Reeves v. Watkins

305 N.W.2d 815, 208 Neb. 804, 1981 Neb. LEXIS 860
CourtNebraska Supreme Court
DecidedMay 15, 1981
Docket43467
StatusPublished
Cited by8 cases

This text of 305 N.W.2d 815 (Reeves v. Watkins) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reeves v. Watkins, 305 N.W.2d 815, 208 Neb. 804, 1981 Neb. LEXIS 860 (Neb. 1981).

Opinion

Krivosha, C.J.

The appellant, Brian R. Watkins (Watkins), appeals from an order entered by the District Court for *805 Lancaster County, Nebraska, affirming a previous order entered by the municipal court of the city of Lincoln, Nebraska, sustaining a motion for summary judgment filed by the appellee, Richard E. Reeves (Reeves). We affirm.

The record discloses that Watkins, a partner in a joint venture known as Venture “78” Ltd., personally entered into a contract with Reeves for architectural services in connection with the design and construction of an office complex to be constructed and owned by Venture “78.” The contract, as disclosed by the evidence, is a standard AIA Document B141, Owner-Architect Agreement, and contains in Article 8 of the agreement a specific provision for liquidated damages. Article 8 of the agreement provides as follows:

“8.1 This Agreement may be terminated by either party upon seven days’ written notice should the other party fail substantially to perform in accordance with its terms through no fault of the party initiating the termination.
“8.2 In the event of termination due to the fault of parties other than the Architect, the Architect shall be paid his compensation for services performed to termination date, including Reimbursable Expenses then due and all termination expenses.
“8.3 Termination Expenses are defined as Reimbursable Expenses directly attributable to termination, plus an amount computed as a percentage of the total compensation earned to the time of termination, as follows: 20 percent if termination occurs during the Schematic Design Phase; or 10 percent if termination occurs during the Design Development Phase; or 5 percent if termination occurs during any subsequent phase.”

The evidence further discloses that sometime after the contract between Watkins and Reeves was entered into on July 22, 1978, and before the project was completed, a mortgage foreclosure involving the project property was filed by the United States *806 National Bank of Omaha against Venture “78” in the District Court for Lancaster County, Nebraska.

Thereafter, Reeves intervened and filed an answer and cross-petition in the mortgage foreclosure. In his cross-petition he alleged the execution of the contract between himself and Watkins and the existence of a valid mechanic’s lien which he sought to foreclose. Furthermore, Reeves alleged that he had “performed all of the duties imposed upon him under the terms of the contract evidenced by Exhibit ‘A.’” He further alleged, as he was required to do, that he had caused to be filed in the office of the Register of Deeds of Lancaster County, Nebraska, a mechanic’s lien which had attached to it a copy of the written agreement between Reeves and Watkins. Watkins answered the cross-petition by filing a general denial.

On May 18, 1979, the District Court for Lancaster County, Nebraska, entered a decree of foreclosure in favor of the United States National Bank as first lienholder. The court further found in its decree that Reeves claimed a lien but that a dispute existed as to the validity of the alleged lien. The court therefore determined that the dispute should be resolved, and if resolved in favor of Reeves, should constitute a third lien against the property, the second lien being in favor of First Savings Company of Lincoln.

The parties then entered into a trial stipulation in the foreclosure action in which Watkins acknowledged executing the agreement with Reeves, and further acknowledged that a mechanic’s lien with attachments, including the contract, was filed in the office of the Register of Deeds of Lancaster County, Nebraska. Watkins further stipulated that the joint venture had paid to Reeves, under the terms of the agreement, the sum of $33,674.88.

Trial was then had on the validity of Reeves’ mechanic’s lien, and on May 29, 1979, judgment was entered by the District Court for Lancaster County, Nebraska, in the foreclosure action in favor of Reeves *807 and against Watkins. In its judgment, the court specifically found that the mechanic’s lien filed by Reeves was a valid mechanic’s lien and should be foreclosed against the joint venture for the amount of $1,744.25. The parties acknowledge that the sum included in the mechanic’s lien foreclosure did not include any part of the liquidated damages now being sought.

Reeves thereafter filed a petition in the municipal court of the city of Lincoln seeking to recover the termination fee in the amount of 5 percent of $36,043.85 as provided for in Article 8.3 of the contract. By way of answer, Watkins admitted the execution of the contract but denied all of the other allegations of Reeves’ petition. Watkins further filed a counterclaim in which he acknowledged that Reeves had previously been paid $36,043.85 but maintained that Reeves had overcharged Watkins and had not given him credit for the overcharge. Furthermore, Watkins alleged that the termination was not due to any act of Watkins but solely due to the acts of Reeves. Watkins also alleged that Reeves had not performed all of the services required to be performed by him in a timely manner and that these delays caused construction cost increases in an amount which Watkins was unable at that time to determine. Watkins further alleged that Reeves failed to. perform all of the requirements of the contract, specifically failing to obtain approval of the project by the Lower South Platte Natural Resources District. The contract, however, makes no provision for the work to be done at a specific time, nor does it require the architect to obtain the approval of the Lower South Platte Natural Resources District.

Based in part upon the facts determined between the parties in the mechanic’s lien foreclosure and in part on Watkins’ admission that he had paid to Reeves the sum of $36,043.85, Reeves filed a motion for summary judgment in the municipal court. The municipal court granted the motion for summary judgment *808 and Watkins appealed to the District Court. After consideration of the matter, the District Court affirmed the judgment of the municipal court. It is from this order by the District Court for Lancaster County, Nebraska, that Watkins appeals, maintaining that the trial court erred in sustaining the motion for summary judgment.

Specifically, Watkins assigns as error the fact that the court could not and should not have found that Watkins was collaterally estopped from objecting to the validity of the contract by virtue of the decree of foreclosure which related only to “work actually performed” by Reeves and did not decide any issues regarding the validity of the contract and the rights of the parties as to termination charges. Watkins further maintains that the trial court erred in sustaining the motion for summary judgment as there were genuine issues of fact which could not be decided by a motion for summary judgment, though, in his assignment of error, he does not set out what those genuine issues of fact are.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Preston Refrigeration v. Omaha Cold Storage
742 N.W.2d 782 (Nebraska Court of Appeals, 2007)
Tilt-Up Concrete, Inc. v. Star City/Federal, Inc.
582 N.W.2d 604 (Nebraska Supreme Court, 1998)
Lange Industries, Inc. v. Hallam Grain Co.
507 N.W.2d 465 (Nebraska Supreme Court, 1993)
Gottsch v. Bank of Stapleton
458 N.W.2d 443 (Nebraska Supreme Court, 1990)
Smith v. Central Investment Co.
358 N.W.2d 772 (Nebraska Supreme Court, 1984)
Cedars Corp. v. Sun Valley Development Co.
330 N.W.2d 900 (Nebraska Supreme Court, 1983)
Sherwood v. Brown
306 N.W.2d 171 (Nebraska Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
305 N.W.2d 815, 208 Neb. 804, 1981 Neb. LEXIS 860, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reeves-v-watkins-neb-1981.