City of Gering v. Patricia G. Smith Co.

337 N.W.2d 747, 215 Neb. 174, 1983 Neb. LEXIS 1237
CourtNebraska Supreme Court
DecidedAugust 12, 1983
Docket82-497
StatusPublished
Cited by21 cases

This text of 337 N.W.2d 747 (City of Gering v. Patricia G. Smith Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Gering v. Patricia G. Smith Co., 337 N.W.2d 747, 215 Neb. 174, 1983 Neb. LEXIS 1237 (Neb. 1983).

Opinion

Krivosha, C.J.

The City of Gering, Nebraska, a municipal corporation, appeals from a judgment in the amount of $26,214 entered by the District Court for Scotts Bluff County, Nebraska, in favor of the City of Gering (City). The damages were awarded by the court, a jury having been waived, for alleged defective work performed by the A. C. Smith Company, Inc., for the City, and the City maintains that the award of damages is inadequate. The appellee, Patricia G. Smith Company, a corporation, formerly A. C. Smith Company, Inc. (Smith), has cross-appealed, maintaining *176 that the City, through its engineer, accepted the work with knowledge of the alleged defect and thereby waived any right to damages. In addition, Smith maintains that it is entitled to attorney fees pursuant to the terms of a contract entered into between the City and Smith. The trial court denied such fees. Because we believe that the trial court was in error in regard to the matter of waiver but correct with regard to the matter of attorney fees, we affirm in part and in part reverse.

The facts which give rise, to this action involve the construction of a four-phase outfall sewer system constructed by the City. The planning and construction of the system, which relies upon gravity to move the sewage, began in 1973. Phase I, the lowest part of the system which empties into the Gering sewer lagoons, was completed in 1974. Phase II, which is an extension of phase I and which empties into phase I, was completed in 1975. Phase III, a further extension of the outfall sewer system which empties into phase II, was completed in 1975. Phase IV, the project involved herein, was designed to consist of 1,850 lineal feet of 21-inch sewer main. At its low end phase IV connects to the phase II sewer main,, and at the high end it terminates in an inverse gravity siphon, to which is connected a sewer system built to serve a subdivision known as Pathfinder Subdivision. Also connected to phase IV, but at points in the middle, are sewers serving another subdivision which was added later.

'Each phase of the system was designed and engineered by M. C. Schaff & Associates, Inc. Following the letting of bids, Smith was awarded the project for phase IV at a price of $47,070. The contract entered into between the City and Smith was a mimeographed document prepared by the City, containing several blank lines which were to be filled in by Smith to reflect the dollar figures agreed upon between the parties. No other terms of the contract *177 were subject to negotiation, but were, rather, a part of the bid process.

Certain of the relevant terms of the contract, which apparently were standard provisions for contracts entered into by the City, provided as follows:

“INTERPRETATION OF CONTRACT DOCUMENTS.

“The interpretation of all contract documents and plans, the inspection and approval of all materials and work, and all tests for the determination of guarantee shall be made by the Engineer, or under his direction.”

“TESTING.

“. . . Before final acceptance of the sewers, all parts of the sewers shall be clean, shall comply with all Contract Documents, and shall be in condition acceptable to the Engineer and the proper municipal authorities.”

“DEFENSE COST.

“The Owner and the contractor agree that in the event either of them institutes a law suit against the other under this contract, the plaintiff in such law suit will pay to the defendent [sic] a portion of the defense cost including investigations, engineering fees, attorney fees, expert witness fees, and any other expenses of the defense which may be incurred. Such portion of the defense cost shall bear the same relation to the total defense cost as a dollar amount of the plaintiff claim which were [sic] not sustained by the court, bears to the total dollar amount of the plaintiff’s claim. The plaintiff shall pay such portion of the defense cost to the defendent [sic] within thirty days after the defendent [sic] furnished the plaintiff with an itemized listing of the defense cost incurred.”

Smith finished the construction of the sewer in November of 1976. On December 7, 1976, the engineer, M. C. Schaff & Associates, filed a certificate of completion, which stated as follows: “I hereby certify that Outfall Sewer - Phase IV and Sanitary *178 Sewer District No. 76-S5, providing for construction of sanitary sewer, under the contract between A.C. Smith Company, Inc., Contractor, and the City of Gering, Nebraska, has been fully completed according to the terms and stipulations of said contract, and I recommend that the work be accepted.” The certificate was signed by M. C. Schaff as president of M. C. Schaff & Associates, Inc.

On December 13, 1976, the city council of the City of Gering, by resolution, made the following findings: ‘‘3. The Special Engineer in charge has filed a Certificate that the work has been completed in accordance with the terms of the contract and that he recommends that the City accept the work.

“4. The City of Gering does hereby find that the work has been completed and that the Certificate of Completion is on file and that the City does hereby accept the work.”

The record is without dispute that the sewerline, as built by Smith, had a sag in. it. But for this defect, there were no other complaints about the quality of the materials provided or workmanship done.

It further appears to be established without dispute that at least one construction engineer working on the project for Schaff knew that the sag existed before the engineer approved the project and the city council accepted it. He testified that others in the Schaff firm surveyed the completed project and that elevations indicating the sag were put on a set of ‘‘as-built plans” drawn up before the certificate of completion was submitted to the city council. Sometime after June 8, 1978, the City of Gering employed Wells Engineers, Inc., to review a plan prepared by Schaff for rebuilding phase IV to correct the sag. During the course of the trial, a dispute developed as to how the sag could have been more easily repaired and what should be the proper measure of damages. However, because we believe that this case must be disposed of on the issue of waiver, *179 we need not consider the matter of damages.

The law is clear and generally without dispute that “An express or implied acceptance of work as in compliance with a building contract operates as a waiver of defective performance, but this rule is inapplicable where the acceptance was under protest or induced by fraud, or where the defects were latent and unknown to the owner.” 17A C.J.S. Contracts § 514(2)a at 840 (1963). As we noted in Peckham v. Deans, 186 Neb. 190, 192, 181 N.W.2d 851, 853 (1970): “Ordinarily, the acceptance of performance after a default in performance waives the right to rely upon the default.” See, also, Wegner v. West, 169 Neb. 546, 100 N.W.2d 542 (1960).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Troy v. RFD-TV The Theater, LLC
498 S.W.3d 550 (Court of Appeals of Tennessee, 2016)
Stewart v. Bennett
727 N.W.2d 424 (Nebraska Supreme Court, 2007)
Nebraska Public Employees Local Union 251 v. Otoe County
595 N.W.2d 237 (Nebraska Supreme Court, 1999)
World Radio Laboratories, Inc. v. Lybrand
538 N.W.2d 501 (Nebraska Court of Appeals, 1995)
Lindsay Manufacturing Co. v. Universal Surety Co.
519 N.W.2d 530 (Nebraska Supreme Court, 1994)
Lange Industries, Inc. v. Hallam Grain Co.
507 N.W.2d 465 (Nebraska Supreme Court, 1993)
Ducheneaux v. Miller
488 N.W.2d 902 (South Dakota Supreme Court, 1992)
Chambers-Dobson, Inc. v. Squier
472 N.W.2d 391 (Nebraska Supreme Court, 1991)
Nichols v. Ach
447 N.W.2d 220 (Nebraska Supreme Court, 1989)
Village of Pawnee v. Azzarelli Construction Co.
539 N.E.2d 895 (Appellate Court of Illinois, 1989)
Equilease Corp. v. Neff Towing Service, Inc.
418 N.W.2d 754 (Nebraska Supreme Court, 1988)
Tetherow v. Wolfe
392 N.W.2d 374 (Nebraska Supreme Court, 1986)
State Ex Rel. Toledo v. Bockmann
355 N.W.2d 521 (Nebraska Supreme Court, 1984)
Quinn v. GODFATHER'S INVESTMENTS, INC.
348 N.W.2d 893 (Nebraska Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
337 N.W.2d 747, 215 Neb. 174, 1983 Neb. LEXIS 1237, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-gering-v-patricia-g-smith-co-neb-1983.