Zepsa Construction, Inc. v. Randazzo

586 S.E.2d 599, 356 S.C. 39, 2003 S.C. App. LEXIS 142
CourtCourt of Appeals of South Carolina
DecidedSeptember 15, 2003
DocketNo. 3673
StatusPublished
Cited by2 cases

This text of 586 S.E.2d 599 (Zepsa Construction, Inc. v. Randazzo) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zepsa Construction, Inc. v. Randazzo, 586 S.E.2d 599, 356 S.C. 39, 2003 S.C. App. LEXIS 142 (S.C. Ct. App. 2003).

Opinion

CURETON, J.:

In this action to foreclose a mechanic’s lien, the master ordered judgment against Phillip and Virginia Randazzo in the amount of $50,846.00, and awarded attorney’s fees to Zepsa in the amount of $8,123.40. The Randazzos appeal, arguing the master erred in: (1) including lost profits and overhead in the amount of the mechanic’s lien; and (2) awarding attorney’s fees to Zepsa. We affirm as modified.

FACTS

Phillip and Virginia Randazzo (collectively, “Randazzos”), owned and operated an Italian restaurant near Tega Cay Village Shopping Center in Fort Mill, South Carolina. In September 1996, they contacted Ed Zepsa, president of Zepsa Construction, Inc. (“Zepsa”) to inquire about the design and construction of a new restaurant. After several months of discussions and negotiations, the parties entered into on May 14, 1997, a written construction contract for Zepsa to build the restaurant. The agreed price was $610,000.00. The terms of the contract required a deposit in the amount of $61,000.00 to be paid when the contract was signed.

[42]*42On May 29, 1997, the Randazzos gave written “notice to proceed” with construction. At that time, they provided Zepsa -with a check for $21,000.00, representing part of the agreed deposit. Zepsa did not begin work at this time because the Randazzos had not paid the full deposit. By letter dated July 1.1997, Zepsa agreed to accept the remainder of the deposit in two installments. These installments were to be paid at the time of the first two payment requests after construction began. Zepsa began work on the site on July 7, 1997. Between July 15 and August 2, 1997, Virginia Randazzo (Virginia) spoke by phone with either Ed Zepsa or the project manager on four occasions. During these conversations, she asked about terminating the contract due to the Randazzos’ marital problems, instructed Zepsa to stop work, and told Zepsa to continue to delay construction while the Randazzos tried to resolve their marital difficulties. On August 3, Virginia called Ed Zepsa and told him she did not want to continue with the project.

On August 4, the Randazzos contacted Ed Zepsa and instructed him to proceed with construction. In response, he submitted a payment request seeking payment of $8,674.00 for work that had been performed and $40,000.00 for the balance of the deposit. Also on August 4, Zepsa received a letter from the Randazzos’ attorney requesting that Zepsa abide by the deposit payment schedule and proceed with the work. Zepsa resumed work on the project.

On August 11, Zepsa submitted a payment request for work performed through July and included a request for the next deposit installment. No payment was made for this completed work or the deposit installments. By letter dated August 28, 1997, the Randazzos’ attorney gave notice of termination of the contract.

Zepsa timely filed a lis pendens and complaint on October 16.1997. The complaint sought judgment against the Randazzos and foreclosure of a mechanic’s lien that Zepsa had previously filed and served. The matter was referred with finality to the master. At the hearing, Zepsa presented uncontested evidence that Zepsa performed construction work on the job site in the amount of $10,846.00. In his order dated January 22, 2001, the master granted Zepsa judgment against [43]*43the Randazzos in the amount of $50,846.00, which included the unpaid balance for work already performed and payment for the remaining deposit balance of $40,000.00. By order dated March 22, 2001, the master awarded Zepsa attorney’s fees in the amount of $8,123.40, and costs in the amount of $1,490.60. The Randazzos appeal.

STANDARD OF REVIEW

“An action to foreclose a mechanic’s lien is a law case in South Carolina.” Keeney’s Metal Roofing, Inc. v. Palmieri, 345 S.C. 550, 553, 548 S.E.2d 900, 901 (Ct.App.2001). “In an action at law, tried without a jury, the judge’s findings will not be disturbed unless they are without evidentiary support.” King v. PYA/Monarch, Inc., 317 S.C. 385, 388, 453 S.E.2d 885, 888 (1995). “His findings are equivalent to those of a jury in an action at law.” Id. at 389, 453 S.E.2d at 888.

DISCUSSION

I. Mechanic’s Lien

The Randazzos argue the master erred by including lost profits in the amount of the mechanic’s lien when only a small portion of the contract work was actually performed.

Section 29-5-10 of the South Carolina Code of Laws defines a mechanic’s lien. S.C.Code Ann. § 29-5-10 (1991 & Supp. 2002).1 This section provides in pertinent part:

(a) A person to whom a debt is due for labor performed or furnished or for materials furnished and actually used in the erection, alteration, or repair of a building or structure upon real estate or the boring and equipping of wells, by virtue of an agreement with, or by consent of, the owner of the building or structure, or a person having authority from, or rightfully acting for, the owner in procuring or furnishing the labor or materials shall have a lien upon the building or structure and upon the interest of the owner of the building [44]*44or structure in the lot of land upon which it is situated to secure the payment of the debt due to him.

S.C.Code Ann. § 29-5-10(a) (1991).

In the instant case, the master granted a judgment against the Randazzos in the amount of $50,846.00 based on two grounds. First, the master found Zepsa’s lost profits and overhead expenses were recoverable as an element of damages for the Randazzos’ breach of the construction contract. Secondly, the master concluded “these elements of damage [were also] recoverable in a mechanic’s lien foreclosure action.” The master reasoned:

Since Zepsa is entitled to profits and overhead expenses, there is a reasonable and equitable basis for claiming the balance of the deposit as an integral part of the payment due under the contract, unrelated to actual work performed. Thus, Zepsa is entitled to be paid the balance of the deposit due, along with the balance due for work which was performed.

As a threshold matter, we find the master erred in awarding Zepsa an in personam judgment based on a breach of contract cause of action.2 In its complaint, Zepsa only pleaded factual allegations consistent with statutory recovery under a mechanic’s lien.3 As such, Zepsa could not recover an in personam judgment against the Randazzos based on a breach of contract action that was neither pleaded nor permitted by the statutory parameters for the foreclosure of a mechanic’s lien. See Atl. Coast Lumber Corp. v. Morrison, 152 S.C. 305, 309-10, 149 S.E. 243, 245 (1929) (“[I]n a proceeding strictly to enforce a mechanic’s lien, the petitioner may not recover a personal judgment against the owner of the property or such judgment for any deficiency that may result from [45]*45its sale.”); Smythe v. Monash, 109 S.C. 82, 85, 95 S.E. 138, 139 (1918) (holding trial judge erred in awarding in personam judgment to plaintiff who brought an action to foreclose a mechanic’s lien given “it would not have been in accordance with the terms of the statute providing for the foreclosure of a mechanic’s lien”); Metz v. Critcher, 83 S.C. 396, 65 S.E.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zepsa Construction v. Randazzo
Court of Appeals of South Carolina, 2005
Ashley Engineering v. TKS Construction
Court of Appeals of South Carolina, 2004

Cite This Page — Counsel Stack

Bluebook (online)
586 S.E.2d 599, 356 S.C. 39, 2003 S.C. App. LEXIS 142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zepsa-construction-inc-v-randazzo-scctapp-2003.