Sentry Engineering & Construction, Inc. v. Mariner's Cay Development Corp.

338 S.E.2d 631, 287 S.C. 346, 1985 S.C. LEXIS 536
CourtSupreme Court of South Carolina
DecidedDecember 11, 1985
Docket22423
StatusPublished
Cited by21 cases

This text of 338 S.E.2d 631 (Sentry Engineering & Construction, Inc. v. Mariner's Cay Development Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sentry Engineering & Construction, Inc. v. Mariner's Cay Development Corp., 338 S.E.2d 631, 287 S.C. 346, 1985 S.C. LEXIS 536 (S.C. 1985).

Opinion

Chandler, Justice:

This action arises out of a breach of contract for condominium construction.

We affirm.

Appellant-Developer (MCDC) and Respondent-Builder (Sentry) executed a “Standard Form of Agreement Between Owner and Contractor” (Base Agreement) providing for the cost of construction. Concurrently, the parties executed a separate document entitled “Agreement for Profit and Overhead” (Side Agreement) for additional compensation above construction cost.

As the project neared completion, Sentry became concerned about payment. It filed a mechanic’s lien for balances due under both Agreements and for change orders, to which MCDC filed an appropriate bond with Appellant Eastern Indemnity Company of Maryland as surety. Sentry exercised its contractual right of arbitration, filing a claim with the American Arbitration Association (AAA) in the amount of its mechanic’s lien. Simultaneously, Sentry filed a petition in Circuit Court to foreclose its lien.

*349 The Circuit Court rejected MCDC’s objection to arbitration and ordered arbitration of all claims arising out of the contract documents. Rights were reserved to the parties to seek statutory relief after the filing of the AAA decision. Sentry then amended its arbitration demand to include claims for damages based on wrongful termination. Sentry also petitioned the Circuit Court for an injunction permitting it access to the site to correct deficiencies in the roof.

The AAA found Sentry entitled to $503,271.00. Pursuant to Sentry’s motions, the Circuit Court adopted the AAA award as a judgment, granted Sentry summary judgment on its mechanic’s lien foreclosure petition, assessed interest and awarded Sentry a reasonable attorney’s fee of $80,000.00. The total judgment was $622,425.00.

MCDC asserts error in (1) ordering arbitration of the Side Agreement, (2) confirmation of the AAA award as a mechanic’s lien judgment, (3) assessment of interest and (4) the award of attorney’s fees.

ISSUES
MCDC contends that the Circuit Judge erred in holding:
(1) that the separate documents, one for construction costs and the other for profit, comprised a single unified agreement;
(2) that Sentry, by seeking Circuit Court relief, did not waive, but retained, its right to arbitration;
(3) that profit and overhead are components of “debt”, as contemplated by the mechanic’s lien statute, S. C. Code Ann. Sec. 29-5-10 (Supp. 1984);
(4) that the arbitration award was convertible into a mechanic’s lien judgment;
(5) that Sentry was entitled to interest;
(6) that Sentry was entitled to attorney’s fees.

I. UNIFIED OR SEPARATE AGREEMENT?

The Base Agreement provided specifically for arbitration, to which the Side Agreement was silent. MCDC contends that the two documents constituted separate contracts, so that Sentry was entitled to arbitration of the Base Agreement dispute only. We disagree.

*350 In Klutts Resort Realty, v. Down ’Round Development Corp., 268 S. C. 80, 232 S. E. (2d) 20 (1977), this Court held

The general rule is that, in the absence of anything indicating a contrary intention, where instruments are executed at the same time, by the same parties, for the same purpose and in the course of the same transaction, the courts will consider and construe the instruments together. The theory is that the instruments are effectively one instrument or contract. [Emphasis supplied.]

268 S. C. at 88, 232 S. E. (2d) at 24.

The Circuit Court found as a fact that the two documents comprised a single, integrated agreement. We agree.

This litigation involves a breach of contract and the enforcement of a statutory lien. Both are actions at law. Moore v. Crowley & Associates, Inc., 254 S. C. 170, 174 S. E. (2d) 340 (1970) (breach of contract); Raines v. Sanders, 134 S. C. 284, 132 S. E. (2d) 581 (1926) (mechanic’s lien). In a non-jury case the findings of fact will not be disturbed unless found to be without reasonable evidentiary support. Townes Associates, Ltd. v. City of Greenville, 266 S. C. 81, 221 S. E. (2d) 773 (1976).

The Side Agreement, by reference, incorporates the Base Agreement and its general conditions. A modification is defined in the Base Agreement as a written amendment signed by both parties. The Side Agreement meets this definition. Thus, each incorporates the other. This reasonably supports the Circuit Judge’s finding of a single, integrated contract subject to arbitration.

The two documents refer to different components of the contract’s price term: payment for actual work and payment for profit. Under the Klutts test, the purpose of both is the same: compensation for project construction. The Circuit Court correctly ordered that Sentry’s claims under both documents be decided by. arbitration.

Additionally, S. C. Code Ann. Sections 15-48-130 (Supp. 1984) and 15-48-140 (Supp. 1984) provide the exclusive procedures for vacating or modifying awards where arbitrators exceed their powers or award upon a matter not properly submitted to them. MCDC filed no motion to vacate or modify within 90 days of delivery of a *351 copy of the award. Consequently, the award became the law of the case.

II. WAIVER OF RIGHT TO ARBITRATE

MCDC asserts Sentry’s acts in filing a petition for a prohibitory injunction allowing it to complete roof work are inconsistent with a right to arbitrate. It argues further that the prejudice resulting to it by Sentry’s action constituted a waiver of arbitration. Sentry counters that the petition for injunction did not seek to litigate any issue raised by arbitration, but was simply an attempt to correct work complained of by MCDC.

Federal decisions require a showing of prejudice when waiver is asserted. Carcich v. Rederi A/B Nordie, 389 F. (2d) 692, 696 (2d Cir. 1968) holds that it is not inconsistency, but the presence or absence of prejudice which is determinative. In this context prejudice is undue burden on the objecting party, brought about by delay in the other party’s making its demand for arbitration. Batson Yarn and Fabrics Machinery Group, Inc. v. Saurer-Alma GmbH-Allgauer Maschinenbau, 311 F. Supp. 68 (D.S.C. 1970); Episcopal Housing Corp. v. Federal Ins. Co., 269 S. C. 631, 239 S. E. (2d) 647 (1977). MCDC shows no prejudice by delay, only the inconvenience of litigating the petition for injunction.

“[Wjaiver may not be inferred from the fact that a party does not rely exclusively on the arbitration provisions of a contract, but attempts to meet all issues raised in litigation between it and another party to the agreement.” Germany v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weckesser v. Knight Enterprises S.E., LLC
228 F. Supp. 3d 561 (D. South Carolina, 2017)
Moorhead Construction, Inc. v. Enterprise Bank
765 S.E.2d 1 (Court of Appeals of South Carolina, 2014)
Sure-Shock Electric, Inc. v. Diamond Lofts Venture, LLC
259 P.3d 546 (Colorado Court of Appeals, 2011)
Witt General Contractors v. Farrell
Court of Appeals of South Carolina, 2011
J.D., Inc. v. A-Team Surface Technologies, Inc.
Court of Appeals of South Carolina, 2010
Deloitte & Touche, LLP v. Unisys Corp.
594 S.E.2d 523 (Court of Appeals of South Carolina, 2004)
Zepsa Construction, Inc. v. Randazzo
591 S.E.2d 29 (Court of Appeals of South Carolina, 2004)
Rich v. Walsh
590 S.E.2d 506 (Court of Appeals of South Carolina, 2003)
MailSource, LLC v. M.A. Bailey & Associates, Inc.
588 S.E.2d 639 (Court of Appeals of South Carolina, 2003)
Garvin v. Homes of CSRA, Inc.
Court of Appeals of South Carolina, 2003
Evans v. Accent Manufactured Homes, Inc.
575 S.E.2d 74 (Court of Appeals of South Carolina, 2003)
General Equipment & Supply Co. v. Keller Rigging & Construction, SC, Inc.
544 S.E.2d 643 (Court of Appeals of South Carolina, 2001)
Stiglich Construction, Inc. v. Larson
621 N.W.2d 801 (Court of Appeals of Minnesota, 2001)
Tilt-Up Concrete, Inc. v. Star City/Federal, Inc.
621 N.W.2d 502 (Nebraska Supreme Court, 2001)
Liberty Builders, Inc. v. Horton Ex Rel. Estate of Horton
521 S.E.2d 749 (Court of Appeals of South Carolina, 1999)
Stier, Kent & Canady, Inc. v. Jackson
452 S.E.2d 606 (Court of Appeals of South Carolina, 1994)
Maddux Supply Co., Inc. v. Safhi, Inc.
450 S.E.2d 101 (Court of Appeals of South Carolina, 1994)
Stanley Smith & Sons, Inc. v. Dumas
431 S.E.2d 595 (Court of Appeals of South Carolina, 1993)
United States Ex Rel. DMI, Inc. v. Darwin Construction Co.
750 F. Supp. 536 (District of Columbia, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
338 S.E.2d 631, 287 S.C. 346, 1985 S.C. LEXIS 536, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sentry-engineering-construction-inc-v-mariners-cay-development-corp-sc-1985.