory notice provision pertaining to claims for additional compensation:

[Guinn] agrees to give notice in writing and make all claims for which [DOTD] is, or may be, liable in the manner provided and in a time framework which is consistent with the Principal Contract so that [Jones] may timely give notice of such claim to [DOTD]. Provided that the preceding sentence does not require earlier action, written notice of such claims shall be given by [Guinn] to [Jones] within one (1) week prior to the beginning of the Work or the event or *300 condition for which such claim is to be made, or immediately upon [Guinn’s] first knowledge of the event or condition, whichever shall first occur. Otherwise, such claims shall be deemed waived. [Guinn] shall give written notice of all claims for which [Jones] is, or may be liable, within five (5) days of the beginning of the event for which claim is made; otherwise, such claims shall be deemed waived. This notice period takes precedence over any other notice provisions provided by, or in, this Subcontract.

The contract between Jones and DOTD contained a similar mandatory notice provision. However, it also contained a requirement that notification of all claims must conform to the requirements of EDSM III.1.1.28, which sets forth specific information and documents which must be submitted in support of a claim.

From the project’s inception, there were significant delays and Guinn’s work was stopped for a number of periods of time. It is these periods of delay, discussed more fully below, which primarily form the basis of this lawsuit.

Eventually, in early 2004, a dispute arose between Jones and the DOTD that caused Jones to demobilize its equipment and discontinue all work on the project. On May 27, 2004, counsel for Jones sent correspondence to Guinn advising Guinn to cease all work on the project and also informing Guinn of settlement negotiations between Jones and DOTD. In response, Guinn indicated that it had “incurred significant down time with this project” and would be “examin[ing] their options closely as to how they should best address the down time issue.” As part of the settlement negotiations, DOTD permitted Jones to rebid the remaining portion, and Guinn submitted a revised bid to Jones on October 11, 2004. Guinn indicated that this revised bid did not include the delay and down time claim because Guinn did not yet have all the information and would submit the claim when it was complete.

Ultimately, in February 2005, under a settlement agreement between Jones and DOTD (Plan Change No. 50) Jones’s involvement in the project was terminated. As part of the settlement agreement, Jones agreed to indemnify the DOTD for all claims arising out of the bridge construction project.

Based on the delays and eventual termination of the contract, Guinn filed suit against Jones in August 2005. Guinn’s complaint contains six numbered causes of action, each describing a separate incident in which Jones allegedly breached the subcontract, causing Guinn to suffer delay damages. In its sixth cause of action, Guinn also sought lost profits and lost material resulting from Jones’s failure to allow Guinn to complete the job. After extensive discovery, Jones moved for summary judgment. On September 27, 2007, 2007 WL 2874598, the district court granted summary judgment to Jones on all of Guinn’s claims. Guinn timely appealed. II.

This Court reviews a district court’s grant of summary judgment de novo, applying the same standards as the district court. Strong v. Univ. Healthcare Sys., L.L.C., 482 F.3d 802, 805 (5th Cir.2007). “Summary judgment is proper when there exists no genuine issue of material fact and the movant is entitled to judgment as matter of law.” Id. (citing Fed.R.Civ.P. 56(c)). “The evidence and inferences from the summary judgment record are viewed in the light most favorable to the nonmovant.” Minter v. Great Am. Ins. Co. of N.Y., 423 F.3d 460, 465 (5th Cir.2005).

The moving party “bears the initial responsibility of informing the district court *301 of the basis for its motion, and identifying those portions of [the record] ... which it believes demonstrate the absence of a genuine issue of material fact.” Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). Once the movant meets this burden, the burden shifts to the nonmovant “to make a showing sufficient to establish the existence of an element essential to that party’s case, and on which that party will bear the burden of proof at trial.” Id. at 322, 106 S.Ct. 2548. To survive a summary judgment motion, the nonmovant “need only present evidence from which a jury might return a verdict in his favor,” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 257, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986), but mere allegations or denials will not defeat a well-supported motion for summary judgment. Fed.R.Civ.P. 56(e)

III.

On appeal, Guinn first argues that the district court erred in granting summary judgment on its claims for lost profits and lost materials because Jones did not move for summary judgment on these claims. Generally, “a district court may not grant summary judgment sua sponte on grounds not requested by the moving party.” Baker v. Metro. Life Ins. Co., 364 F.3d 624, 632 (5th Cir.2004) (quoting John Deere Co. v. Am. Nat’l Bank, 809 F.2d 1190, 1192 (5th Cir.1987)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
287 F. App'x 298, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guinn-bros-llc-v-jones-brothers-inc-of-tennessee-ca5-2008.