Ruscon Construction Co. v. Beaufort-Jasper Water Authority

191 S.E.2d 715, 259 S.C. 314, 1972 S.C. LEXIS 246
CourtSupreme Court of South Carolina
DecidedSeptember 20, 1972
Docket19492
StatusPublished
Cited by8 cases

This text of 191 S.E.2d 715 (Ruscon Construction Co. v. Beaufort-Jasper Water Authority) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ruscon Construction Co. v. Beaufort-Jasper Water Authority, 191 S.E.2d 715, 259 S.C. 314, 1972 S.C. LEXIS 246 (S.C. 1972).

Opinion

Littlejohn, Justice.

On November 20, 1963, Ruscon Construction Company of Florida contracted to build subaqueous mains for Beaufort Jasper Water Authority. The work was performed by Ruscon and accepted by Water Authority in August, 1965. At that time Ruscon submitted its final estimate for final payment for work done under the contract. A dispute arose concerning the proper type of release Ruscon should give upon- final payment, and as a result Water Authority held the final payment of $180,758.96 until September 1, 1967, at which time Ruscop signed the release and accepted payment. This sum held by Water Authority was invested by it and earned interest in the amount of $16,428.40 as of September 1, 1967.

This action was commenced by Ruscon against Water Authority in May, 1969, to recover the amount of the interest the $180,000.00 had earned during the time payment was delayed. The $180,000.00 was paid and accepted with a stipulation that an action could be bropght to settle the interest question.

*317 The questions we decide on this appeal are whether Water Authority’s tender conditioned upon a complete release was valid and whether the refusal of acceptance by Ruscon was justified.

The complaint alleges that payment of the final installment was delayed through no fault of Ruscon and alleges that it is due the interest earned by the investment during the delay. It prays judgment in the amount of $16,428.40 plus interest earned by the interest since September 1, 1967.

The answer of Water Authority denies that it is indebted to Ruscon for the earned interest. It alleges that it made to Ruscon a legal tender and that the legal tender was rejected by Rusco,n, thereby relieving Water Authority of any liability for interest.

Ruscon replied to Water Authority’s answer, denying that a legal tender was made and asserting that the tender was not legal because it was conditional. Ruscon alleges that W. J. McLamb and Son, one of its subcontractors on the project, brought an action in the federal court against Ruscon to settle a dispute relative to this construction project. Ruscon impleaded Water Authority as a third party defendant in that suit on the theory that if McLamb was successful, Rus-con could in turn seek indemnity from Water Authority. Ruscon further alleges that after Water Authority was im-pleaded a meeting was held between representative of Ruscon and representatives of Water Authority and that an agreement was reached whereby Ruscon would drop its third party action against Water Authority in the McLamb suit to enable Water Authority to sell its bonds. In return, Rus-con alleges that Water Authority agree that in the event McLamb should prevail in its suit against Ruscon, then Ruscon would have an action over and against Water Authority for indemnification. Ruscon further alleges that when Water Authority tendered payment, it was accompanied by a demand that Ruscon sign a full release to Water Authority of all claims and liability which Ruscon might have against *318 Water Authority. Therefore, alleges Ruscop, the tender was not valid since it required Ruscon to relinquish rights under both the original construction agreement and the subsequent agreement to dismiss Water Authority from the Mc-Lamb action.

Rucsop subcontracted the project to W. J. McLamb and Son, who subsequently defaulted; a later subcontractor completed the project. After default, McLamb brought an action against Ruscon on the theory of impossibility of performing the contract prepared by Water Authority and its engineer, W. P. Barber. McLamb alleged that the contract was null and void.

When tender of the $180,000.00 was made, about August 1, 1965, the McLamb v. Ruscon case was still in litigation in federal coprt.

The constructiop contract entered into between Ruscon and Water Authority contemplated that Water Authority would receive a full release upon receipt of the final payment. Paragraph 26 of the contract reads as follows:

“Article 26, Acceptance of Final payment as Release.
‘The acceptance by the contractor of final payment shall be and operate as a release to the owner of all claims and liability to the contractor for all things done or furnished in connection with this work and for every act and neglect of the owner and the others relating to or arising out of this wo.rk. No payment, however, final or otherwise shall operate to release the contractor or his sureties from any obligation under this contract or the performance and payment bond.’ ”

After Water Authority and W. P. Barber had been made parties to the federal action, Water Authority needed to, sell revenue bonds but could not do so as long as it was a third party defendant in the federal action. It was at this point that Ruscon agreed to a consent order dismissing Water Authority and W. P. Barber from the action. Thereafter the bonds were sold.

*319 It is the contention of Ruscon that an agreement was made such that if McLamb prevailed in its actio,n against Ruscon, Ruscon would have an action over against Water Authority and Barber. It is the contention of Water Authority that no such agreement was made and that Ruscon agreed to the dismissal of Water Authority and Barber in order that the bonds could be sold to raise money to pay Ruscon and others.

When Water Authority made its tender, it demanded a full and complete release consistent with paragraph 26 of the contract. Ruscon refused to give such a release and offered instead to give a similar release with an exception to the effect that if McLamb prevailed in its federal action, Ruscon would not be barred from seeking indemnification from Water Authority and Barber.

The lower court has left unanswered the factual question: was an agreement entered into between Ruscon and Water Authority whereby the right of Ruscon to sue Water Authority for indemnification was preserved? We think that the evidence is susceptible of the inference that such an agreement was made, but we do no.t think that the result of the case must hinge upon a factual determination of whether such agreement was entered into. It is sufficient that Ruscon belived it would have a bona fide claim for indemnification against Water Authority should McLamb prevail in its collateral action against Rusco.n.

The release which Water Authority demanded for payment included relinquishment of a claim against itself not contemplated by paragraph 26 of the contract, and also included a release of W. P. Barber, the engineer. The claim which Ruscon sought to preserve grew o.ut of a factual situation which arose long after the construction contract was made. Water Authority was not justified in demanding a release of the indemnification claim in exchange for final payment. Water Authority sought and received a benefit when it prevailed upo,n Ruscon to dismiss it from the federal *320 action. Ruscon gave up the right to keep Water Authority and Barber in the case.

It is a long recognized principle in our courts that a valid tender stops the running of interest. Smith v. Stinson, 1 Brev. 1 (1793) ; Ryan v. Baldrick, 3 McCord 498 (1826).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Quarter Pointe Ventures v. Lineberger
Court of Appeals of South Carolina, 2019
Vista Antiques & Persian Rugs, Inc. v. Noaha, LLC
823 S.E.2d 179 (Court of Appeals of South Carolina, 2008)
Flynn v Korneffel
547 N.W.2d 249 (Michigan Supreme Court, 1996)
Stier, Kent & Canady, Inc. v. Jackson
452 S.E.2d 606 (Court of Appeals of South Carolina, 1994)
T & S Brass and Bronze Works, Inc. v. Pic-Air, Inc.
790 F.2d 1098 (Fourth Circuit, 1986)
Sentry Engineering & Construction, Inc. v. Mariner's Cay Development Corp.
338 S.E.2d 631 (Supreme Court of South Carolina, 1985)
Dull v. Dull
674 P.2d 911 (Court of Appeals of Arizona, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
191 S.E.2d 715, 259 S.C. 314, 1972 S.C. LEXIS 246, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ruscon-construction-co-v-beaufort-jasper-water-authority-sc-1972.