Grand Island School District 2 v. Celotex Corp.

279 N.W.2d 603, 203 Neb. 559, 26 U.C.C. Rep. Serv. (West) 939, 1979 Neb. LEXIS 886
CourtNebraska Supreme Court
DecidedMay 29, 1979
Docket42052
StatusPublished
Cited by99 cases

This text of 279 N.W.2d 603 (Grand Island School District 2 v. Celotex Corp.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grand Island School District 2 v. Celotex Corp., 279 N.W.2d 603, 203 Neb. 559, 26 U.C.C. Rep. Serv. (West) 939, 1979 Neb. LEXIS 886 (Neb. 1979).

Opinion

White, J.

Appellant, Grand Island School District #2, brought this action to recover damages arising from a leaky roof installed on the Barr Junior High School building. The appellees, defendants below, were sued un *561 der various theories of liability. Those involved in the design, supervision, construction, or supply of materials for the building or the roof were Johnson Builders, Inc. (hereinafter Johnson), Shaver and Company (hereinafter Shaver), Krause Roofing and Sheet Metal, Inc. (hereinafter Krause), and The Celotex Corporation (hereinafter Celotex). Johnson entered into a written contract with the school district as general contractor on the building. Johnson was to construct the building in accordance with the specifications of Shaver, the architect. Shaver also had the duty to inspect the work at intermittent stages. Johnson subcontracted the roofing work to Krause. Celotex supplied to Krause the roofing material known as the “Bond Ply” system. Also joined as defendants were: The Travelers Indemnity Company, which issued a limited guaranty bond on the roof; the St. Paul Fire and Marine Insurance Company, surety for Johnson under a performance and maintenance bond; and the Jim Walter Corporation, parent corporation to Celotex.

The defendant Krause demurred to plaintiff’s amended petition, alleging it did not state facts sufficient to constitute a cause of action. The sustaining of the demurrer was not assigned as error in this court nor was it discussed in the plaintiff’s extensive brief or its reply brief. The order sustaining the demurrer is therefore affirmed. Consideration of the cause in this court is generally limited to errors assigned and discussed. Rule 8 a 2 (3), Revised Rules of the Supreme Court, 1977; Cofer v. Perkins, 199 Neb. 327, 258 N. W. 2d 807.

Each of the other defendants moved for summary judgment on the basis that the various statutes of limitations had run. The District Court sustained the motions. We affirm.

Construction on Barr Junior High School began in 1966. In 1967, the roof on the building was completed. The building was occupied in the summer of *562 that year and all construction was completed shortly after classes started in the fall. The first leaks in the roof appeared in late 1968. Then, according to the plaintiff, there began a cycle of complaints by the plaintiff to the defendants and independent parties, repairs to the roof which alleviated the leaks for a period of months, and then the appearance of new leaks. This cycle continued until July 1976 when an engineering consultant took samples of the roof and related to the school board its opinion that the insulation boards beneath the roofing membrane had not been taped; that the insulation and membrane were not in compliance with specifications; that there was little or no adhesion between the insulation boards and the underlying concrete deck; and that the roof had not been properly vented. This suit was instituted a month later on August 4, 1976, and about that same time the school board authorized replacement of the old roof. Other evidence of careless and improper installation was allegedly found when the old roof was removed.

The plaintiff alleged that the defendants, Johnson and Shaver, breached implied warranties and their written contracts with the plaintiff, and that they were negligent in failing to supervise and inspect the installation of the roof to insure that it would meet the contract specifications. Unless a more specific statute of limitations is applicable, actions in tort and actions upon implied contracts, (which would include implied warranty) must be brought within 4 years. § 25-206 and 25-207 (3), R. R. S. 1943. Actions on written contracts can only be brought within 5 years. § 25-205, R. R. S. 1943. The arguments of the plaintiff raise the question of when these statutes of limitations start to run.

The traditional rule is that the statute begins to run as soon as the action accrues, and the cause is said to accrue when the aggrieved party has the right to institute and maintain a suit. In a contract *563 action this means as soon as breach occurs, and in tort, as soon as the act or omission occurs. These rules would apply even though the plaintiff was then ignorant of the injury sustained or could not ascertain the amount of his damages. See 51 Am. Jur. 2d, Limitation of Actions, § 109, p. 681.

In 1976, the Legislature modified this “accrual” rule as it applies to improvements to real property and adopted instead a partial “discovery” rule.

Section 25-223, R. S. Supp., 1978, provides, in part: “Any action to recover damages based on any alleged breach of warranty on improvements to real property or based on any alleged deficiency in the design, planning, supervision, or observation of construction, or construction of an improvement to real property shall be commenced within four years after any alleged act or omission constituting such breach of warranty or deficiency. If such cause of action is not discovered and could not be reasonably discovered within such four-year period, or within one year preceding the expiration of such four-year period, then the cause of action may be commenced within two years from the date of such discovery or from the date of discovery of facts which would reasonably lead to such discovery, whichever is earlier.” (Emphasis supplied.) The statute’s effective date was July 10, 1976, which was prior to the date on which this suit was commenced.

“ ‘It is well settled that it is competent for the legislature to change statutes prescribing limitations to actions, and that the one in force at the time suit is brought is applicable to the cause of action. The only restriction on the exercise of this power is, that the legislature cannot remove a bar or limitation which has already become complete, and that no limitation shall be made to take effect on existing claims without allowing a reasonable time for parties to bring action before these claims are absolutely barred by a new enactment.’ In this case the *564 court held that there was a reasonable and sufficient time given to bring the action between the time of the passage of the act and the time when it took effect.” Educational Service Unit No. 3 v. Mammel, O., S., H. & S., Inc., 192 Neb. 431, 222 N. W. 2d 125, citing Horbach v. Miller, 4 Neb. 31 (1875).

It is clear that if the contract and warranty actions against Johnson and Shaver had accrued at the time of the breach, they were barred by sections 25-205 and 25-206, R. R. S. 1943, prior to the passage of section 25-223, R. S. Supp., 1978. The passage of the latter act would be ineffective to revive those actions.

The applicability of section 25-223, R. S. Supp., 1978, to the cause of action in negligence is less clear, for this court had, prior to its passage, already adopted a discovery rule in certain classes of tort cases. The rule was first applied in workmen’s compensation cases alleging latently appearing industrial diseases. The statute was said to run, not from the time of the initial injury, but from the date of discovery of a compensable disability. See Dryden v. Omaha Steel Works, 148 Neb. 1, 26 N. W. 2d 293.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Susman v. Kearney Towing & Repair Ctr.
310 Neb. 910 (Nebraska Supreme Court, 2022)
Walz v. Harvey
28 Neb. Ct. App. 7 (Nebraska Court of Appeals, 2020)
Carol Marmo v. Tyson Fresh Meats
457 F.3d 748 (Eighth Circuit, 2006)
Joswick v. Chesapeake Mobile Homes, Inc.
747 A.2d 214 (Court of Special Appeals of Maryland, 2000)
Nebraska Popcorn, Inc. v. Wing
602 N.W.2d 18 (Nebraska Supreme Court, 1999)
Kratochvil v. Motor Club Ins. Ass'n
588 N.W.2d 565 (Nebraska Supreme Court, 1999)
Cavenaugh v. City of Omaha
567 N.W.2d 592 (Nebraska Court of Appeals, 1997)
Durrett v. Leading Edge Products, Inc.
965 F. Supp. 280 (D. Connecticut, 1997)
Hroch v. Farmland Industries, Inc.
548 N.W.2d 367 (Nebraska Court of Appeals, 1996)
Butler v. Bantz (In re Howe Grain, Inc.)
176 B.R. 515 (D. Nebraska, 1994)
Upah v. Ancona Bros. Co.
521 N.W.2d 895 (Nebraska Supreme Court, 1994)
State v. Hirsch
511 N.W.2d 69 (Nebraska Supreme Court, 1994)
Opinion No. (1993)
Nebraska Attorney General Reports, 1993
State v. Hirsch
510 N.W.2d 534 (Nebraska Court of Appeals, 1993)
Ed Miller & Sons, Inc. v. Earl
502 N.W.2d 444 (Nebraska Supreme Court, 1993)
State of Minn. Ex Rel. Hove v. Doese
501 N.W.2d 366 (South Dakota Supreme Court, 1993)
Givens v. Anchor Packing, Inc.
466 N.W.2d 771 (Nebraska Supreme Court, 1991)
Hillcrest Country Club v. N.D. Judds Co.
461 N.W.2d 55 (Nebraska Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
279 N.W.2d 603, 203 Neb. 559, 26 U.C.C. Rep. Serv. (West) 939, 1979 Neb. LEXIS 886, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grand-island-school-district-2-v-celotex-corp-neb-1979.