Fortune v. Superior Court

768 P.2d 1194, 159 Ariz. 549, 28 Ariz. Adv. Rep. 9, 1989 Ariz. App. LEXIS 38
CourtCourt of Appeals of Arizona
DecidedFebruary 14, 1989
DocketNo. 1 CA-SA 88-244
StatusPublished
Cited by4 cases

This text of 768 P.2d 1194 (Fortune v. Superior Court) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fortune v. Superior Court, 768 P.2d 1194, 159 Ariz. 549, 28 Ariz. Adv. Rep. 9, 1989 Ariz. App. LEXIS 38 (Ark. Ct. App. 1989).

Opinions

OPINION

JACOBSON, Judge

This is a special action from the trial court’s order denying defendants’ motion for partial summary judgment, which motion sought to release a mechanic’s and materialmen’s lien recorded by the plaintiff/real party in interest, Million Development Company (Million). The issue raised is whether the trial court erred in failing to find the lien invalid as a matter of law.

Procedural Background

This special action arises out of an action brought by Million against petitioners, Robert L. Fortune and Joan E. Fortune (Fortunes), for breach of a contract that provided for Million to supervise the planning and construction of a 4,500 square foot custom home for the Fortunes, at an anticipated [550]*550cost of $450,000, with Million’s payment to be 12% of the cost, or $54,000, due and payable in several increments as construction progressed. Count One of the complaint sought foreclosure of a mechanic’s lien for $48,600 that Million had recorded against Fortunes’ property. Count Two sought damages for breach of contract and attorneys’ fees.

The Fortunes filed a motion for partial summary judgment as to Count One for release of the mechanic’s and material-men’s lien. They argued that the lien was invalid on three grounds: first, that Million’s services as an independent contractor were not lienable “labor” or “professional services” under the statutory scheme; second, that a lien could not attach for the contract balance of $48,600, which constituted unperformed. services or anticipated profits; and third, that the lien was untimely recorded. The trial court denied the motion, ruling, "There are issues of fact in this matter which must be determined at trial.” The Fortunes brought this special action seeking review of that ruling.

Special Action Jurisdiction

We generally decline jurisdiction of cases seeking review of orders denying summary judgment. See United States v. Superior Court, 144 Ariz. 265, 269, 697 P.2d 658, 662 (1985). When, however, a pure issue of law can be decided as well at this stage as on appeal after lengthy litigation, we may exercise our discretion and accept jurisdiction. Id.

Here, the Fortunes contend that if we find the lien invalid as a matter of law, special action relief would effectively terminate that part of the litigation regarding the lien, thus allowing them to develop or sell the real property while the parties are litigating their contract claims. Million argues, however, that the Fortunes have an adequate remedy at law because, pursuant to A.R.S. § 33-1004, they can discharge the mechanic’s lien by filing a bond. Fortunes reply that the required amount of the bond, $79,200, would tie up almost $80,000 in cash, in both fees and security deposits, while the litigation is pending. Their only alternative to the bond is to live with the cloud on their title to the subject property caused by an invalid lien until a final judgment is entered, and perhaps appealed. We note that Fortunes have already exhausted their remedy of filing a complaint with the Registrar of Contractors to extinguish the lien, see A.R.S. § 33-420, apparently without gaining any relief, because the Registrar, noting that this matter was pending in superior court, declined to adjudicate the legality of the lien and dismissed that complaint.

Because we conclude that the trial court abused its discretion by failing to find the lien invalid as a purely legal issue, and our ruling will terminate this portion of the litigation, we exercise our discretion and accept special action jurisdiction.

Facts

The following facts are undisputed. In July 1986, the parties entered into a “Custom Construction Agreement,” which provided that Million would supervise the development of plans and construction of the Fortunes’ home. Although Million was a licensed general contractor, its role in connection with the project was “to supervise the construction of the Project as an independent contractor of Owner,” and it had no liability to pay any contractor it hired for the project. The contract set forth the following schedule of payments to Million:

... The fee shall be in percentages of the total anticipated cost of construction. The total anticipated cost of construction is four hundred fifty thousand dollars ($450,000) which Owner hereby approves and acknowledges as only an estimate. The anticipated total fee is 12% of the above anticipated cost of construction, or $54,000. The fee shall be due and payable as follows:
(A) Upon the execution of this Agreement 10% of the anticipated total fee: or based on the estimated cost, the sum of $5,400;
(B) The sum of 15% of the anticipated total fee upon approval of floor plans, elevations and working drawing; or $8,100;
[551]*551(C) The sum of 25% of the anticipated total fee upon completion of the concrete slab; or $13,500;
(D) The sum of 25% of the anticipated total fee upon completion of the drywall; or $13,500; and
(E) The balance, or 25% of the total actual fee, upon completion of the Project. This balance is variable since it will be calculated as that amount remaining to be paid after deducting all fee payments from the total actual Project cost x 12%.

The contract also provided that as liquidated damages Million was entitled to a sum equal to “the balance of the total fee owing to Million pursuant to [the schedule of payments above].”

The Fortunes had paid Million $4,000 at their initial meeting, and paid it an additional $1,400 on execution of the contract, to total the $5,400 initial scheduled payment. Their next payment thus was due upon approval of the plans.

Million began working with an architectural firm, whom the Fortunes paid, to design construction plans. Several new plans were developed until all the requested modifications were incorporated. The architect calculated the square footage of the modified plans at 7,000 square feet, and the Fortunes asked for a cost estimate.

While the plan modifications were underway, Million arranged for an electrician to bury an electrical line under the Fortunes’ property in January 1987, and arranged for a fence to be constructed on the property in March 1987. The Fortunes paid the contractors directly for these improvements.

In April 1987, Million presented a cost estimate, based on the revised plans, of $125 per square foot, or $785,000. This exceeded the original estimate of $80 per square foot, on which the $450,000 anticipated project cost was based. On April 23, 1987, the Fortunes advised Million that they would not approve the plans, and that they no longer wanted- Million involved in the project. Million presented them with a bill for the second payment installment of $8,100, which the Fortunes refused to pay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zepsa Construction, Inc. v. Randazzo
591 S.E.2d 29 (Court of Appeals of South Carolina, 2004)
United Metro Materials, Inc. v. Pena Blanca Properties, L.L.C.
4 P.3d 1022 (Court of Appeals of Arizona, 2000)
Tilt-Up Concrete, Inc. v. Star City/Federal, Inc.
582 N.W.2d 604 (Nebraska Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
768 P.2d 1194, 159 Ariz. 549, 28 Ariz. Adv. Rep. 9, 1989 Ariz. App. LEXIS 38, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fortune-v-superior-court-arizctapp-1989.