Village of Doniphan v. Starostaka Group Unlimited

CourtNebraska Court of Appeals
DecidedOctober 21, 2014
DocketA-13-658
StatusPublished

This text of Village of Doniphan v. Starostaka Group Unlimited (Village of Doniphan v. Starostaka Group Unlimited) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Village of Doniphan v. Starostaka Group Unlimited, (Neb. Ct. App. 2014).

Opinion

Decisions of the Nebraska Court of Appeals 464 22 NEBRASKA APPELLATE REPORTS

handguns were designed or had the ability to expel a projectile by the action of the explosive black gunpowder. Clearly, the evidence was sufficient for the jury to find Tharp guilty of both counts of felon in possession of a firearm. This assignment of error is without merit. CONCLUSION In conclusion, Tharp failed to preserve the issue of the motion to suppress for appellate review, and given the plain language of § 28-1201, the evidence presented at trial was suf- ficient for the jury to convict Tharp of two counts of felon in possession of a firearm. Tharp’s assignments of error are with- out merit, and as such, we affirm. Affirmed.

Village of Doniphan, a municipal corporation, appellant, v.Starostka Group Unlimited, Inc., a Nebraska corporation, appellee. ___ N.W.2d ___

Filed October 21, 2014. No. A-13-658.

1. Directed Verdict: Appeal and Error. In reviewing a trial court’s ruling on a motion for directed verdict, an appellate court must treat the motion as an admis- sion of the truth of all competent evidence submitted on behalf of the party against whom the motion is directed; such being the case, the party against whom the motion is directed is entitled to have every controverted fact resolved in its favor and to have the benefit of every inference which can reasonably be deduced from the evidence. 2. Directed Verdict: Evidence. A directed verdict is proper at the close of all the evidence only when reasonable minds cannot differ and can draw but one con- clusion from the evidence, that is, when an issue should be decided as a matter of law. 3. Judgments: Verdicts. On a motion for judgment notwithstanding the verdict, the moving party is deemed to have admitted as true all the relevant evidence admitted that is favorable to the party against whom the motion is directed, and, further, the party against whom the motion is directed is entitled to the benefit of all proper inferences deducible from the relevant evidence. 4. ____: ____. To sustain a motion for judgment notwithstanding the verdict, the court resolves the controversy as a matter of law and may do so only when the facts are such that reasonable minds can draw but one conclusion. Decisions of the Nebraska Court of Appeals VILLAGE OF DONIPHAN v. STAROSTKA GROUP UNLIMITED 465 Cite as 22 Neb. App. 464

5. Motions for New Trial: Appeal and Error. A motion for new trial is addressed to the discretion of the trial court, whose decision will be upheld in the absence of an abuse of discretion. 6. Verdicts: Juries: Appeal and Error. A jury verdict will not be set aside unless clearly wrong, and it is sufficient if any competent evidence is presented to the jury upon which it could find for the successful party.

Appeal from the District Court for Hall County: Teresa K. Luther, Judge. Affirmed. Austin L. McKillip, of Cline, Williams, Wright, Johnson & Oldfather, L.L.P., and James H. Truell, of Truell, Murray & Associates, for appellant. Larry E. Welch, Jr., of Welch Law Firm, P.C., for appellee. Irwin, Moore, and Pirtle, Judges. Pirtle, Judge. INTRODUCTION The Village of Doniphan, a municipal corporation, appeals from an order of the district court for Hall County, which entered judgment upon the verdict of the jury finding that Doniphan’s breach of contract claim against Starostka Group Unlimited, Inc. (Starostka Group), a Nebraska corporation, was barred by the statute of limitations. Doniphan contends that the trial court erred in failing to grant its motion for directed verdict and erred in failing to grant its motion for judgment notwithstanding the verdict or, in the alternative, a motion for new trial. Based on the reasons that follow, we affirm the judg- ment of the district court. BACKGROUND This action arises from a breach of contract claim brought by Doniphan against Starostka Group. Specifically, in August 2005, Starostka Group entered into an agreement with Doniphan to construct a sanitary sewer system and water lines according to prescribed specifications for a new residential development known as Hoffman subdivision. In the spring of 2006, the subdivision experienced significant drainage and standing water problems which caused sinking and damage to Decisions of the Nebraska Court of Appeals 466 22 NEBRASKA APPELLATE REPORTS

the paving above the sanitary sewer system and water lines constructed by Starostka Group. On February 11, 2010, Doniphan commenced this action to recover damages, alleging that Starostka Group breached the construction contract by failing to comply with the speci- fications for the design and construction of the project. In its amended answer filed October 21, Starostka Group raised the affirmative defense that Doniphan’s claims were barred by the applicable statute of limitations. Starostka Group filed a motion for summary judgment, which the trial court overruled. The court found that the sub- stantial completion date of the project presented a genuine issue of material fact. The case proceeded to a jury trial on the issue of when sub- stantial completion of the project occurred, thereby determining whether Doniphan’s claim against Starostka Group was barred by the statute of limitations. The evidence presented showed that Doniphan and Starostka Group entered into a written con- struction contract whereby Starostka Group agreed to complete the work necessary for “[t]he installation of water and sewer mains for the proposed [s]ubdivision as well as the earthwork needed to bring the site to the proposed elevations.” The con- tract listed a start date in August 2005, listed the total price for Starostka Group’s work on the project as $197,475.34, and provided for progress payments of the total contract price as the work was completed. The contract named JEO Consulting Group, Inc. (JEO Consulting), as the project engineer and authorized it to act as Doniphan’s representative. The contract specifically stated that JEO Consulting would act as the initial interpreter of the requirements of the contract and the judge of the acceptability of the work thereunder. As such, upon receipt of an application for progress payment from Starostka Group, JEO Consulting inspected the work completed by Starostka Group before it recommended that Doniphan make partial pay- ments under the contract. The contract also addressed the specifications for disin- fection of the water distribution system and required that Starostka Group disinfect the water lines and document that the lines had passed two consecutive bacteriological tests. The Decisions of the Nebraska Court of Appeals VILLAGE OF DONIPHAN v. STAROSTKA GROUP UNLIMITED 467 Cite as 22 Neb. App. 464

contract further provided that separate payment for disinfec- tion and bacteriological testing of the water lines would not be made and that such work is considered subsidiary to the work indicated in the project. On or about August 29, 2005, Starostka Group was given a notice to proceed by Doniphan to construct the project’s sewer system and water lines. At the end of September, Starostka Group submitted its first “Contractor Application for Payment” to JEO Consulting requesting payment in the amount of $142,144.63 for work on the project completed through September 29. At the October 2005 meeting of Doniphan’s board of trust- ees (the Board), Dale Sall, who served as the project engi- neer for JEO Consulting, presented Starostka Group’s payment request for approval by the Board. Upon unanimous approval by the Board, Doniphan issued to Starostka Group a check in the amount requested. On October 31, 2005, Starostka Group submitted its sec- ond “Contractor Application for Payment” to JEO Consulting requesting payment in the amount of $46,163.84 for work on the project completed through October 28.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R & D Properties, LLC v. Altech Const. Co.
776 N.W.2d 493 (Nebraska Supreme Court, 2009)
PIONEER ENTERPRISES, INC. v. Edens
345 N.W.2d 16 (Nebraska Supreme Court, 1984)
Bellino v. McGrath North Mullin & Kratz, PC LLO
738 N.W.2d 434 (Nebraska Supreme Court, 2007)
Lange Industries, Inc. v. Hallam Grain Co.
507 N.W.2d 465 (Nebraska Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Village of Doniphan v. Starostaka Group Unlimited, Counsel Stack Legal Research, https://law.counselstack.com/opinion/village-of-doniphan-v-starostaka-group-unlimited-nebctapp-2014.