Professional Const. Services, Inc. v. Lee M. Marcello Contractor, Inc.

550 So. 2d 968, 1989 La. App. LEXIS 1804, 1989 WL 124629
CourtLouisiana Court of Appeal
DecidedOctober 12, 1989
Docket89-CA-202
StatusPublished
Cited by8 cases

This text of 550 So. 2d 968 (Professional Const. Services, Inc. v. Lee M. Marcello Contractor, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Professional Const. Services, Inc. v. Lee M. Marcello Contractor, Inc., 550 So. 2d 968, 1989 La. App. LEXIS 1804, 1989 WL 124629 (La. Ct. App. 1989).

Opinion

550 So.2d 968 (1989)

PROFESSIONAL CONSTRUCTION SERVICES, INC.
v.
LEE M. MARCELLO CONTRACTOR, INC.

No. 89-CA-202.

Court of Appeal of Louisiana, Fifth Circuit.

October 12, 1989.
Writ Denied January 5, 1990.

*969 Lawrence A. Mann, Donald E. McKay, Jr., Leake & Anderson, New Orleans, for plaintiff/appellant.

Michael I. Rodriguez, New Orleans, for defendant/appellee.

Before KLIEBERT, BOWES and GOTHARD, JJ.

GOTHARD, Judge.

Plaintiff, Professional Construction Services, Inc. (PCS), instituted this suit against defendant, Lee M. Marcello Contractor, Inc. (Marcello) for the alleged breach of a subcontract for concrete work at the E.I. Dupont de Nemours drum storage plant in La Place. PCS claimed damages totalling $42,236.63 for costs incurred in completion of the job and payment of Marcello's debts to materialmen. Marcello answered and filed a reconventional demand alleging PCS breached the contract by failing to pay progress payments and by firing Marcello unjustly.

After hearing the merits the trial court found in favor of Marcello in the amount of $11,219.36. In the reasons for judgment the trial court found 60% of the work had been completed in a proper and timely manner with no breach of contract. The trial court calculated the award due Marcello in the following manner:

60% of contract price of   $58,260.00     $34,956.00
Less:
Advance March 5, 1987                     $ 4,000.00
Bills paid by Professional
Construction:
  H. Construction Co., Inc.               $ 7,000.00
  Building Specialties Co.                $ 6,000.00
  Mid-South Steel                         $ 1,338.75
  National Polyfab Corp.                  $ 5,397.89
                                          __________
Judgment for Marcello
Contractor, Inc.                          $11,219.36

PCS has appealed from this judgment taking the position that the evidence does not support the findings and the trial court's calculation of damages is manifestly erroneous as a matter of law and fact. We affirm.

The evidence reveals that PCS contracted to act as general contractor for construction of a drum storage plant in La Place for E.I. Dupont de nemours. On February 12, 1987 Marcello entered into a written subcontract agreement with PCS to perform all of the concrete work on the plant, including the building foundation, parking lot and three small catch basins. The subcontract agreement provides in pertinent part as follows:

*970 Time is of essence in this contract and we are to meet the schedule set up by Dupont for the completion of this work. This subcontractor will work whatever time is necessary to accomplish this, furnishing whatever labor and/or materials necessary to accomplish the schedule.

All of the terms and conditions of the Dupont inquiry are included in this subcontract as if written therein.

(3) Subcontract Price:
    Original quoted price:               $58,586.00
    Revision due to the reduction in
    the size of the building:               (450.00)
    Addition for hand excavation:         +  124.00
                                         __________
      Total amount due this
      subcontract                        $58,260.00

The contract contains no provisions for progress payments.

As work on the project progressed, Marcello was unable to meet payroll obligations. He testified that payments due, but unreceived, from two other unrelated jobs precipitated his financial difficulties. Marcello requested and received a $4,000.00 advance on the contract from PCS.

At trial Lee Marcello testified that two PCS representatives, Freddie Yoder and Leonard Hebert, promised to pay a progress payment upon completion of the first concrete pour, that pour occurred on March 16, 1987 and a bill was submitted to PCS the next day.

A meeting was set up between the parties for March 18, 1987. At that meeting PCS advised Marcello that he was in default of his contract for substandard and untimely work. No further payments were made to Marcello. Marcello admitted at trial that without the anticipated progress payment he could not complete the contract since he was behind two payrolls at that point and could not continue without sufficient funding. However, he denied that his work was inferior or untimely.

What actually was agreed upon at the March 18, 1987 meeting between Lee Marcello and Wallace Guillot representing Marcello, and Freddie Yoder, Leonard Hebert and Blaze Gagliano representing PCS is in dispute. PCS informed Marcello of its understanding of the agreement by way of a registered letter written on March 19, 1987. The body of that letter, made part of the record, reads as follows:

Dear Mr. Marcello:
This letter will confirm the meeting in our conference room on Wednesday, March 18, 1987 in connection with your subcontract with us on the subject project.
We discussed the progress of the work, the quality of the work, and the non-payment of Lee Marcello Contractor to his personnel.
It was decided at the conclusion of the meeting that it would be to everyone's benefit for Professional Construction Services, Inc. to place Lee Marcello in default of his subcontract and take over his work.
We propose to use the material and any equipment that you may have on the jobsite to complete this work, to charge all costs of completing the work to the account of Lee M. Marcello Contractor, and at the conclusion of the job, to have an accounting and to either pay you the difference between your subcontract price and what we have spent or to send you an invoice if there is an overage.
You agreed to this method of procedure and you are to assist us in all possible ways to complete the work on schedule and to lend any assistance that you could to help us.
We pointed out to you that there are several of your workers who have complained to our superintendent, and they have also called our office, that they have not been paid. You agreed to arrange for their payment and you are to see that there are no labor liens placed on the job by these workers.
You are responsible for all invoices that you have incurred to date on the job and will see that there (sic) are properly discharged.

At trial Freddie Yoder and Leonard Hebert verified that agreement. Mr. Yoder testified that Marcello seemed relieved to allow PCS to take over the job. Both Yoder and Leonard agreed that the letter accurately represented the agreement between the parties formulated at the March 18th meeting.

*971 Lee Marcello admitted that he was advised that he was being placed in default at the meeting but asserts that he was not in agreement with the proposal made in the letter. However, there is no indication that Marcello objected to the letter at the time it was received.

Guillot testified that Marcello agreed to PCS taking over the job when it was certain that no progress payments would be made. Both Marcello and Guillot denied that they agreed to be responsible for payment due to others for the completion of the work.

Although there is testimony to the fact that Marcello was behind schedule in his work at the time he was placed in default, we cannot say that the trial court erred in finding that there was no breach of contract by Marcello for untimely execution. The subcontract states that time is of the essence and ties the time schedule to Dupont.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stipp v. MetLife Auto & Home Insurance Agency, Inc.
225 So. 3d 1182 (Louisiana Court of Appeal, 2017)
Aqua Pool Ren. v. Paradise Manor Comm. Club
880 So. 2d 875 (Louisiana Court of Appeal, 2004)
L & a CONTRACTING v. Ram Indus. Coatings, Inc.
762 So. 2d 1223 (Louisiana Court of Appeal, 2000)
Robinson v. Thornton
705 So. 2d 745 (Louisiana Court of Appeal, 1997)
Fridge v. Sampognaro
700 So. 2d 1090 (Louisiana Court of Appeal, 1997)
BIG" D" DIRT SERVICES INC. v. Westwood, Inc.
653 So. 2d 604 (Louisiana Court of Appeal, 1995)
RIVER OAKS v. Blue Cross of Louisiana
595 So. 2d 785 (Louisiana Court of Appeal, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
550 So. 2d 968, 1989 La. App. LEXIS 1804, 1989 WL 124629, Counsel Stack Legal Research, https://law.counselstack.com/opinion/professional-const-services-inc-v-lee-m-marcello-contractor-inc-lactapp-1989.