Lanier v. Lovett

213 P. 391, 25 Ariz. 54, 1923 Ariz. LEXIS 109
CourtArizona Supreme Court
DecidedMarch 14, 1923
DocketCivil No. 2012
StatusPublished
Cited by17 cases

This text of 213 P. 391 (Lanier v. Lovett) is published on Counsel Stack Legal Research, covering Arizona Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lanier v. Lovett, 213 P. 391, 25 Ariz. 54, 1923 Ariz. LEXIS 109 (Ark. 1923).

Opinion

ROSS, J.

This suit involves the establishment and foreclosure of a lien under the mechanic’s lien law. It was instituted against J. E. Lanier and Sadie E. Lanier, his wife, as the owners, or reputed owners, of lot 4, block 11, East Evergreen addition to the city of Phoenix, and N. S. Brown as the contractor to whom, the notice of lien and the complaint state and allege, the material was furnished and the labor and services rendered. The case was tried before the court, without a jury, and at its close judgment for the amount of the lien claim was entered against the defendants Lanier only for the foreclosure of the mechanic’s lien. From this judgment the defendants appeal.

The defendants’ first contention is that the court committed error in entering judgment establishing the lien and foreclosing it against defendants Laniers’ property, in the absence of Contractor Brown, who was not served with process and did not appear. It is insisted that the contractor was a necessary or indispensable party defendant.

In Lucky Boy Min. & Mill. Co. v. Moore, 23 Ariz. 291, 203 Pac. 556, the very question raised was passed upon and the conclusion reached that the original contractor was a necessary party. Following the authority of some of the cases cited therein to the effect that the owner of the property, against which the lien is sought, may waive his right to have the original contractor joined in the suit, we think this case affords an example wherein there was such waiver.

The failure of plaintiff to obtain service upon the original contractor, and his nonappearance, were not [57]*57raised in the court below. The trial proceeded, both parties introduced their evidence, and the judgment of foreclosure was entered without any objection on the part of the defendants. It was not made the basis of a motion for new trial. It is first suggested on appeal.

In Lewis v. Beeman, 46 Or. 311, 80 Pac. 417, the lien claimants made the contractors parties defendant in their complaint, but failed to serve them with summons, and they did not appear in the action. The case proceeded to trial, the parties introduced their evidence, whereupon the defendant land owner objected to the entry of the judgment because the contractor had not been served with process. Upon that state of the record, the trial court refused to enter judgment for the plaintiff, and upon appeal there was a reversal; the Supreme Court stating:

“The statutory requirement of making persons parties who are personally liable, which was enacted for the benefit of the mine owner, is not one in the enforcement of which the public has an interest;, and therefore such owner can waive the advantage which the law confers. This he does when he fails to demand that the persons personally liable shall be brought in for his protection, . . . and, in the case at bar, as the Beemans did not object to the defect of parties until after the testimony was taken, they thereby voluntarily relinquished the right upon the exercise of which they insisted, when the cause was submitted, in dismissing which the court erred.”

If there was a waiver in that case merely by delaying to interpose an objection until after the testimony was introduced, it would seem that the conduct of the defendants in this case should be construed as a waiver, since they not only participated in the trial and acquiesced in the entry of judgment in the lower court, but entirely failed to raise the question until it reached the Supreme Court. [58]*58Brace etc. Mill Co. v. Burbank, 87 Wash. 356, Ann. Cas. 1917E, 739, 151 Pac. 803.

It is next contended that the notice of lien is insufficient in not specifying the material furnished or labor performed, or what labor and material the lien claimant’s contract with Brown required him to furnish, or what he was required to do under such contract.

Paragraph 3641, Civil Code of 1913, prescribes a form of lien notice, which in this instance was followed in its general outline. Subdivision 1 of the notice of lien affirms the performance of labor and furnishing of materials in the construction of the building, improvement or structure, and describes the lot upon which said building, improvement or structure is located, giving' its number and description according to the map of East Evergreen addition to the city of Phoenix. Subdivision 2 designates J. R. Lanier as the owner of said lot, and states that he caused said improvements to be made. Subdivision 3 gives the name of N. S. Brown as the contractor. We quote subdivisions 4 and 6:

“(4) That on the 14th day of October, 1920, he (claimant) entered into a contract with said N. S. Brown for the furnishing of labor and material and for the installation of plumbing in said building which contract was oral, and the following is the statement of the terms, time given and conditions thereof:
“That affiant agreed with said N. S. Brown to furnish the materials and to perform the labor necessary for the installation of all the plumbing on said above-described premises, and that said plumbing, and the materials furnished therefor, and the labor performed thereon, was to be paid for upon the completion of the building by said N. S. Brown.”
“(6) That the following is a statement of his demand under said contract, after deducting all just credits and offsets:
“Original contract price, $372.00.
[59]*59“Amount paid thereon, 000.00.
“Amount due and unpaid after deducting all just credits and offsets, $372.00.”

Paragraph 3640, Id., provides what the notice of lien shall contain as follows:

“(a) A description of the lands and improvements to be charged with the lien, sufficient for identification.
“(b) The name of the owner or reputed owner of the property concerned, if known, and also the name of the person by whom the lienor was employed or to whom he furnished materials.
“(c) A statement of the terms, time given and conditions of his contract, if the same be oral, or a copy of the contract, if written.
“(d) A statement of the lienor’s demand, after deducting all just credits and offsets.”

The defendants’ contention is that the contract set out in the notice of lien does not meet the requirements of this statute, in that it does not state what labor was to be performed or material furnished and, further, that the notice itself is defective in not itemizing such material and labor.

It seems to us the contract as stated is not open to serious criticism, since it embraces all work and material to a completed job of plumbing. The omission in the notice of lien to itemize the different articles that went into the job, and the days of labor consumed in placing them, may be excused on the theory that they were not, under the contract between the contractor and plaintiff, to be paid for as furnished or rendered, but as a whole. It is true, the owner may not be compelled to pay more than “the reasonable value of labor or materials furnished” (paragraph 3639, Civ. Code), and is not bound by the agreed price between the contractor and the lien claimant, yet such agreed price may be taken as prima facie correct. Mitchell Planing Mill Co. v. Allison, 138 Mo. 50, 60 Am. St. Rep.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Midwest Floor Co. v. Miceli Development Co.
304 S.W.3d 243 (Missouri Court of Appeals, 2009)
Judd Fire Protection, Inc. v. Davidson
773 A.2d 573 (Court of Special Appeals of Maryland, 2001)
United Metro Materials, Inc. v. Pena Blanca Properties, L.L.C.
4 P.3d 1022 (Court of Appeals of Arizona, 2000)
Fortune v. Superior Court
768 P.2d 1194 (Court of Appeals of Arizona, 1989)
Diener v. Cubbage
270 A.2d 471 (Court of Appeals of Maryland, 1970)
Scutti v. State Road Department
220 So. 2d 628 (District Court of Appeal of Florida, 1969)
Lenslite Co. v. Zocher
388 P.2d 421 (Arizona Supreme Court, 1964)
Monarch Lumber Co. v. Wallace
314 P.2d 884 (Montana Supreme Court, 1957)
Parker v. Holmes
284 P.2d 455 (Arizona Supreme Court, 1955)
Springfield Gas Light Co. v. Board of State Examiners
110 N.E.2d 113 (Massachusetts Supreme Judicial Court, 1953)
Rosebud Lumber & Coal Co. v. Holms
53 N.W.2d 82 (Nebraska Supreme Court, 1952)
State Ex Rel. Holbert v. Robinson
59 S.E.2d 884 (West Virginia Supreme Court, 1950)
Palmer v. Apperson
215 P.2d 1020 (Arizona Supreme Court, 1950)
Kendall Lumber & Coal Co. v. Roman
91 N.E.2d 187 (Indiana Court of Appeals, 1950)
Caird Engineering Works v. Seven-Up Gold Mining Co., Inc.
111 P.2d 1267 (Montana Supreme Court, 1940)
Netter v. Scholtz, Mayor
138 S.W.2d 951 (Court of Appeals of Kentucky (pre-1976), 1940)

Cite This Page — Counsel Stack

Bluebook (online)
213 P. 391, 25 Ariz. 54, 1923 Ariz. LEXIS 109, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lanier-v-lovett-ariz-1923.