Charles v. E. F. Hallack Lumber & Manufacturing Co.

22 Colo. 283
CourtSupreme Court of Colorado
DecidedJanuary 15, 1896
StatusPublished
Cited by10 cases

This text of 22 Colo. 283 (Charles v. E. F. Hallack Lumber & Manufacturing Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charles v. E. F. Hallack Lumber & Manufacturing Co., 22 Colo. 283 (Colo. 1896).

Opinion

Mr. Justice Goddard

delivered the opinion of the court.

It appears from the certificate to the bill of exceptions that it does not contain all of the evidence introduced upon the trial of the cause, the original exhibits which include the plans and' specifications being omitted. These are made in express terms a part of the contract, and are therefore important and essential factors in determining the principal issue in the case. Without them before us we are unable to [289]*289determine whether the building was completed in conformity with them or not, or pass upon the sufficiency of the evidence to sustain the conclusions reached by the trial court, and must accept as conclusive its finding that Thompson & Tomlinson had substantially performed their contract, except in the particular mentioned.

It is insisted by plaintiff in error that this finding in itself, by reason of the exception, fails to bring the case within the most liberal rule of substantial performance, since it shows so material a deviation as to entitle Charles to the sum of $2,000 as damages on account thereof, and that the exception neutralizes the force of the finding as to the fact of substantial performance, and leaves the question open for this court to examine the contract in the light of the evidence, and determine whether the condition of the floors was in conformity with its stipulations and the plans and specifications ; but for the reason above stated we are precluded from this investigation, and can only look to the pleadings, and ascertain therefrom the theory upon which the case was tried, and determine whether, under all the provisions of the contract therein set forth, such finding can be upheld, and, if so, its sufficiency to support a recovery in this character of action. Upon an examination of the contract it will be seen that, while performance as to work and materials in conformity with its provisions is made a condition precedent to payment, it also provides that if the work or material are contrary to its requirements the architect shall have authority to remove the same and replace them by proper work and materials at the contractors’ cost. It also appears from the pleadings that although the issue of performance was tendered by the cross complaint of Thompson & Tomlinson, and the answer of Charles, that by way of counterclaim he sought to recoup damages on account of defective floors, and alleged as a ground for such damages that he was compelled “to wholly relay and cover with, new flooring.said building, and by reason of said acts mentioned of said defendants [290]*290Thompson & Tomlinson in respect to said flooring, he was damaged thereby in the sum and amount of $4,000 ; ” etc.

And he further avers that on or about the 5th day of May, 1890, Thompson & Tomlinson made and presented a statement and account of extra work and labor; and thereupon he made and presented to them a statement and account for labor and materials omitted, and also presented a claim fox-damages, by reason of bad floors, accruing up to that time; and that being unable to agx-ee, the respective claims and demands were .referred to L. Cutshaw, architect, for his examination and decision, both under the terms of said contract and by express agreemeixt of the several parties; and it was decided by said Cutshaw, among other things, “that fox-damages as aforesaid by reason of bad floors, there ought to be allowed the defendant the sum of $1,500 ; ” etc. In his prayer he asks, among other things, that axx accounting may be had as between him and Thompson & Tomlinson as to the sum, if any, due to them; and that upon such accounting he may be allowed and credited with his damages in said sum of $4,000, etc.; and that he may recoup the same against their claim under the contract, and that he may be permitted and directed to bring such sum as may be found due from him to said Thompson & Tomlinson into court, etc.

It would seem, therefore, that the finding was in accordance with the issues made by the pleadings, and a proper one in view of the theory upoix which the case was tried, and that the plaintiff in error is not now in a position to invoke the application of the rigid rule anixounced by some courts to the effect that when performance is stipulated for and made a condition precedent to the right of recovery, axxd the action is solely oix the contract, performance in every essential particular must be shown before a recovery can be had, or to insist that under the issues tendered by the pleadings in this case no excuse for íxonperformance can be shown, nor x-ecovery of the contract price (less damages on account of omissioxx) be had. Whether he xxxight, if he had elected so to do, have stood upon his technical rights under the contract, [291]*291and successfully resisted payment of the balance of the contract price until a strict performance of all the requirements of the contract was had and the certificate of the architect produced, as provided therein, it is unnecessary to determine, since he has elected to avail himself of his option under the contract to replace the defective flooring and repair the omissions of the contractors in respect thereto, and to submit his claim for the amount expended in the completion of their work as a set-off or counterclaim against the amount, if any, found due them under the contract. In support of his position he invokes the rule adopted in New York and some other states to the effect that a strict performance is necessary as a condition precedent to recovery on the contract. Among them, the case of Van Clief v. Van Vechten, 130 N. Y. 571, is cited as being particularly in point upon the proposition that when a substantial sum is required to finish the work, a substantial performance has not been had. In that case the contractor was to furnish materials and erect a building for the net price of $4,023, payable in installments. Among such installments was the sum of $800, to be paid when the plastering was finished. He abandoned his contract, leaving the building uncompleted, and refused further performance. After such refusal the owner furnished materials and employed a workman to finish the building at an expense of $1,905.20, which included $200 for completing the plastering. The suit was brought by a subcontractor to obtain a lien against the building for materials furnished the contractor.

After referring with approval to the doctrine announced in former cases upon the subject of substantial performance, and expressly finding that the plastering was not substantially finished, and that the abandonment of the work was willful, and the omission to perform intentional, thé court say:

“ The owner, however, although under no obligation to do so, completed the building herself, according to the oontract, which thus continued operative through her action. After the contractor refused to proceed she performed the contract [292]*292for him, as it expressly permitted her to do. As her action was according to the contract, it will be presumed, under all the circumstances and in support of the judgment, that it was under the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Little Thompson Water Association v. Strawn
466 P.2d 915 (Supreme Court of Colorado, 1970)
Campbell v. Koin
391 P.2d 365 (Supreme Court of Colorado, 1964)
Monarch Lumber Co. v. Wallace
314 P.2d 884 (Montana Supreme Court, 1957)
Dickinson v. Brotherhood of Locomotive Firemen & Enginemen
255 P. 450 (Supreme Court of Colorado, 1927)
Lanier v. Lovett
213 P. 391 (Arizona Supreme Court, 1923)
Morris v. Hokosona
26 Colo. App. 251 (Colorado Court of Appeals, 1914)
State Bank v. Plummer
54 Colo. 144 (Supreme Court of Colorado, 1912)
Price v. Immel
48 Colo. 163 (Supreme Court of Colorado, 1910)
Lombard v. Overland Ditch & Reservoir Co.
41 Colo. 253 (Supreme Court of Colorado, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
22 Colo. 283, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charles-v-e-f-hallack-lumber-manufacturing-co-colo-1896.