Preston Refrigeration v. Omaha Cold Storage

742 N.W.2d 782, 16 Neb. Ct. App. 228, 2007 Neb. App. LEXIS 208
CourtNebraska Court of Appeals
DecidedDecember 4, 2007
DocketA-07-472
StatusPublished
Cited by5 cases

This text of 742 N.W.2d 782 (Preston Refrigeration v. Omaha Cold Storage) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Preston Refrigeration v. Omaha Cold Storage, 742 N.W.2d 782, 16 Neb. Ct. App. 228, 2007 Neb. App. LEXIS 208 (Neb. Ct. App. 2007).

Opinion

742 N.W.2d 782 (2007)
16 Neb. App. 228

PRESTON REFRIGERATION CO., INC., Appellee,
v.
OMAHA COLD STORAGE TERMINALS, INC., Appellant.

No. A-07-472.

Court of Appeals of Nebraska.

December 4, 2007.

*784 Alan J. Mackiewicz, Omaha, for appellant.

Andrew M. DeMarea and Jay E. Heidrick, Overland Park, KS, of Shughart, Thomson & Kilroy, P.C., and Steven J. Reisdorff, Lincoln, for appellee.

SIEVERS, CARLSON, and CASSEL, Judges.

SIEVERS, Judge.

This appeal presents the question of whether a lawsuit which seeks foreclosure on a construction lien can also include a separate cause of action for additional damages for breach of contract. Pursuant to the authority granted this court under Neb. Ct. R. of Prac. 11B(1) (rev.2006), this case has been ordered submitted for decision without oral argument.

FACTUAL BACKGROUND

Given the narrow issues raised by the assignments of error, our factual recitation is limited. The appellee, Preston Refrigeration Co., Inc. (Preston), is a refrigeration contractor located in Kansas City, Kansas, and the appellant, Omaha Cold Storage Terminals, Inc. (Cold Storage), is a Nebraska corporation doing business in Omaha, Nebraska, and other states. Cold Storage owned real estate in rural Saline County, Nebraska, upon which it intended to construct a cold processing storage facility known as the Crete Project. In October *785 2001, Cold Storage arranged for Preston to produce an electrical design for the Crete Project at a cost of $30,000. In late November 2001, Preston agreed to perform work on eight screw compressors to be used at the Crete Project at a cost of $156,565 and a written contract for such work in such amount was entered into between Preston and Cold Storage. On January 20, 2002, Preston and Cold Storage entered into a contract whereby Preston would perform all work related to the design and construction of the cooling system at the Crete Project, which, as an adjunct, involved work at another facility in Fort Dodge, Iowa. The amount of the contract was $3,413,800. It appears that the majority of the work performed by Preston was actually performed at Preston's facility in Kansas City. In April 2002, Cold Storage indicated to Preston that the Crete Project would be delayed. Work by Preston on the Crete Project as well as a project in Fort Dodge was stopped for 6 weeks, and work on the Crete Project did not recommence in a substantial way. In January and February 2003, Preston performed some additional work under the general outlines of the contract, which work Preston described as necessary to maintain and preserve the materials being held by Preston at its home office and to protect them from natural deterioration. While Preston did not specifically invoice Cold Storage for this work, its charge therefor was $1,884.80.

Preston's last invoice to Cold Storage was dated August 15, 2002, in the amount of $321,948. On March 7, 2003, Preston filed a construction lien with the register of deeds of Saline County in that amount under Neb.Rev.Stat. § 52-147 (Reissue 2004). Thereafter, in October 2003, Cold Storage substituted collateral for the construction lien, in the form of a cashier's check in the amount of $370,300 deposited with the clerk of the district court for Saline County.

PROCEDURAL HISTORY

Although the transcript in this case contains over 400 pages, including several amendments to the complaint, discovery documents, pretrial filings, and court orders, extensive recitation of the procedural history is not necessary for several reasons. The primary reason is that the case ultimately came on for a bench trial before the district court upon Cold Storage's general denial without any affirmative defenses. The primary issue raised by Cold Storage was whether the lawsuit for foreclosure of a construction lien could also include a cause of action for additional damages for breach of contract. The trial court rejected Cold Storage's claim that the action was limited solely to the foreclosure of the lien. The matter was tried on June 26, 2006, and on December 27, a decision was rendered by the district court which gave judgment to Preston on its lien for $321,948, as well as $1,884.88 "for work performed under the contract but not invoiced to [Cold Storage] for maintenance of the compressors," for a total judgment of $323,832.88. Preston filed a timely motion for new trial and/or to alter or amend the judgment on the ground that the court had not dealt with the breach of contract damages which were claimed. The court entered its order on March 30, 2007, and amended its previous decision to add an additional $748,428 in damages for lost profits due to Cold Storage's breach of contract between the parties, for a total judgment of $1,072,260.88.

The second reason that we do not extensively discuss the procedural history, or the evidence for that matter, is the limited scope of the assignments of error advanced by Cold Storage.

ASSIGNMENTS OF ERROR

Cold Storage makes five separate assignments of error, but examination of its *786 brief reveals that such have been consolidated and argued as three claims, which are as follows: (1) The trial court did not have subject matter jurisdiction to try any common-law causes of action in this statutory action for foreclosure of a construction lien; (2) Preston did not satisfy its burden of proving that its claim was filed in time to create a lien; and (3) Preston never pled a claim for the labor charges of January and February 2003 in the amount of $1,884.88, and as a result, the trial court committed error in including such amount in its judgment.

STANDARD OF REVIEW

Statutory interpretation presents a question of law, in connection with which an appellate court has an obligation to reach an independent conclusion irrespective of the decision made by the court below. Gage Cty. Bd. v. Nebraska Tax Equal. & Rev. Comm., 260 Neb. 750, 619 N.W.2d 451 (2000). In a bench trial of a law action, the trial court's factual findings have the effect of a jury verdict and will not be disturbed on appeal unless clearly wrong. Par 3, Inc. v. Livingston, 268 Neb. 636, 686 N.W.2d 369 (2004).

ANALYSIS

May Action Brought to Foreclose Construction Lien Include Cause of Action for Other Damages Arising Out of Breach of Contract?

At the outset, we note that the amount sought in conjunction with the foreclosure of Preston's construction lien — $321,948 — is not disputed, except as to whether the construction lien was timely perfected. In short, Cold Storage does not contest that the amount sought was fair, reasonable, and necessary, or that the work was not performed. Likewise, Cold Storage does not dispute the amount of $748,428 awarded to Preston as lost profits for unperformed work by virtue of breach of contract by Cold Storage. Rather, Cold Storage's claim is that a breach of contract cause of action for lost profits cannot be brought in this lawsuit. That argument is premised upon Cummins Mgmt. v. Gilroy, 266 Neb. 635, 667 N.W.2d 538 (2003). In that case, to secure a note, John M. Gilroy and Cynthia H.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
742 N.W.2d 782, 16 Neb. Ct. App. 228, 2007 Neb. App. LEXIS 208, Counsel Stack Legal Research, https://law.counselstack.com/opinion/preston-refrigeration-v-omaha-cold-storage-nebctapp-2007.