Board of Regents of the University of Nebraska v. Lueder Construction Co.

433 N.W.2d 485, 230 Neb. 686, 1988 Neb. LEXIS 463
Nebraska Supreme Court·Decided December 23, 1988·No. 87-955·Published·Cited by 38 cases

Opinion

Grant, J.

On April 13, 1984, the appellant, Board of Regents of the University of Nebraska (University), filed this action against Lueder Construction Company (Lueder) for damages premised on breaches of contract and warranty in the construction of the college of pharmacy building at the University of Nebraska Medical Center (UNMC) in Omaha. Lueder acted as general contractor on the project. Insurance Company of North America (INA), Lueder’s performance bond surety for the project, was also named as a defendant. The district court granted INA’s motion for summary judgment, and the University has not appealed that ruling.

The University’s petition alleged two causes of action: (1) that Lueder breached its contract in that the exterior brick walls and the brick supporting structure had not been installed according to plans and specifications; and (2) that Lueder breached its contract in failing to install the number of steel reinforcing bars required in the floor slabs and in failing to posttension the tendons in both the floor slabs and spandrel *688 sections to specification force. Lueder’s answer admitted and denied various factual allegations of the petition and pled that any claim which the University might have against Lueder was “specifically barred by the applicable statutes and periods of limitation for commencement of actions under the laws of the State of Nebraska.”

The trial was bifurcated pursuant to Neb. Rev. Stat. § 25-221 (Reissue 1985) to determine the issues related to Lueder’s statute of limitations defense. After a trial to the court on that issue, the district court for Douglas County held that the “action was brought more than two years after the existence of facts which would have, if pursued, led to the discovery of [the University’s] causes of action” and was, therefore, barred by the applicable statute of limitations, Neb. Rev. Stat. § 25-223 (Reissue 1985). The district court further ordered that Lueder’s third-party action against The Prescon Corporation (Prescon), seeking indemnification for all sums adjudged against Lueder, be dismissed.

The University timely appealed and in this court claims the district court erred (1) in finding that the action was barred by the statute of limitations, when the University, exercising reasonable diligence under the circumstances, did not discover facts which reasonably led to the discovery of the breach giving rise to its first cause of action until summer 1983, nor did it discover facts which reasonably led to the discovery of the breach giving rise to the second cause of action until February 20, 1984; (2) in not finding that the University exercised reasonable diligence to discover the defects, when there was sufficient evidence presented at trial to support such finding; and (3) in holding that a reasonable investigation in 1980 or 1981 should have led to the discovery of the defects set out in the plaintiff’s two causes of action. We affirm.

The record shows that on May 6, 1974, the University contracted with architects Wilscam Mullins Birge, Inc. (Wilscam), for the design and continued inspection of construction of the college of pharmacy building. Wilscam hired Walter D. Rudeen and Associates, Inc. (Rudeen), to perform the structural engineering design work for the building. See Board of Regents v. Wilscam Mullins Birge, ante *689 p. 675, 433 N.W.2d 478 (1988). On May 19, 1975, the University entered into a written owner-contractor agreement with Lueder for Lueder to construct the building. Lueder contracted with Prescon to prepare shop drawings for the project.

The project was substantially completed on October 11, 1976, and the building was accepted by the University on that date. During the following year, University personnel monitored the new building for deficiencies. In March 1977, University personnel observed cracks beginning to form in the north and south exterior brick walls of the west section of the building. In preparation for a 1-year review of the building, George Money, director of planning and construction at UNMC, prepared a “punch list” of deficiencies to be reviewed by Wilscam and Lueder. The punch list, dated September 27, 1977, refers to several instances of brick cracking:

24. South wall has a crack at the east end of the west window, starting at the window sill and going up about half the window height, coming up about seven blocks (about half way up).
25. The overhang at the south wall west end. There is a crack that starts in the corner third brick up and then goes to the west up to the eighth brick.
26. Another crack on the south wall west side of the attrium [sic] that is up 18 blocks above the start of square block and over six blocks. Mortar joint missing on the east wall fifth course above the dock head about two blocks west of the television camera.
28. On the north side the brick is broken out the fourth row down from the square brick course on the west end of the atrium. The west end of the atrium up five of the square brick crack starts and goes over half brick and then up the tile over the next joint. Goes on up about eight or nine courses.

On September 27, 1977, representatives of the University, Lueder, and Wilscam met to conduct the 1-year review of the building. The punch list items related to cracking were discussed, and it was agreed that Wilscam would perform a *690 further investigation of the cracks. The University asked Wilscam to provide a written report on the matter.

Structural engineer Walter Rudeen and Wilscam’s field architect, Frederick Fast, visited the site in October 1977. During this visit, Rudeen investigated only one horizontal crack in the north wall and did not examine several diagonal “stairstep” cracks in the mortar, which had been brought to Wilscam’s attention at the September 27,1977, meeting. Walter Rudeen determined that the horizontal crack was caused by downward movement of a brick support angle, which had resulted from construction error. The Wilscam firm, in turn, orally reported to the University about the cause of the horizontal crack. Wilscam never provided the University with a written report on the causes of cracking and never provided any explanation as to the cause of the stairstep diagonal cracks. As architect Donald Mullins testified, “[T]he university did not make a big deal of the cracks in the walls.” Wilscam orally advised the University in 1977 that the cracks were superficial and that they should be monitored and caulked to prevent further damage to the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Board of Regents of the University of Nebraska v. Lueder Construction Co., 433 N.W.2d 485, 230 Neb. 686, 1988 Neb. LEXIS 463 (Neb. 1988).

433 N.W.2d 485 (Board of Regents of the University of Nebraska v. Lueder Construction Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Wolfson v. Regency Homes
Nebraska Court of Appeals, 2025
McCaulley v. C L Enters.
309 Neb. 141 (Nebraska Supreme Court, 2021)
Adams v. Manchester Park
291 Neb. 978 (Nebraska Supreme Court, 2015)
Andres v. McNeil Co., Inc.
707 N.W.2d 777 (Nebraska Supreme Court, 2005)
Grassmueck v. American Shorthorn Ass'n
365 F. Supp. 2d 1042 (D. Nebraska, 2005)
St. Paul Fire & Marine Insurance v. Touche Ross & Co.
507 N.W.2d 275 (Nebraska Supreme Court, 1993)
Murphy v. Spelts-Schultz Lumber Co.
481 N.W.2d 422 (Nebraska Supreme Court, 1992)
Economy Housing Co., Inc. v. Rosenberg
475 N.W.2d 899 (Nebraska Supreme Court, 1991)
Sherbeck v. Schaper
442 N.W.2d 364 (Nebraska Supreme Court, 1989)