Heavy Equipment Movers and Installation, LLC v. Calgon Carbon Corporation

CourtDistrict Court, S.D. Mississippi
DecidedJuly 30, 2025
Docket1:24-cv-00061
StatusUnknown

This text of Heavy Equipment Movers and Installation, LLC v. Calgon Carbon Corporation (Heavy Equipment Movers and Installation, LLC v. Calgon Carbon Corporation) is published on Counsel Stack Legal Research, covering District Court, S.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heavy Equipment Movers and Installation, LLC v. Calgon Carbon Corporation, (S.D. Miss. 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF MISSISSIPPI SOUTHERN DIVISION

HEAVY EQUIPMENT MOVERS AND INSTALLATION, LLC PLAINTIFF

v. CAUSE NO. 1:24CV61-LG-RPM

CALGON CARBON CORPORATION DEFENDANT

MEMORANDUM OPINION AND ORDER CONCERNING THE PARTIES’ MOTIONS FOR SUMMARY JUDGMENT

Plaintiff Heavy Equipment Movers and Installation, LLC, (“HEMI”) filed this lien enforcement action against Calgon Carbon Corporation pursuant to Miss. Code. Ann. § 85-7-403. It now seeks summary judgment that the principal amount due on the lien is $5,071,883.87, and that it is entitled to pre- and post-judgment interest and attorney’s fees. In the alternative, it seeks partial summary judgment that the principal amount due is at least $3,000,000.00. Defendant Calgon has also filed a [71] Motion for Summary Judgment in which it asks the Court to reduce the amount of HEMI’s lien “to any part of HEMI’s Subcontract price that remains unpaid.” Def.’s Mot. [71] at 4. After reviewing the submissions of the parties, the record in this matter, and the applicable law, the Court finds that HEMI’s [60] Motion should be denied, and Calgon’s [71] Motion should be granted in part and denied in part.1

1 Calgon filed a [66] Memorandum in Opposition to HEMI’s Motion, and HEMI filed a [82] Memorandum in Opposition to Calgon’s Motion, but they did not file a separate response as required by the Local Rules. See L. U. Civ. R. 7(b)(4) (“Counsel for respondent must, within 14 days after service of movant’s motion and memorandum brief, file a response and memorandum brief in support of the BACKGROUND HEMI entered into a Revised Subcontract Agreement with general contractor O’Neal Constructors, LLC,2 “to furnish labor, services, materials, and equipment for

the piping and mechanical scope of work” on the Calgon Carbon G-Line Expansion Project. Compl. [1-1] at p. 2. The project owner was Defendant Calgon. The original Subcontract price for HEMI’s work was $8,748,669.00, but O’Neal approved change orders that increased the price to $10,705,718.43. O’Neal has paid HEMI a total of $10,563,483.13. However, HEMI asserts that it was “required to perform millions of dollars of extensive work outside its original Subcontract scope and to expend hundreds of thousands of dollars in additional costs to procure materials

and equipment that the Subcontract explicitly stated O’Neal or others would provide.” Id. at 4. A dispute arose between O’Neal and HEMI concerning the amount owed to HEMI for its work on the project, so HEMI filed an arbitration complaint against O’Neal. On November 29, 2023, HEMI and O’Neal entered into a partial settlement agreement in which O’Neal agreed to pay $1,454,548,40.3 On March 19, 2024,

response.”). It was not necessary for the Court to consider Calgon’s Memorandum because, as explained infra, HEMI did not meet its initial summary judgment burden. The Court has considered HEMI’s Memorandum, but Counsel for both HEMI and Calgon are instructed to comply with the Local Rules in future filings.

2 The Court denied Calgon’s [20] Motion for Leave to File a Third-Party Complaint against O’Neal for subrogation.

3 The parties further agreed, “Nothing in this Agreement shall be deemed a presumption, a concession, or an admission by any Party of any fault, liability, or HEMI and O’Neal then entered into a final settlement agreement, in which O’Neal agreed to pay HEMI an additional $3,500,000, plus $300,000 in interest. Final Settlement [49-3] at 2.4 In May 2024, O’Neal claimed insolvency and stopped

making payments pursuant to the settlement agreements. HEMI filed a motion asking the arbitration panel to convert the parties’ settlement agreements to an arbitration award, but its motion was denied. HEMI then filed a second arbitration complaint against O’Neal for breach of the settlement agreements, but O’Neal filed a Chapter 7 bankruptcy petition before an arbitration hearing could be held. HEMI asserts that it “has no reasonable expectation of any further payment from O’Neal.” HEMI Mem. [82] at 17.

In addition to its efforts to recover payment from O’Neal, HEMI filed a $6,256,867.00 lien on Calgon’s property on August 18, 2023. HEMI filed an amended lien in the amount of $5,907,809.815 after it received additional payments from O’Neal. On January 31, 2024, HEMI filed the present lawsuit against Calgon for enforcement and foreclosure of its lien. It demands an in rem judgment on Calgon’s property in the amount of $5,907,809.81 in addition to pre-judgment

interest, post-judgment interest, statutory penalties under the Prompt Pay Act,

wrongdoing as to any facts, claims, or defenses . . . .” Partial Settlement [49-2] at 4– 5.

4 Like the partial settlement agreement, the final agreement contained a clause in which the parties denied liability and agreed that the settlement did not constitute an admission of wrongdoing on the part of either party.

5 HEMI admits that O’Neal made an additional payment after the lien was amended, but it has not reduced the lien to account for that payment. attorney’s fees and expenses, and costs.6 Calgon counters that Miss. Code Ann. § 85-7-403 prohibits HEMI from including overtime, delay, and other similar damages in its lien on Calgon’s

property. Thus, it claims that HEMI’s lien should be reduced to $142,235.30, which is the adjusted value of the Subcontract ($10,705,718.43) minus payments O’Neal made to HEMI ($10,563,483.13). DISCUSSION I. SUMMARY JUDGMENT STANDARD A motion for summary judgment may be filed by any party asserting that there is no genuine issue of material fact, and that the movant is entitled to prevail

as a matter of law on any claim. Fed. R. Civ. P. 56. The movant bears the initial burden of identifying those portions of the pleadings and discovery on file, together with any affidavits, which it believes demonstrate the absence of a genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 325 (1986). “If the moving party fails to meet this initial burden, the motion must be denied, regardless of the nonmovant’s response. If the movant does, however, meet this burden, the

nonmovant must go beyond the pleadings and designate specific facts showing that there is a genuine issue for trial.” Littlefield v. Forney Indep. Sch. Dist., 268 F.3d 275, 282 (5th Cir. 2001).

6 Mr. Ahern states, “HEMI did not agree to release Calgon Carbon [when it settled with O’Neal]. HEMI’s lien claim remained in place, this action—filed in January 2024—remained pending, and HEMI did not release Calgon Carbon, its mechanic’s lien or this litigation in any way.” Ahern Decl. [82-1] at ¶15. II. MISSISSIPPI’S STATUTE ALLOWING LIENS FOR LABOR, SERVICES, OR MATERIALS PROVIDED FOR THE IMPROVEMENT OF REAL ESTATE

Courts are required to apply the plain meaning of a Mississippi statute if its language is clear and unambiguous. Watson v. Oppenheim, 301 So. 3d 37, 41 (Miss. 2020). “Mississippi law mandates that ‘all words and phrases contained in the statutes are used according to their common and ordinary meaning . . . .’” Id. at 41– 42 (quoting Lawson v. Honeywell Int’l, Inc., 75 So. 3d 1024, 1027 (Miss. 2011)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Littlefield v. Forney Independent School District
268 F.3d 275 (Fifth Circuit, 2001)
Mumblow v. Monroe Broadcasting, Inc.
401 F.3d 616 (Fifth Circuit, 2005)
Arismendez v. Nightingale Home Health Care, Inc.
493 F.3d 602 (Fifth Circuit, 2007)
Paz v. Brush Engineered Materials, Inc.
555 F.3d 383 (Fifth Circuit, 2009)
Provident Financial, Inc. v. Strategic Energy, L.L
404 F. App'x 835 (Fifth Circuit, 2010)
Burwell v. South Carolina National Bank
340 S.E.2d 786 (Supreme Court of South Carolina, 1986)
Sea Pines Co. v. Kiawah Island Co., Inc.
232 S.E.2d 501 (Supreme Court of South Carolina, 1977)
Regions Bank v. Schmauch
582 S.E.2d 432 (Court of Appeals of South Carolina, 2003)
Ellie, Inc. v. Miccichi
594 S.E.2d 485 (Court of Appeals of South Carolina, 2004)
O'Neal v. Carolina Farm Supply of Johnston, Inc.
309 S.E.2d 776 (Court of Appeals of South Carolina, 1983)
Sentry Engineering & Construction, Inc. v. Mariner's Cay Development Corp.
338 S.E.2d 631 (Supreme Court of South Carolina, 1985)
Erb Lumber Co. v. Homeowner Construction Lien Recovery Fund
522 N.W.2d 917 (Michigan Court of Appeals, 1994)
Brown v. Brown
574 So. 2d 688 (Mississippi Supreme Court, 1990)
Erie Insurance v. Winter Construction Co.
713 S.E.2d 318 (Court of Appeals of South Carolina, 2011)
Patsystems (Na) LLC v. the Trend Exchange, Inc.
695 F. App'x 206 (Ninth Circuit, 2017)
Gregory G. Nethery v. CapitalSouth Partners Fund II, L.P.
257 So. 3d 270 (Mississippi Supreme Court, 2018)
Lillian Smith v. Travelers Casualty Ins. Co.
932 F.3d 302 (Fifth Circuit, 2019)
Lawson v. Honeywell International, Inc.
75 So. 3d 1024 (Mississippi Supreme Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Heavy Equipment Movers and Installation, LLC v. Calgon Carbon Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heavy-equipment-movers-and-installation-llc-v-calgon-carbon-corporation-mssd-2025.