Witt General Contractors v. Farrell

CourtCourt of Appeals of South Carolina
DecidedMay 4, 2011
Docket2011-UP-203
StatusUnpublished

This text of Witt General Contractors v. Farrell (Witt General Contractors v. Farrell) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Witt General Contractors v. Farrell, (S.C. Ct. App. 2011).

Opinion

THIS OPINION HAS NO PRECEDENTIAL VALUE.  IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 268(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA
In The Court of Appeals

Witt General Contractors, Inc., Respondent,

v.

Robert Farrell, Appellant.


Appeal From Horry County
Honorable Willard D. Hanna Jr., Special Referee


Unpublished Opinion No. 2011-UP-203
Submitted March 1, 2011 – Filed May 4, 2011   


AFFIRMED


Tucker S. Player, of Columbia, for Appellant.

V. Denise Hamilton and Stacy L. Stanley, of Little River, for Respondent.

PER CURIAM:  In this mechanic's lien foreclosure action, appellant Robert Farrell appeals the decision of the special referee asserting error in the referee's (1) failure to offset the amount of damages for his breach of warranty claim against the judgment in favor of respondent Witt General Contractor's, Inc., (hereinafter Contractor) (2) award of judgment for Contractor on its breach of contract cause of action, and (3) award of judgment on Contractor's mechanic's lien cause of action.  We affirm.[1]

FACTUAL/PROCEDURAL BACKGROUND

This action arises from a dispute over construction on a house.  Contractor filed a mechanic's lien and thereafter sought foreclosure of the mechanic's lien in an action asserting causes of action of breach of contract and unjust enrichment.  Contractor asserted he was entitled to judgment in the sum of $32,137.53, together with interest, costs and attorney's fees.  Farrell answered and counterclaimed, raising various defenses and asserting deficiencies in Contractor's work to support his counterclaims for, among other things, negligence, unjust enrichment, and breach of warranty. 

By consent, the matter was referred to a special referee. At the hearing on the matter, Wilbur Witt, the owner and president of Witt General Contractor's, Inc., testified he was first contacted by Farrell to work on the house in question around the beginning of October 2004.  According to Witt, Farrell was interested in purchasing the home and wanted him to "check out" the house and see "whether or not he could go ahead and purchase it and finish it and put it on the market" to make a profit.  Based on his evaluation, Witt estimated it would cost between $80,000 and $100,000 to repair the home.  Witt stated his estimation was just a general overview of the house when he went through it, and he did not know exactly "how bad" the house would be until he got in there.  When asked about his arrangement with Farrell, Witt testified that when his men were on the jobsite, "it was going to be time and material," that he was going to pay for all the subcontractors that he subbed out, and at the end of the project they would "divvy up some of the profits." [2]  Witt denied the parties had a fixed price contract, stating he would never have accepted that because of the potential for unforeseen problems.  When explaining what he meant by his assertion that he was to be paid on a time and material basis, Witt stated the time spent on the job was to be billed at his company's hourly rate for each employee.  When Witt took his general walk-through of the property, he noticed some framing problems, but once he got into the project he found other problems with the house, most notably the trusses.  The problems with the trusses then caused significant other problems throughout the house.  Witt maintained he could not have known about these problems when he talked with Farrell about the project in October, as he did not have the truss diagrams at that time.

Contractor began working on the home on December 7, 2004.  In order to provide money for the work, an account was opened by Farrell at a local bank with Farrell and Witt's names on it.  Farrell initially wired $25,000 into the account and Contractor would pay bills from the account as needed, calling Farrell when the account would get low so that Farrell could wire more money.  The parties agreed that Farrell deposited a total of $115,000 into the account for construction of the home.  Toward the end of the project, Farrell informed Witt that he could not put any more money into the house.  Because there were outstanding bills, Witt borrowed $20,000 on a line of credit and put the money in the account for payment of these bills.  Around the middle of May 2005, Contractor had a final inspection on the home and obtained a certificate of occupancy.  According to Witt, the home still needed some touch-up, clean-up and repair work, but Farrell withdrew the remaining money from the account and prevented Contractor from going on the job site to finish the work.  The money Farrell removed from the account included over $4,000 of the unspent portion of the line of credit money Witt had provided.

Included within the cost of the project was labor provided by two of Witt's employees.  Witt acknowledged that he billed them at a rate of $45 an hour for the project, and what he billed for their labor was higher than what the employees were actually paid. Witt explained that $45 was the rate he billed for a "time and material" job, and that this allowed him to cover his overhead and profit.  He noted his overhead included workers' compensation and liability insurance, as well as fuel costs, his own salary and "everything else it takes to operate a business."  Witt stated $45 was his going rate for any customer.

Farrell testified that he asked Witt to look at the house and let him know what he thought it would take to finish the construction.  He stated Witt informed him he could complete the house for between $80,000 and $100,000, closer to $100,000 if he wanted certain upgrades.  According to Farrell, the parties had a verbal contract.  He claimed it was a fixed price contract, where Witt would complete the house for between $80,000 and $100,000.  When they had already spent $110,000 and Witt asked for $5,000 more, Farrell agreed but told Witt that he would put no more into the project.  Farrell changed the locks on the house, locking out Witt, when Witt failed to complete the house within a promised two week period.  Farrell acknowledged that Witt loaned $20,000 to the project, depositing the money into the account on June 2, 2005.  However, he testified Witt did not tell him about the loan and he thought the remaining money he removed from the account was his.  When asked whether he had an issue with Witt's labor charges of $45 an hour, Farrell stated he did not, asserting that the parties had a fixed price contract.  He further stated he was not concerned with the labor charges "in the least bit, not under the agreed contract." 

Free access — add to your briefcase to read the full text and ask questions with AI

Related

I'On, L.L.C. v. Town of Mt. Pleasant
526 S.E.2d 716 (Supreme Court of South Carolina, 2000)
Lafaye v. Timmerman
502 S.E.2d 920 (Court of Appeals of South Carolina, 1998)
Roberts v. Gaskins
486 S.E.2d 771 (Court of Appeals of South Carolina, 1997)
T.W. Morton Builders Inc. v. Von Buedingen
450 S.E.2d 87 (Court of Appeals of South Carolina, 1994)
Stanley Smith & Sons v. Limestone College
322 S.E.2d 474 (Court of Appeals of South Carolina, 1984)
Myrtle Beach Hospital, Inc. v. City of Myrtle Beach
532 S.E.2d 868 (Supreme Court of South Carolina, 2000)
Sentry Engineering & Construction, Inc. v. Mariner's Cay Development Corp.
338 S.E.2d 631 (Supreme Court of South Carolina, 1985)
Zepsa Construction, Inc. v. Randazzo
591 S.E.2d 29 (Court of Appeals of South Carolina, 2004)
Van Ness v. Eckerd Corp.
566 S.E.2d 193 (Court of Appeals of South Carolina, 2002)
Robinson v. Robinson
619 S.E.2d 425 (Supreme Court of South Carolina, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Witt General Contractors v. Farrell, Counsel Stack Legal Research, https://law.counselstack.com/opinion/witt-general-contractors-v-farrell-scctapp-2011.