Artisan Pools, Inc. v. Siemer

CourtNebraska Court of Appeals
DecidedMay 12, 2026
DocketA-25-246
StatusUnpublished

This text of Artisan Pools, Inc. v. Siemer (Artisan Pools, Inc. v. Siemer) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Artisan Pools, Inc. v. Siemer, (Neb. Ct. App. 2026).

Opinion

IN THE NEBRASKA COURT OF APPEALS

MEMORANDUM OPINION AND JUDGMENT ON APPEAL (Memorandum Web Opinion)

ARTISAN POOLS, INC. V. SIEMER

NOTICE: THIS OPINION IS NOT DESIGNATED FOR PERMANENT PUBLICATION AND MAY NOT BE CITED EXCEPT AS PROVIDED BY NEB. CT. R. APP. P. § 2-102(E).

ARTISAN POOLS, INC., A NEBRASKA CORPORATION, APPELLEE, V.

JOSHUA SIEMER AND JENA SIEMER, INDIVIDUALS, APPELLANTS.

Filed May 12, 2026. No. A-25-246.

Appeal from the District Court for Washington County: ZACHARY L. BLACKMAN, Judge. Affirmed. Rhys T. Hansen and David V. Drew, of Drew Law Firm, P.C., L.L.O., for appellant. Oluseyi O. Olowolafe, of Olowolafe Law Firm, L.L.C., for appellee.

RIEDMANN, Chief Judge, and BISHOP and FREEMAN, Judges. RIEDMANN, Chief Judge. I. INTRODUCTION Joshua Siemer and Jena Siemer appeal from the order of the district court for Washington County. The Siemers argue the court erred by finding that Artisan Pools, Inc. (hereinafter “Artisan”) did not act in bad faith when it filed or later refused to release its construction lien on their property. For the reasons stated herein, we affirm. II. BACKGROUND In May 2023, Artisan, a company that builds residential in-ground pools, and the Siemers executed a written contract for Artisan to build a pool on the Siemers’ property. The contract was later modified to provide that construction of the pool would be completed in stages and the Siemers would pay a percentage of the total contract price at the completion of each stage.

-1- The Siemers made the required payments until Artisan requested the final payment on July 31, 2023. The Siemers refused to disperse the final payment because they were dissatisfied with aspects of Artisan’s work. After some conversations regarding the Siemers’ grievances, communication between Artisan and the Siemers broke down. After a heated conversation between Artisan’s owner, K.C. Barth, and Joshua, Barth sent Joshua a text message on September 15, terminating the parties’ contract, and stating that Artisan intended to sue the Siemers and file a lien on their property the next week. Through counsel, the Siemers sent Artisan a letter later in September 2023, setting forth various issues they had with the pool, including that a required inspection by the city had not been completed. On December 1, Artisan called the city inspector, and the inspection of the pool was completed in early January 2024. On January 25, 2024, Artisan filed a construction lien on the Siemers’ property. In the lien application, Artisan stated that the Siemers had not made the final payment under the contract, and it identified December 1, 2023, as the last date on which it had provided materials or services. Artisan never sent a copy of the lien to the Siemers. On February 6, 2024, the Siemers’ attorney sent a letter to Artisan, demanding that it release the lien. This letter stated the lien was void because it overstated the amount due under the contract, it misidentified the last date services were performed, and the Siemers did not receive the legally required notice. However, Artisan did not release the lien. The Siemers’ attorney sent another letter on February 16, 2024, informing Artisan that the Siemers had “gone under contract” to sell their home and demanding again that Artisan release its lien because it was invalid for the same reasons listed in the February 6 letter. Artisan still did not release the lien. In March 2024, Artisan filed a complaint against the Siemers in the district court, seeking foreclosure on the construction lien and damages for breach of contract and unjust enrichment. The Siemers filed an answer denying Artisan’s allegations, asserting affirmative defenses, and setting forth a counterclaim for bad faith lien, slander of title, breach of contract, and unjust enrichment. Regarding the bad faith lien, the Siemers specifically asserted that Artisan filed and refused to release the lien on their property in bad faith because the lien was filed outside the requisite statutory timeframe, and they were not given proper notice of the lien; they accordingly requested the court award damages and attorney fees. A bench trial was held on two dates in November 2024. Barth testified at trial that he believed the lien was valid. He stated that he believed the lien was filed within the statutory timeframe because the phone call he made for the city inspection of the pool constituted services rendered under the contract. Thus, he believed December 1, 2023, was the date from which the statutory timeframe would be calculated. Barth also testified that he had “no reason to believe that the [Siemers] were not given notice” of the lien. He testified that although neither he nor anyone else at Artisan had sent notice to the Siemers, the county register of deeds had provided the Siemers with “constructive” notice of the lien. He further explained that the February 6, 2024, demand letter implied that the Siemers had received notice of the lien from the county register of deeds within 10 days of its filing; therefore, Artisan sending notice would have been redundant.

-2- Because Artisan sending a copy of the lien to the Siemers was a prerequisite to foreclosure, the court granted a directed verdict against Artisan on its claim for foreclosure of the construction lien. The district court entered an order resolving the parties’ remaining claims. The court noted that it generally found the testimony of all witnesses to be credible. Regarding the competing claims for breach of contract, the court found that Artisan breached the contract by making a premature demand for payment and that it unjustifiably terminated the contract prior to full completion of the contract. It awarded the Siemers a setoff against the remaining amounts due. It denied Artisan’s claim for unjust enrichment and denied the Siemers’ claim for slander of title. As to the claim for bad faith lien, the court noted that although the lien was not valid because Artisan had failed to provide the Siemers with notice, there was no evidence that Artisan had knowledge the construction lien was invalid or that Artisan acted in reckless disregard for such facts when it filed or refused to release the lien. The Siemers now appeal only from the portion of the district court’s order denying their claim for bad faith lien. III. ASSIGNMENT OF ERROR The Siemers assign, restated and condensed, that the district court erred by denying their claim for bad faith lien. IV. STANDARD OF REVIEW In an appeal of an equitable action, an appellate court tries factual questions de novo on the record and reaches a conclusion independent of the findings of the trial court, provided, where credible evidence is in conflict on a material issue of fact, the appellate court considers and may give weight to the fact that the trial judge heard and observed the witnesses and accepted one version of the facts rather than another. Tilt-Up Concrete v. Star City/Federal, 255 Neb. 138, 582 N.W.2d 604 (1998). An appellate court will uphold a lower court’s decision allowing or disallowing attorney fees for frivolous or bad faith litigation in the absence of an abuse of discretion. See Chicago Lumber Co. of Omaha v. Selvera, 282 Neb. 12, 809 N.W.2d 469 (2011). See also Model Interiors v. 2566 Leavenworth, LLC, 19 Neb. App. 56, 809 N.W.2d 775 (2011), disapproved on other grounds, Echo Group v. Tradesmen Internat., 312 Neb. 729, 980 N.W.2d 869 (2022). V. ANALYSIS The Siemers claim that the district court’s order should be reversed because Artisan acted in bad faith when filing and refusing to release its construction lien on their property. Under the Nebraska Construction Lien Act, Neb. Rev. Stat.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tilt-Up Concrete, Inc. v. Star City/Federal, Inc.
582 N.W.2d 604 (Nebraska Supreme Court, 1998)
Wayne L. Ryan Revocable Trust v. Ryan
308 Neb. 851 (Nebraska Supreme Court, 2021)
Echo Group v. Tradesmen Internat.
980 N.W.2d 869 (Nebraska Supreme Court, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
Artisan Pools, Inc. v. Siemer, Counsel Stack Legal Research, https://law.counselstack.com/opinion/artisan-pools-inc-v-siemer-nebctapp-2026.