In Re Worldcom, Inc.

382 B.R. 610, 2008 WL 427986, 2008 Bankr. LEXIS 1137
CourtUnited States Bankruptcy Court, S.D. New York
DecidedFebruary 21, 2008
Docket19-35123
StatusPublished
Cited by6 cases

This text of 382 B.R. 610 (In Re Worldcom, Inc.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Worldcom, Inc., 382 B.R. 610, 2008 WL 427986, 2008 Bankr. LEXIS 1137 (N.Y. 2008).

Opinion

OPINION REGARDING CLAIM NUMBER 3059 INCLUDING WALDINGER CORP.’S MOTION FOR RECONSIDERATION

ARTHUR J. GONZALEZ, Bankruptcy Judge.

I. INTRODUCTION

Waldinger Corporation (“Waldinger”) asserts a secured claim against WorldCom, *614 Inc. (the “Debtors” or “WorldCom”) for $371,362 plus interest and attorneys’ fees, secured by a construction lien under Nebraska law. The Debtors dispute that the claim is secured and additionally dispute the basis of the claim.

After considering multiple hearings and pleadings, the Court issued an opinion on February 23, 2007 (the “February Opinion”) granting the Debtors’ motion for partial summary judgment to classify Wal-dinger’s claim as unsecured because of the finding that the Lien lapsed as matter of law on May 20, 2004. Waldinger requests the Court to reconsider that partial summary judgment and to allow its claim as secured.

Waldinger asserts it is further entitled to the Nebraska statutory interest rate for a mechanic’s lien of 12% per annum pursuant to Nebraska statutes §§ 45-103.02(2) and 45-104, and the recovery of all fees and expenses, including attorney’s fees (collectively, “Attorney’s Fees”) pursuant to section 506 of chapter 11 of title 11 of the United States Code (the “Bankruptcy Code”). The Debtors argue that Waldinger is not entitled to interest or Attorney’s Fees for various reasons.

The Court held a trial on this matter on December 13, 2007. For the reasons that follow, the Court has reconsidered its earlier judgment in the February Opinion that Waldinger’s lien lapsed as matter of law but concludes that Waldinger is not entitled to a secured claim for other reasons. The Court finds that Waldinger is entitled to recovery under quantum meru-it, but the Court must hold a further hearing to determine the reasonable value of the services Waldinger provided to the Debtors.

II. JURISDICTION

The Court has subject matter jurisdiction over this proceeding pursuant to sections 1334 and 157(b) of title 28 of the United States Code, the July 10, 1984 “Standing Order of Referral of Cases to Bankruptcy Judges” of the United States District Court for the Southern District of New York (Ward, Acting C.J.), and paragraph 32 of the Court’s Order Confirming Debtors’ Modified Second Amended Joint Plan of Reorganization under chapter 11 of title 11 of the United States Code. This matter is a core proceeding pursuant to section 157(b)(2)(B) of title 28 of the United States Code. Venue is proper before the Court pursuant to sections 1408 and 1409 of title 28 of the United States Code.

III. BACKGROUND

A. Factual and Procedural Background 1

Waldinger is engaged in the construction business in Omaha, Nebraska and the surrounding region. WorldCom owns a building in Omaha named the Mid-Continent Data Center at 7400 World Communications Drive, Omaha, Nebraska (the “Data Center”). Sometime in 2000, WorldCom executives informed the Data Center’s building manager, Raymond Brock (“Brock”), that they wanted to have additional air handling units installed to meet their forecasted additional need. (Trial Ex. 37, Brock Depo. 21:11-21:20.) Air handing units are large machines essential to cool and ventilate the rooms in which multiple computer systems and data storage hardware are located. Brock stated that a colleague at WorldCom told him that Waldinger had done “some” to “all” of the mechanical work at the Data Center and thus should be contacted to install the air handing units. (Id. at 21:21-22:22.) Brock testified that he subsequently had *615 contact with Michael Smearman (“Smear-man”), a manager for Waldinger, regarding the Debtors’ need for additional air handling units. (Id. at 28:3-23:6.) In mid to late-2000, WorldCom requested a proposal and quote from Waldinger regarding air handling units for the Data Center. On September 15, 2000, Waldinger submitted a proposal to the Data Center (Trial Ex. 1.) The proposal provided a quote of $1,098,000 in labor and materials for the purchase and installation of three new air handling units numbers 6, 7, and 43 (the “AHU’s”), at the Data Center, and contained proposed work for existing air handling unit number 5. The proposal by Wal-dinger included $576,332 for the cost of the three AHU’s. (Trial Ex. 4.) On November 14, 2000, WorldCom Purchasing, LLC issued a written purchase order to Waldinger for the purchase of the three AHU’s referenced in the proposal at the price of $576,000. (Trial Ex. 2.) Installation was not referenced in that purchase order.

Waldinger’s employees were at the Data Center performing work on other air handing units, numbers 5 and 24, in the fall and winter of 2000. The Data Center is a secure facility and Waldinger’s employees needed authorization to access the facility. Waldinger testified that from March through July 2001, Waldinger’s employees performed work to prepare the Data Center for the delivery and installation of the AHU’s, for example, building raised concrete “housekeeping pads” where the AHU’s were to be placed, and installing ductwork, piping, and sheet metal. WorldCom’s building manager at the Data Center, Brock, stated in a deposition that there was some “prep work” that needed to be done for the three AHU’s to be put in place, including putting up some ductwork and installing the housekeeping pads. (Trial Ex 37, 47:19-47:48.) A Wal-dinger job foreman, George Russell (“Russell”), testified that he observed Waldinger employees working to prepare the sheet metal ducts at the Data Center prior to the installation and delivery of the three AHU’s. (Russell Depo., Trial Ex. 34, 43:8-44:7, 49:6-49:11). Brock affirmed that Waldinger moved lights to make ductwork fit. (Trial Ex. 37, 52:21-52:23.) Brock acknowledges that Waldinger did some sheet metal work, but disputes whether they were directed to do so. (Trial Ex. 37, 49:9^1918.) Brock stated that he did not tell any employee of Waldinger that they were authorized to install the AHU’s. (Trial Ex. 37, 49:9-49:18; 64:5-64:9.)

Russell testified that Brock authorized work on another air handling unit, number 5 (Trial Ex. 34, 8:14-8:23, 10:12-10:20.) Brock admits that he instructed Russell or Smearman to get the work done on number five, as instructed by the Debtors’ governance people. (Trial Ex. 37, 47:19-48:4.)

The three AHU’s were delivered to the Data Center in July 2001. Waldinger contends that it rented a crane and forklifts to offload and move the AHU’s to the concrete pads and that its employees performed that work. At trial, Waldinger showed that it paid a sub-contractor in full for cost of the AHU’s. (Trial Ex. 21.) Some time after the AHU’s were in place on the concrete pads, Brock instructed Waldinger to stop all further work. Brock testified that it was after the AHU’s had been delivered and placed on the concrete pads, that a more senior WorldCom employee, Arnold Espinosa (“Espinosa”), 2 *616 told him to instruct Waldinger to stop work. (Trial Ex.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
382 B.R. 610, 2008 WL 427986, 2008 Bankr. LEXIS 1137, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-worldcom-inc-nysb-2008.